Arizona Statutes

§ 32-1184 — Interruption of performance of construction contract; damages; termination of contract

Arizona·Title 32 Arizona Revised Statutes·Ch. 10 CONTRACTORS·Art. 5 Prompt Pay
A.A contractor licensed under this chapter may interrupt the performance of a construction contract without penalty or liability for breach of contract if any applicable law or rule requires the cessation of work or the contractor encounters any hazardous substance or hazardous material which is required to be removed or contained by any applicable law or rule and either of the following apply:
1.Any applicable law or rule prohibits the contractor from proceeding to remove or contain the hazardous material or hazardous substance unless the contractor is duly licensed and the contractor is not so licensed.
2.The removal or containment of the hazardous material or hazardous substance cannot be accomplished without a cessation of work.
B.A contractor licensed under this chapter whose w

Free access — add to your briefcase to read the full text and ask questions with AI

Arizona § 32-1184 (Interruption of performance of construction contract; damages; termination of contract) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Nearby Sections

15
View on official source ↗