IN THE UNITED STATES COURT OF FEDERAL CLAIMS ___________________________________ ) ZOLON PCS II, LLC, ) ) Plaintiff, ) ) v. ) No. 25-21 ) THE UNITED STATES, ) Filed: April 15, 2025 ) Defendant, ) Re-issued: April 30, 2025 * ) and ) ) EXACTA SOLUTIONS, LLC, et al., ) ) Defendant- ) Intervenors. ) ___________________________________ )
OPINION AND ORDER
This is the second bid protest brought in this Court by disappointed bidder Zolon PCS II,
LLC (“Plaintiff” or “Zolon”), challenging an ongoing corrective action taken by the National
Geospatial-Intelligence Agency (“NGA” or “Agency”) related to a solicitation for management
support services. In the prior protest, Zolon sought to enjoin an amendment to the solicitation that
incorporated a one-time deviation from the Federal Acquisition Regulation’s (“FAR”) System for
Award Management (“SAM”) continuous registration requirement. The deviation had the effect
of allowing three of the five original awardees to continue to compete for a new award during the
corrective action, despite the fact that the awardees had SAM registration lapses. The Court set
aside the deviation as arbitrary and capricious. Within a few months of the Court’s decision, and
* The Court issued this opinion under seal on April 15, 2025, and directed the parties to file any proposed redactions by April 22, 2025. As no party submitted proposed redactions, the Court reissues the opinion publicly in full. while the procurement remained in corrective action, the Federal Acquisition Regulatory Council
(“FAR Council”) revised the SAM registration rule to eliminate the requirement for continuous
registration. The NGA then incorporated the new version of the rule into the solicitation via
another amendment. Zolon again argues that the amendment is arbitrary and capricious, as well
as contrary to law. Four of the five awardees have intervened as defendants. All parties moved
for judgment on the administrative record.
For the reasons explained below, the Court GRANTS the Government’s Motion to
Complete the Administrative Record, DENIES Zolon’s Motion for Judgment on the
Administrative Record, and GRANTS the Government’s and Defendant-Intervenors’ Cross-
Motions for Judgment on the Administrative Record. In addition, the Court DENIES AS MOOT
Defendant-Intervenor Exacta Solutions, LLC’s Motion to Dismiss and the Government’s Motion
to Modify Protective Order.
I. BACKGROUND
A. Factual and Prior Procedural Background
This bid protest concerns Solicitation No. HM0476-21-R-0023 (“Solicitation” or “RFP”)
for a procurement referred to as “CLOVER.” A fulsome factual and procedural background,
including a description of the RFP as amended, the prior Government Accountability Office
(“GAO”) protests, and the corrective action, is provided in the Court’s August 2024 opinion and
order issued in Plaintiff’s first bid protest. See Zolon PCS II, LLC v. United States, 172 Fed. Cl.
742, 747–50 (2024) (“Zolon I”). In that opinion, the Court found that the plain text of the SAM
registration requirement in effect at the time, FAR 52.204-7 (OCT 2018), which was incorporated
in the original RFP’s proposal submission requirements, required offerors to maintain continuous
SAM registration from the time of initial offer to the time of award. Id. at 742 (“[O]fferors must
2 be registered in SAM at the time they submit an offer and must ‘continue to be registered until
time of award’ and through contract performance.” (quoting FAR 52.204-7(b)(1) (OCT 2018))).
It further held that the NGA failed to provide a rational basis for deviating from that mandatory
requirement and enjoined the NGA from proceeding under the RFP amendment to the extent it
incorporated the deviation. Id. at 752, 761–63. The Court granted judgment in favor of Zolon on
August 29, 2024. See id. at 747.
Following the Court’s August 2024 opinion in Zolon I, the CLOVER procurement returned
to, and has since remained in, an ongoing corrective action posture. Aside from the issue of SAM
registration, as part of the corrective action the NGA committed to “reassessing the relevant
experience, past performance, and risk assessment volume[s]” submitted by offerors. AR 20543.
