§ 23-18-510 — Certificate of environmental compatibility and public need - Requirement - Exceptions
Arkansas·Title 23
(a)(1) Except for persons exempted as provided in subsection (c) of this section and § 23-18-504(a) and § 23-18-508 , a person shall not begin construction of a major utility facility in the state without first obtaining a certificate of environmental compatibility and public need for the major utility facility from the Arkansas Public Service Commission.
(2)The replacement or expansion of an existing transmission facility with a similar facility in substantially the same location or the rebuilding, upgrading, modernizing, or reconstruction for the purposes of increasing capacity shall not constitute construction of a major utility facility if no increase in width of right-of-way is required.
(b)An entity, including without limitation a person, public utility, utility, regional transmis
Free access — add to your briefcase to read the full text and ask questions with AI
Arkansas § 23-18-510 (Certificate of environmental compatibility and public need - Requirement - Exceptions) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.
Related
Hempstead County Hunting Club, Inc. v. Arkansas Public Service Commission
324 S.W.3d 697 (Court of Appeals of Arkansas, 2009)
Legislative History
Amended by Act 2013, No. 1133,§ 4, eff. 8/16/2013. Acts 1973, No. 164, § 4; 1977, No. 866, § 1; A.S.A. 1947, § 73-276.3; Acts 2007, No. 658, § 2.
Nearby Sections
15
§ 23-1-101
Definitions§ 23-1-103
Compliance with Acts 1935, No. 324, and rules of commission required - Penalties for noncompliance§ 23-1-106
Penalties cumulative - Recovery of penalty not bar to further penalty or criminal prosecution§ 23-1-108
Jurisdiction and venue of actions§ 23-1-110
Actions tried without jury - Exceptions§ 23-1-111
Copies of official papers as evidence§ 23-1-115
Citizens band radio equipment