Zoning Bd. of Appeals of Woburn v. Hous. Appeals Comm.

94 N.E.3d 880, 92 Mass. App. Ct. 1115
CourtMassachusetts Appeals Court
DecidedNovember 21, 2017
Docket16–P–1163
StatusPublished

This text of 94 N.E.3d 880 (Zoning Bd. of Appeals of Woburn v. Hous. Appeals Comm.) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Zoning Bd. of Appeals of Woburn v. Hous. Appeals Comm., 94 N.E.3d 880, 92 Mass. App. Ct. 1115 (Mass. Ct. App. 2017).

Opinion

A judge of the Land Court entered judgment on cross motions for judgment on the pleadings, affirming a decision of the Housing Appeals Committee (HAC). The HAC's decision vacated the Woburn zoning board of appeals's (board) denial of Woburn 38 Development, LLC's (developer) application for modification of a 2006 comprehensive permit issued pursuant to G. L. c. 40B, §§ 20 - 23. The board appeals, arguing that the HAC (i) improperly shifted the burden of proof to the board and (ii) failed to recognize the board's concerns regarding the duration of the construction project and associated noise as a "local concern" that outweighs the need for low income housing. We affirm the judgment.

Background. The project at issue has a long history and was the subject of a 2006 decision pursuant to our rule 1:28 which upheld the HAC's decision to vacate the board's denial of the original application for a comprehensive permit. Board of Appeals of Woburn v. Housing Appeals Comm., 66 Mass. App. Ct. 1109 (2006). Thereafter, the board issued the original comprehensive permit to the developer's predecessor in interest on September 26, 2006, and has twice extended it. In 2011-2012, a new owner, the developer, sought a modification of the comprehensive permit. The proposed modification includes the same number of units, 168, but replaces the proposed single six-story building with four three-story buildings, associated parking, and a clubhouse. It requires nearly double the amount of blasting and ledge removal and extends the duration of the site preparation and construction phase of development from six months to at least a year. Even accepting that the modified project will comply with applicable noise regulations, the HAC noted that construction will be loud and unusually lengthy.3

Following a public hearing, the board denied the modification application, finding, among other things, that the twelve months of blasting and gravel removal required for the modification rather than the six months required for the original proposal would interfere with the abutters' "quiet enjoyment of their property," cause unacceptable noise pollution, and adversely affect the public health, welfare, and safety of the direct abutters, as well as the surrounding residential neighborhood. The board concluded that "[a]lthough the design of the modified Project may be more aesthetically pleasing, where the number of affordable units will remain the same, the Board finds that the more extensive construction period associated with the modified Project and the attendant disruptions to abutters and the surrounding residential neighborhood are not mere inconveniences, but create local concerns which outweigh the need for such affordable housing."

The HAC vacated the board's decision, finding that it was not consistent with local needs, and directed the board to permit the requested modification, subject to certain conditions, including that construction comply with all noise and vibration regulations.4 A judge of the Land Court affirmed.

Discussion. The comprehensive permit act, G. L. c. 40B, §§ 20 - 23 (act), "is designed to facilitate the development of low and moderate income housing in communities throughout the Commonwealth.... [The] 'act was intended to remove various obstacles to the development of affordable housing, including regulatory requirements that had been utilized by local opponents as a means of thwarting such development in their towns.' " Eisai, Inc. v. Housing Appeals Comm., 89 Mass. App. Ct. 604, 608-609 (2016), quoting from Dennis Hous. Corp. v. Zoning Bd. of Appeals of Dennis, 439 Mass. 71, 76 (2003). Review of a local board's decision by HAC "is limited to the issue whether 'the decision of the board of appeals was reasonable and consistent with local needs.' " Eisai, 89 Mass. App. Ct. at 609, quoting from Zoning Bd. of Appeals of Holliston v. Housing Appeals Comm., 80 Mass. App. Ct. 406, 414 (2011). Appeal of the HAC's decision is in accordance with G. L. c. 30A, and the "reviewing judge considers whether the HAC's decision was arbitrary, capricious, lacking substantial evidence, or otherwise contrary to the law, and whether the substantial rights of any party have been prejudiced." Eisai, 89 Mass. App. Ct. at 610.

In support of its contention that the HAC erred in overturning the board's decision, the board makes two related arguments and we confine our review to those arguments. The board first contends that the HAC failed to comply with its pretrial order, which placed the burden on the developer to establish a prima facie case that "the blasting and earth removal operations" will comply "with federal or state statutes or regulations or with generally recognized standards" "relating to noise and dust and vibrations."5 Focusing only on noise-related issues, the board contends the HAC impermissibly shifted to the board the burden of proof on this issue. We disagree.

In the case of a denial, the developer's burden in establishing a prima facie case is to show that "its proposal complies with federal or state statutes or regulations, or with generally recognized standards as to matters of health, safety, the environment, design, open space, or other matters of Local Concern." 760 Code Mass. Regs. § 56.07(2)(a)(2) (2012). It is true, however, that the HAC's decision in this case suggests that in reviewing a modification decision, as compared to an outright denial of a project, the burden should not have been placed on the developer to prove that its proposal complies with State or Federal standards. What the board ignores, however, is that the HAC did not end its decision regarding noise impacts there. Rather, the HAC expressly found that "even if the burden were on the developer, the extensive evidence presented by the developer with regard to noise is clearly sufficient to establish a prima facie case." As such, the board's argument that the HAC failed to comply with its pretrial order and misplaced the burden of proof is unavailing.

Assuming the developer was required to establish a prima facie case, it did so. The developer presented expert evidence that the project will comply with all applicable noise requirements. Despite the blasting and earth removal required for this project, the developer did not seek a waiver of any Federal, State, or local regulation related to noise. The HAC specifically found that "[c]onstruction of the development will not go forward unless it is in compliance" with all noise requirements, and, in fact, made the comprehensive permit subject to a condition that construction comply with all Massachusetts, Federal, and local noise and vibration regulations and requirements. In addition, the comprehensive permit provides that "[l]ocal officials and residents may take whatever actions are normally taken to ensure enforcement of such requirements."

In Zoning Bd. of Appeals of Holliston v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Eisai, Inc. v. Housing Appeals Committee
52 N.E.3d 1097 (Massachusetts Appeals Court, 2016)
Dennis Housing Corp. v. Zoning Board of Appeals
785 N.E.2d 682 (Massachusetts Supreme Judicial Court, 2003)
Zoning Board of Appeals v. Housing Appeals Committee
953 N.E.2d 721 (Massachusetts Appeals Court, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
94 N.E.3d 880, 92 Mass. App. Ct. 1115, Counsel Stack Legal Research, https://law.counselstack.com/opinion/zoning-bd-of-appeals-of-woburn-v-hous-appeals-comm-massappct-2017.