Following re-evaluation, the NGA plans to make new award decisions. Id. The NGA has thus
required offerors over the course of the corrective action to periodically update their proposals
with information necessary for the re-evaluation, including recertifying labor rates, recertifying
the validity of proposals, and recertifying and resubmitting conflict of interest disclosures. See
AR 20560, 20831, 20859, 20883.
It was during this post-Zolon I phase of the ongoing corrective action that the FAR Council
changed the SAM registration rule. Specifically, on November 12, 2024, the FAR Council issued
a new interim rule changing FAR 52.204-7 to remove the continuous SAM registration
requirement. AR 20882–87. Effective immediately, to be eligible for a contract award, offerors
must simply have an active SAM registration “when submitting an offer . . . and at time of award.”
89 Fed. Reg. 89472-01, 89475 (Nov. 12, 2024). The FAR Council explained in the Federal
Register that the new rule was intended to “clarify” that SAM registration is required at those two
points in a procurement, but not necessarily “at every moment in between those two points.” Id.
3 at 89472–73; see Def.’s Cross-Mot. for J. on Admin. R. at 17–18, ECF No. 50. Clarification was
necessary given the numerous bid protest decisions, including in Zolon I, that interpreted the plain
text of FAR 52.204-7 (OCT 2018) as requiring an offeror to maintain uninterrupted registration
from the point of offer submission through contract award. 89 Fed. Reg. at 89474. Despite its
choice of language, the FAR Council explained that it did not intend the prior version of the rule
to impose “new requirements with such severe ramifications for offerors.” Id. The Council stated
that the “unintended interpretation” of the courts had “resulted in [a] loss of resources for otherwise
successful small business offerors (e.g., time and costs of litigation, lost income),” caused delays
in agency-mission execution, and deprived the Government of best-value providers. Id. at 89473–
74. The Council made the interim rule immediately effective in order to avoid those costs as well
as “undue confusion and frustration” for small businesses and contracting officers. Id. at 89474.
The Council provided a public notice and comment period, which ended on January 13, 2025. See
id. at 89475; ECF No. 50 at 19.
On December 4, 2024, the NGA issued Amendment 12 to the RFP. Most relevant here,
the amendment replaced FAR 52.204-7 (OCT 2018) with FAR 52.204-7 (NOV 2024) in the RFP’s
proposal submission instructions. The amendment also removed the deviation that was the subject
of the first bid protest, changed the period of performance to begin May 19, 2025, and requested
final proposal revisions by January 10, 2025. AR 20882–83. The NGA later issued a
Memorandum for Record (“MFR”) on December 30, 2024, explaining its reasoning for
incorporating the changed rule into the CLOVER procurement via Amendment 12. AR 20887–
92. The MFR explained that incorporation was warranted for, among other things, the reasons
described by the FAR Council in the published interim rule. AR 20891. It also explained that
incorporating the new rule “carries out the NGA’s original intent for SAM registration” because
4 the NGA had not interpreted the 2018 rule to require continuous registration. Id. Incorporation
also enables the NGA to make awards to best-value offerors “based on the stated evaluation
criteria,” without eliminating potential awardees for “an administrative issue that has absolutely
no practical impact on the Government.” AR 20892.
Eleven offerors submitted final proposal revisions in response to Amendment 12. AR
20893–21668. The Government represented that the NGA has diligently engaged in the re-
evaluation that it committed to during the corrective action and has voluntarily agreed to stay
making new awards through April 15, 2025, to allow for the Court to issue a final decision in this
bid protest. ECF No. 50 at 16 n.4, 39.
B. This Litigation
On January 8, 2025, Zolon filed a Complaint challenging the NGA’s incorporation of FAR
52.204-7 (NOV 2024) into the RFP via Amendment 12. Zolon alleges that the NGA again seeks
to change the RFP post-award to remove the continuous SAM registration requirement set forth in
FAR 52.204-7 (OCT 2018) and restore the eligibility of its previously selected awardees. Compl.
