§ 27-952 — Notice of complete, incomplete or denied plan
Arizona § 27-952
JurisdictionArizona
Title 27Arizona Revised Statutes
Ch. 5MINED LAND RECLAMATION
Art. 3Exploration Operations Reclamation Plan
This text of Arizona § 27-952 (Notice of complete, incomplete or denied plan) is published on Counsel Stack Legal Research, covering Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Bluebook
Ariz. Rev. Stat. Ann. § 27-952 (2026).
Text
A.The state mine inspector shall notify the operator that a reclamation plan is administratively complete or incomplete within thirty days after receiving the plan.
B.If the inspector notifies the operator that a plan is incomplete or denied, the inspector shall include a written explanation stating the reasons for denial including recommendations for correcting incomplete or unacceptable parts of the plan consistent with the requirements of this chapter. The operator must refile the corrected plan within ninety days after notification that the previous plan was incomplete or denied or within a time frame mutually agreed on between the operator and the state mine inspector that would not materially affect the safety of employees or cause undue hardship on an operator.
Free access — add to your briefcase to read the full text and ask questions with AI
Nearby Sections
15
§ 27-101
Definitions§ 27-1021
Inspections§ 27-1022
Compliance orders§ 27-1024
Injunctive relief; civil penalties§ 27-1025
Agency order; appeal§ 27-1026
Violation; classification§ 27-105
Immunity§ 27-106
Duties of Arizona geological survey; mining, mineral and natural resources educational museum§ 27-107
Powers and duties; fund§ 27-108
Publications; depositCite This Page — Counsel Stack
Bluebook (online)
Arizona § 27-952, Counsel Stack Legal Research, https://law.counselstack.com/statute/az/27-952.