§ 23-18-519 — Decision of commission - Modifications of application

Arkansas·Title 23
(a)(1) The Arkansas Public Service Commission shall render a decision upon the record either granting or denying the application as filed or granting it upon such terms, conditions, or modifications of the location, financing, construction, operation, or maintenance of the major utility facility as the commission may deem appropriate.
(2)The record may include by reference the findings of the commission in an energy resource declaration-of-need proceeding that the utility needs additional energy supply resources or transmission resources.
(b)The commission shall not grant a certificate for the location, financing, construction, operation, and maintenance of a major utility facility, either as proposed or as modified by the commission, unless it finds and determines:
(1)(A) The basis of

Free access — add to your briefcase to read the full text and ask questions with AI

Arkansas § 23-18-519 (Decision of commission - Modifications of application) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Sierra Club v. United States Army Corps of Engineers
645 F.3d 978 (Eighth Circuit, 2011)
93 case citations
Hempstead County Hunting Club, Inc. v. Arkansas Public Service Commission
2010 Ark. 221 (Supreme Court of Arkansas, 2010)
10 case citations
Hempstead County Hunting Club, Inc. v. Arkansas Public Service Commission
324 S.W.3d 697 (Court of Appeals of Arkansas, 2009)
7 case citations

Legislative History

Amended by Act 2019, No. 315,§ 2482, eff. 7/24/2019. Amended by Act 2013, No. 1133,§ 6, eff. 8/16/2013. Acts 1973, No. 164, § 9; 1977, No. 866, § 1; A.S.A. 1947, § 73-276.8; Acts 1999, No. 1556, § 10; 2001, No. 324, §§ 9, 10; 2003, No. 204, §§ 14, 15; 2007, No. 658, § 5; 2009, No. 164, § 8; 2011, No. 910, § 9.