¶ 8, ECF No. 1. Although this time the NGA is doing so through an amendment incorporating the
new FAR rule instead of a deviation from the prior FAR rule, Zolon argues that “similar
improprieties exist, and the Agency still lacks a rational basis for its actions.” Id. Because the
amendment “conveniently removed the continuous SAM registration requirement under which
several of the previously selected awardees should have been deemed incurably deficient,” Zolon
adds that Amendment 12 is intended to help a few particular offerors. Id. ¶ 10. Zolon also argues
that FAR 52.204-7 (NOV 2024), which is still an interim rule, does not provide for retroactive
application to solicitations issued before the rule’s effective date. Id. ¶¶ 81–82. Accordingly,
Zolon urges the Court to conclude that Amendment 12 is arbitrary, capricious, an abuse of
5 discretion, and otherwise unlawful. Id. ¶ 104. Zolon further alleges that Amendment 12
constitutes a breach of the NGA’s implied duty to fairly and honestly consider Zolon’s proposal.
Id. ¶ 107. It requests a permanent injunction barring the NGA from proceeding with a corrective
action re-evaluation of proposals under Amendment 12, disqualifying offerors who failed to
comply with FAR 52.204-7 (OCT 2018), and directing the agency to re-evaluate the remaining
offerors’ proposals in accordance with the RFP and render a new award decision. Id. at 40
(Request for Relief). It also requests bid proposal costs. Id.
Consistent with the Court’s scheduling order, Zolon moved for judgment on the
administrative record. See Pl.’s Mot. for J. on Admin. R., ECF No. 45. The Government and
Defendant-Intervenors cross-moved for judgment on the administrative record, with one of the
intervenors (Exacta) also moving to dismiss the case for lack of standing. See ECF No. 50;
Compass’ Cross-Mot. & Resp., ECF No. 47; Logic Gate’s Cross-Mot. & Resp., ECF No. 48;
Credence Dynamo’s Cross-Mot. & Resp., ECF No. 52; Exacta’s Mot. to Dismiss, Cross-Mot. &
Resp., ECF No. 53. Also before the Court is the Government’s Motion to Complete the
Administrative Record with documents showing the NGA terminated the original CLOVER
awards after issuing Amendment 12. See ECF No. 49. All motions are now fully briefed. 1 See
Pl.’s Resp. & Reply, ECF No. 56; Def.’s Reply, ECF No. 67; Logic Gate’s Reply, ECF No. 62;
Credence Dynamo’s Reply, ECF No. 63; Exacta’s Reply, ECF No. 64; see also Pl.’s Resp. to Mot.
1 The Government also filed a motion requesting that the Court modify the Protective Order entered in this case to allow personnel from the Small Business Administration access to protected materials. Def.’s Mot. to Modify, ECF No. 65. As grounds for the request, the Government stated that “the parties have presented issues in this bid protest that implicate small business concerns that require consultation with the Small Business Administration.” Id. at 2. The Government subsequently withdrew arguments based on such concerns—i.e., Zolon’s mentor-protégé agreement. See Def.’s Notice of Withdrawal at 1, ECF No. 68. Accordingly, the Court denies the motion to modify as moot.
6 to Complete, ECF No. 58; Def.’s Reply on Mot. to Complete, ECF No. 66. The Court held oral
argument on March 20, 2025. See Min. Entry (March 20, 2025).
II. LEGAL STANDARDS
A. Motion for Judgment on the Administrative Record
Rule 52.1(c) of the Rules of the United States Court of Federal Claims (“RCFC”) governs
motions for judgment on the administrative record. Such motions are “properly understood as . . .
an expedited trial on the record.” Bannum, Inc. v. United States, 404 F.3d 1346, 1356 (Fed. Cir.
2005). In contrast to the standard for summary judgment, “the standard for judgment on the
administrative record is narrower” and involves determining, “given all the disputed and
undisputed facts in the administrative record, whether the plaintiff has met the burden of proof to
show that the [challenged action or] decision was not in accordance with the law.” Martinez v.
United States, 77 Fed. Cl. 318, 324 (2007) (citing Bannum, 404 F.3d at 1357). Therefore, a
genuine issue of disputed fact does not prevent the Court from granting a motion for judgment on
the administrative record. See Bannum, 404 F.3d at 1357.
