Arkansas Statutes

§ 19-4-1411 — Processing of payments

Arkansas § 19-4-1411

This text of Arkansas § 19-4-1411 (Processing of payments) is published on Counsel Stack Legal Research, covering Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ark. Code Ann. § 19-4-1411 (2026).

Text

(a)(1) When a contractor submits a properly prepared request for payment of work completed on state construction projects and the request for payment conforms with the provisions of the contract award and laws of the State of Arkansas, the following maximum time is allowed for the processing of the payment requests by the various parties involved, excluding time required for transmittal from one (1) party to another:
(A)A design professional - five (5) working days;
(B)A state agency or institution of higher education exempt from review and approval by the Building Authority Division - five (5) working days, including preparation of a voucher and submission for payment; and (C) The Department of Finance and Administration - five (5) working days.
(2)Should payment be contested by any o

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

Amended by Act 2019, No. 910,§ 6084, eff. 7/1/2019. Acts 1973, No. 876, § 22; 1977, No. 813, § 3; 1979, No. 833, § 9; A.S.A. 1947, § 13-348; Acts 2001, No. 214, § 4; 2001, No. 961, § 6; 2003, No. 364, § 6.

Nearby Sections

15
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Arkansas § 19-4-1411, Counsel Stack Legal Research, https://law.counselstack.com/statute/ar/19-4-1411.