Arkansas Statutes
§ 23-18-904 — Exceptions to commission jurisdiction
Arkansas·Title 23
(a)If the Arkansas Public Service Commission issues a financing order to a utility pursuant to this section, the commission shall not:
(1)Consider the storm recovery bonds issued pursuant to the financing order to be the debt of the utility other than for federal and state income tax purposes;
(2)Consider the storm recovery charges paid under the financing order to be the revenue of the utility for any purpose;
(3)Consider the storm recovery costs or financing costs specified in the financing order to be the costs of the utility; or (4) Determine any action taken by a utility which is consistent with the financing order to be unjust or unreasonable.
(b)The commission shall not:
(1)Order or otherwise directly or indirectly require a utility to use storm recovery bonds to finance any p
Free access — add to your briefcase to read the full text and ask questions with AI
Arkansas § 23-18-904 (Exceptions to commission jurisdiction) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.
Legislative History
Amended by Act 2021, No. 641,§ 1, eff. 4/12/2021. Acts 2009, No. 729, § 1.
Nearby Sections
15
§ 23-1-101
Definitions§ 23-1-103
Compliance with Acts 1935, No. 324, and rules of commission required - Penalties for noncompliance§ 23-1-106
Penalties cumulative - Recovery of penalty not bar to further penalty or criminal prosecution§ 23-1-108
Jurisdiction and venue of actions§ 23-1-110
Actions tried without jury - Exceptions§ 23-1-111
Copies of official papers as evidence§ 23-1-115
Citizens band radio equipment