B. Bid Protest Standard of Review
The Tucker Act, as amended by the Administrative Dispute Resolution Act of 1996,
provides the Court of Federal Claims with “jurisdiction to render judgment on an action by an
interested party objecting to . . . the award of a contract or any alleged violation of statute or
regulation in connection with a procurement.” 28 U.S.C. § 1491(b)(1). In such actions, the Court
“review[s] the agency’s decision pursuant to the standards set forth in section 706” of the
Administrative Procedure Act (“APA”). Id. § 1491(b)(4); see Banknote Corp. of Am., Inc. v.
United States, 365 F.3d 1345, 1350 (Fed. Cir. 2004). Accordingly, the Court examines whether
the agency’s action was “arbitrary, capricious, an abuse of discretion, or otherwise not in
7 accordance with law.” 5 U.S.C. § 706(2)(A); see Impresa Construzioni Geom. Domenico Garufi
v. United States, 238 F.3d 1324, 1332 n.5 (Fed. Cir. 2001). Under such review, an “award may be
set aside if either: (1) the procurement official’s decision lacked a rational basis; or (2) the
procurement procedure involved a violation of regulation or procedure.” Impresa, 238 F.3d at
1332.
In reviewing an agency’s procurement decision, the Court may not substitute its own
judgment for the agency’s. Id. (citations omitted); see M.W. Kellogg Co. v. United States, 10 Cl.
Ct. 17, 23 (1986) (deference required if “procurement decisions . . . have a rational basis and do
not violate applicable law or regulations”). The Court “will not vacate an agency’s decision unless
it ‘has relied on factors which Congress had not intended it to consider, entirely failed to consider
an important aspect of the problem, offered an explanation for its decision that runs counter to the
evidence before the agency, or is so implausible that it could not be ascribed to a [different view]
or [agency expertise].’” Nat’l Ass’n of Home Builders v. Defs. of Wildlife, 551 U.S. 644, 658
(2007) (citation omitted). A procurement decision is rational if the agency “provided a coherent
and reasonable explanation of its exercise of discretion.” Dell Fed. Sys., L.P. v. United States, 906
F.3d 982, 992 (Fed. Cir. 2018) (citation omitted). A protestor therefore bears a “heavy burden,”
Impresa, 238 F.3d at 1332–33 (citation omitted), in demonstrating that an agency decision
exceeded the “bounds of reasoned decision making,” Balt. Gas & Elec. Co. v. Nat. Res. Def.
Council, Inc., 462 U.S. 87, 105 (1983).
The APA, however, “prescribes no deferen[ce]” to agencies’ legal determinations. Loper
Bright Enters. v. Raimondo, 603 U.S. 369, 391–92 (2024) (“The APA . . . specifies that courts, not
agencies, will decide ‘all relevant questions of law.’” (quoting 5 U.S.C. § 706)); see also, e.g.,
Eagle Hill Consulting, LLC v. United States, 171 Fed. Cl. 115, 129 (2024) (“[This Court] does not
8 afford deference on questions of law.” (citation omitted)). For example, the “interpretation of . . .
procurement regulations presents [legal] questions” that get de novo review. Eagle Hill
Consulting, 171 Fed. Cl. at 129 (citing NVT Techs, Inc. v. United States, 370 F.3d 1153, 1159 (Fed.
Cir. 2004); United States v. Boeing Co., 802 F.2d 1390, 1393 (Fed. Cir. 1986)).
To prevail in a bid protest, the “protestor must [also] show a significant, prejudicial error
in the procurement process.” WellPoint Mil. Care Corp. v. United States, 953 F.3d 1373, 1377
(Fed. Cir. 2020) (quoting Alfa Laval Separation, Inc. v. United States, 175 F.3d 1365, 1367 (Fed.
Cir. 1999)); see also 5 U.S.C. § 706 (“due account shall be taken of the rule of prejudicial error”).
