A.The state mine inspector must approve any substantial change to an approved reclamation plan as provided by this section before the change is implemented.
B.The owner or operator of the exploration operation or mining unit shall submit a notice of a proposed change to the inspector describing the purpose and scope of the proposed change and whether it constitutes a substantial change to the approved reclamation plan. If the inspector fails to respond within thirty days, the change is considered to be consistent with the operation's or unit's approved reclamation plan.
C.If the inspector determines that the change is substantial the inspector shall:
1.Notify the owner or operator of the decision within fifteen days after receiving the notice.
2.Require the owner or operator to su
Free access — add to your briefcase to read the full text and ask questions with AI
Arizona § 27-927 (Substantial changes to approved reclamation plan; fee) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.
Nearby Sections
15
§ 27-101
Definitions§ 27-1021
Inspections§ 27-1022
Compliance orders§ 27-1024
Injunctive relief; civil penalties§ 27-1025
Agency order; appeal§ 27-1026
Violation; classification§ 27-105
Immunity§ 27-106
Duties of Arizona geological survey; mining, mineral and natural resources educational museum§ 27-107
Powers and duties; fund§ 27-108
Publications; deposit