§ 28-7364 — Design-build criteria

Arizona § 28-7364
JurisdictionArizona
Title 28Arizona Revised Statutes
Ch. 20STATE HIGHWAYS AND ROUTES
Art. 13Alternative Contracting Procedures

This text of Arizona § 28-7364 (Design-build criteria) is published on Counsel Stack Legal Research, covering Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ariz. Rev. Stat. Ann. § 28-7364 (2026).

Text

The department shall use the following criteria as the minimum basis for determining when to use the design-build method of project delivery:

1.The extent to which it can adequately define the project requirements.
2.The time constraints for delivery of the project.
3.The capability and experience of potential teams with the design-build method of project delivery.
4.The suitability of the project for use of the design-build method of project delivery in the areas of time, schedule, costs and quality.
5.The capability of the department to manage the project, including the employment of experienced personnel or outside consultants.
6.The capability of the department to oversee the project with persons who are familiar with the design-build method of project delivery.
7.Other c

Free access — add to your briefcase to read the full text and ask questions with AI

Nearby Sections

15
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Arizona § 28-7364, Counsel Stack Legal Research, https://law.counselstack.com/statute/az/28-7364.