In post-award protests, the protestor demonstrates prejudice by showing that, but for the error, the
protestor had a substantial chance of receiving a contract award. Off. Design Grp. v. United States,
951 F.3d 1366, 1373–74 (Fed. Cir. 2020). In pre-award protests, however, “it is difficult, if not
impossible, to establish a substantial chance of winning the contract prior to the submission of any
bids.” Orion Tech., Inc. v. United States, 704 F.3d 1344, 1348 (Fed. Cir. 2013) (citing Weeks
Marine, Inc. v. United States, 575 F.3d 1352, 1361 (Fed. Cir. 2009)). Accordingly, the United
States Court of Appeals for the Federal Circuit has approved a different standard, more frequently
applied in the standing context, which requires the Court to assess whether the agency’s error
caused the protestor to suffer a “non-trivial competitive injury.” Weeks Marine, 575 F.3d at 1362.
A court should still apply the “substantial chance” standard, however, in pre-award cases where
there is “an adequate factual predicate” to apply the test. Oracle Am., Inc. v. United States, 975
F.3d 1279, 1291 n.3 (Fed. Cir. 2020); see generally Aero Spray, Inc. v. United States, 156 Fed. Cl.
548, 563–64 (2021) (explaining that the “substantial chance” standard should apply when there
are sufficient facts before the court to apply it).
9 C. Motions to Complete or Supplement the Administrative Record
Different standards govern motions to complete and motions to supplement the
administrative record. The standard for completing the record is less stringent than that of
supplementing it. See Linc Gov’t Servs., LLC v. United States, 95 Fed. Cl. 155, 159 (2010).
“Ordinarily, the government’s designation of an administrative record is entitled to a presumption
of completeness,” but “courts have recognized that this [presumption] can be rebutted with clear
evidence to the contrary.” Poplar Point RBBR, LLC v. United States, 145 Fed. Cl. 489, 494 (2019).
A motion to complete is appropriate when a party seeks to add “information that was generated
and considered by the agency” during the procurement but was omitted from the filed record.
Smith v. United States, 114 Fed. Cl. 691, 695 (2014), aff’d, 611 F. App’x 1000 (Fed. Cir. 2015).
Separate from this standard, the Court’s rules list “relevant” “core documents” that may “qualify
for inclusion in the administrative record.” Poplar Point, 145 Fed. Cl. at 494; RCFC App. C § VII,
¶ 22.
By comparison, bid-protest parties have a “limited” ability to supplement the record.
Axiom Res. Mgmt., Inc. v. United States, 564 F.3d 1374, 1379 (Fed. Cir. 2009). This is because
“the focal point for judicial review should be the administrative record already in existence, not
some new record made initially in the reviewing court.” Id. (quoting Camp v. Pitts, 411 U.S. 138,
142 (1973)). Thus, the record “should be supplemented only if the existing record is insufficient
to permit meaningful review consistent with the [APA].” Id. at 1381. Courts have thus found
supplementation appropriate where the supplemental material is “necessary to help explain an
agency’s decision,” Orion Int’l Techs. v. United States, 60 Fed. Cl. 338, 343 (2004) (citing Camp,
411 U.S. at 142–43); helps explain what the contracting officer considered in reaching a decision,
Precision Standard, Inc. v. United States, 69 Fed. Cl. 738, 747 (2006), aff’d, 228 F. App’x 980
10 (Fed. Cir. 2007); or “correct[s] mistakes and fill[s] gaps” in the administrative record, Pinnacle
Sols., Inc. v. United States, 137 Fed. Cl. 118, 130 (2018) (citing Axiom, 564 F.3d at 1379–81).
III. DISCUSSION
This dispute concerns Plaintiff’s allegation that the NGA’s incorporation of FAR 52.204-
7 (NOV 2024) into the amended RFP was irrational and contrary to law because it had the effect
of removing the continuous SAM registration requirement that otherwise rendered several
awardees ineligible. In addition, the Government requests to complete the Administrative Record
with notices of termination issued on February 20, 2025, showing that the NGA terminated the
original May 2023 awards. ECF No. 49 at 1. Addressing the issues in reverse order, the
Government’s Motion to Complete is granted because the notices are, in any event, necessary for
meaningful judicial review. In addition, the Court concludes that the NGA lawfully and
reasonably incorporated FAR 52.204-7 (NOV 2024) through Amendment 12, and thus the
amendment should not be set aside. Given that holding, Exacta’s Motion to Dismiss is denied as
moot.
