§ 19-11-1404 — Construction Manager-General Contractor Method of Procurement Pilot Program - Creation

Arkansas § 19-11-1404

This text of Arkansas § 19-11-1404 (Construction Manager-General Contractor Method of Procurement Pilot Program - Creation) is published on Counsel Stack Legal Research, covering Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ark. Code Ann. § 19-11-1404 (2026).

Text

(a)The State Highway Commission may develop a Construction Manager-General Contractor Method of Procurement Pilot Program to test the utilization of the construction manager-general contractor method as a cost-effective option for constructing transportation projects.
(b)(1) (A) For the first phase of the program, the commission may select a total of five (5) transportation projects on which to utilize the construction manager-general contractor method.
(B)(i) The sum of the construction cost estimates prepared as required under § 19-11-1407 of all five (5) construction manager-general contractor method transportation projects selected under subdivision (b)(1)(A) of this section shall not exceed two hundred million dollars ($200,000,000).
(ii)A construction cost estimate of a construct

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

Amended by Act 2023, No. 823,§ 2, eff. 8/1/2023. Amended by Act 2023, No. 823,§ 1, eff. 8/1/2023. Amended by Act 2019, No. 1019,§ 3, eff. 7/24/2019. Amended by Act 2019, No. 1019,§ 2, eff. 7/24/2019. Added by Act 2017, No. 809,§ 1, eff. 8/1/2017.

Nearby Sections

15
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Arkansas § 19-11-1404, Counsel Stack Legal Research, https://law.counselstack.com/statute/ar/19-11-1404.