A. The Notices of Termination Are Necessary for Meaningful Judicial Review.
As a threshold matter, the Court first reviews the Government’s Motion to Complete. See
ECF No. 49. To guide an agency in compiling an administrative record, the Court’s rules provide
a non-exhaustive list of “core documents relevant to a protest” that the agency “may include, as
appropriate.” RCFC App. C § VII, ¶ 22. This list includes “documents relating to any stay,
suspension, or termination of award or performance pending resolution of the bid protest.” Id.
¶ 22(s). The Government argues that, although the termination notices were issued after
Amendment 12, they fall under ¶ 22(s) as “documents relating to any . . . termination of award”
and should therefore be added to the record. ECF No. 49 at 3. Zolon asserts that ¶ 22(s) only
11 allows such core documents to be included in the administrative record “as appropriate.” ECF No.
58 at 6, 10. According to Zolon, the case law establishes that the only appropriate documents for
purposes of the administrative record are “those materials developed and considered by the agency
in making its decision,” Insight Pub. Sector v. United States, 157 Fed. Cl. 398, 407 (2021) (cleaned
up), and that “[t]he record should not include materials created or obtained subsequent to the
agency’s decision,” Allied Tech. Grp., Inc., v. United States, 92 Fed. Cl. 226, 229–30 (2010).
Zolon asserts that the Court should instead treat the Government’s Motion to Complete as a Motion
to Supplement and apply the more stringent standard—a standard the Government does not meet.
ECF No. 58 at 9.
Even applying the higher supplementation standard, the Government has met its burden.
The Court finds that the termination notices are necessary “to permit meaningful review consistent
with the APA.” Axiom, 564 F.3d at 1381. Zolon repeatedly emphasizes in its dispositive motion
that, as of the date of filing, the NGA had not terminated the unlawful awards initially made in
May 2023. See, e.g., ECF No. 45 at 24 n.4 (“To repeat, the Agency still has not terminated its
initial, unlawful awards.”); id. at 5, 9, 30 n.6, 32, 36, 38, 40, 43 n.8. Indeed, as part of its request
for relief, Zolon asks the Court to terminate the awards. Id. at 44. This factual representation
permeates Zolon’s merits arguments, both challenging Amendment 12 and asserting that the
Agency breached its implied duties. In particular, Zolon argues that the limited exception in FAR
1.108(d)(2) that allows contracting officers to include FAR changes in solicitations issued before
the effective date of the new rule does not apply “because contract awards were issued on May 24,
2023 . . . and they apparently have not been terminated.” Id. at 32.
The notices establish that the NGA has since terminated the initial May 2023 CLOVER
awards. Ex. A to Def.’s Mot. to Complete at 1–5, ECF No. 49-1. Zolon did not object to the
12 NGA’s issuing of the notices; in fact, it is the result for which Zolon advocated. See ECF No. 49
at 2; Oral Arg. Tr. at 18:25–19:24, ECF No. 74. In short, the termination notices constitute part
of what “actually transpired” in this procurement, and they must be considered by the Court to
resolve the parties’ arguments. See AshBritt, Inc. v. United States, 87 Fed. Cl. 344, 366 (2009)
(“Allowing a protest to be decided upon an [administrative record] which does not reflect what
actually transpired would perpetuate error and impede and frustrate effective judicial review.”).
For these reasons, the Government’s Motion to Complete is granted.
B. Amendment 12 Is Not Arbitrary and Capricious or Contrary to Law.
Proceeding to the merits, Zolon argues that (1) the NGA lacks authority to incorporate a
FAR change in the Solicitation, (2) Amendment 12 impermissibly applies FAR 52.204-7 (NOV
2024) retroactively to the CLOVER procurement, and (3) the NGA’s rationale for incorporating
the new rule was otherwise arbitrary and capricious. Each of these grounds fails.
1. The FAR Authorizes the NGA to Include New Regulations in Existing Solicitations.
As an initial matter, the Court must determine whether the FAR expressly authorized the
NGA’s incorporation of FAR 52.204-7 (NOV 2024) into Amendment 12. FAR 1.108(d) provides
guidance to contracting officers about when to apply new FAR rules to solicitations and contracts.
It states:
(d) Application of FAR changes to solicitations and contracts. Unless otherwise specified— (1) FAR changes apply to solicitations issued on or after the effective date of the change; (2) Contracting officers may, at their discretion, include the FAR changes in solicitations issued before the effective date, provided award of the resulting contract(s) occurs on or after the effective date; and (3) Contracting officers may, at their discretion, include the changes in any existing contract with appropriate consideration.
13 FAR 1.108(d). Zolon argues that this provision does not apply because, in this case, the NGA
issued awards in May 2023, which it did not terminate until after it issued the amendment. ECF
No. 45 at 31–32. Zolon adds that the NGA did not cite to FAR 1.108(d)(2) in its MFR explaining
its reasons for incorporating FAR 52.204-7 (NOV 2024) in Amendment 12, so it cannot now
justify the rationality of its decision by reference to the provision. Id. at 33. Neither argument is
persuasive.
The key question to determining whether FAR 1.108(d)(2) applies here is whether
“resulting contract(s)” in the CLOVER procurement will occur after November 12, 2024—the
effective date of FAR 52.204-7 (NOV 2024). The term “resulting” means, in ordinary speech,
“[t]o happen as a consequence.” Resulting, The American Heritage Dictionary (5th ed. 2022); see
FAR 1.108(a) (“Undefined words retain their common dictionary meaning.”). Thus, the Court
must analyze whether the CLOVER contracts will be awarded as a consequence of Amendment
12. If so, then the NGA had the discretion to incorporate the new rule by way of amendment. See
DigiFlight, Inc. v. United States, 167 Fed. Cl. 158, 167 (2023), appeal dismissed, No. 2024-1051,
2023 WL 7179084 (Fed. Cir. Nov. 1, 2023) (noting FAR 1.108(d)(2) “allow[s] contracting officers
to amend solicitations . . . to include regulatory changes that become effective after the
solicitation . . . is issued”).
Here, the NGA has represented that it intends to issue new awards at the conclusion of the
corrective action re-evaluation. See ECF No. 50 at 23–24. The Court recognized as much in Zolon
I. See 172 Fed. Cl. at 749, 758. And although the NGA previously told the GAO in connection
with the corrective action notice that it would simply “lift the stop work order” “[i]f the new award
decision is to the original awardees,” AR 20543, as a functional matter it cannot do so at this point.
The Agency made the initial CLOVER awards almost two years ago based on proposals submitted
14 in response to a Solicitation that has since been amended six times. The NGA, presumably
appreciating that its earlier representation to GAO had been overtaken by events, formally
terminated the initial CLOVER awards on February 20, 2024. See ECF No. 49-1. Accordingly,
at the conclusion of the corrective action, the Agency will unquestionably be making new awards.
Those awards will “happen as a consequence” of Amendment 12, incorporating the new SAM
registration rule, after the effective date of the new rule. Regardless of other questions about the
incorporation’s legality (such as retroactivity and rationality), the Court finds that FAR 1.108(d)(2)
gives the NGA discretion to include FAR 52.204-7 (NOV 2024) in the Solicitation via Amendment
12.
Zolon argues that FAR 1.108(d)(2) “cannot be applied to the CLOVER procurement to
permit retroactive application of FAR 52.204-7 (NOV 2024)” because the NGA already made
contract awards (now terminated) in the procurement. ECF No. 45 at 32. According to Zolon, the
provision applies only where a solicitation is ongoing and the procuring agency has never made
an award. Zolon’s reading of FAR 1.108(d)(2) does not square with its text. The provision does
not limit its applicability to a procurement where the agency has not yet made any award, nor does
it limit its applicability to procurements where the initial contract award is made after the new
rule’s effective date. It states that contracting officers “may, at their discretion, include the FAR
changes in solicitations issued before the effective date, provided award of the resulting
contract(s) occurs on or after the effective date.” FAR 1.108(d)(2) (emphasis added). As
explained above, the Government has repeatedly represented that it intends to make new awards—
i.e., awards of resulting contracts—under Amendment 12. To accept Zolon’s interpretation would
effectively prohibit contracting officers from exercising their discretion under FAR 1.108(d)(2) in
15 any post-award corrective action. The Court will not read into the FAR a limitation that has no
grounding in the provision’s language.
Zolon further asserts that FAR 1.108(d)(2) cannot apply here because the NGA did not
purport to rely on that provision in Amendment 12 or in the MFR explaining the Agency’s rationale
for incorporating FAR 52.204-7 (NOV 2024) in the amendment. ECF No. 56 at 10. It
characterizes the Government’s reliance on the provision in its dispositive briefing as an
impermissible post-hoc rationalization. Id. However, FAR 1.108(d)(2) is not a rationale for the
NGA’s decision to incorporate the new SAM registration rule into Amendment 12, it is the source
of authority that permits the Agency to do so. 2 Zolon cites no authority for the proposition that an
agency must expressly refer to FAR 1.108(d)(2) in order to exercise its discretion under that
provision when incorporating a new FAR rule into a solicitation. Nor does FAR 1.108(d)(2)
contain any documentation requirement that an agency must follow when exercising its discretion
under that provision. Zolon lists examples of other, unrelated FAR changes where it appears the
FAR Council made it “abundantly clear in the Federal Register” upon issuing those changes that
it intended for them to apply to existing solicitations. ECF No. 45 at 32–33 (citing, e.g., 78 Fed.
Reg. 70477, 70478 (2013)). But the discretion provided to contracting officers in FAR 1.108(d)(2)
is not dependent on the FAR Council’s express approval, and the FAR Council’s statements with
2 To be sure, when an agency claims it relied on a particular authority in making a decision, the Government may not argue after-the-fact that the agency’s decision was rational under a separate authority on which the agency did not contemporaneously rely. See, e.g., BAE Sys. Norfolk Ship Repair, Inc. v. United States, 163 Fed. Cl. 217, 227 (2022) (“An agency must defend its actions based on the reasons it gave when it acted.” (quoting Dep’t of Homeland Sec. v. Regents of the Univ. of Cal., 140 S. Ct. 1891, 1909) (2020))). To that end, the Court agrees with Zolon that the NGA must defend its action based on the reasons that it invoked in the MFR. Here, the Court is merely analyzing whether the FAR permitted the challenged action under FAR 1.108(d). When considering the rationality of the NGA’s action, the Court will accordingly consider only the reasons the NGA gave for taking such action. See infra § III.A.3.
16 respect to certain individual rule changes does not demonstrate that an agency must cite FAR
1.108(d)(2) as Zolon suggests. Arguably, the FAR Council’s stated intention for the application
of a new FAR rule to an ongoing solicitation may be relevant under a retroactivity analysis—and
the Court will consider the rule against retroactivity in the next part—but it is irrelevant to whether
FAR 1.108(d)(2) applies here.
2. Amendment 12 Is Not Impermissibly Retroactive.
While the Court has concluded that the NGA acted within the discretion provided in FAR
1.108(d)(2) to incorporate FAR 52.204-7 (NOV 24) into Amendment 12, the question remains
whether doing so was impermissibly retroactive. Zolon argues that independent of FAR
1.108(d)(2), binding precedent prohibits the type of backwards application of law accomplished
in Amendment 12. ECF No. 45 at 28–29. The Court disagrees. 3
The Supreme Court has instructed that “[r]etroactivity is not favored in the law.” Bowen
v. Georgetown Univ. Hosp., 488 U.S. 204, 208 (1988). For that reason, courts interpret statutes
with a presumption against retroactivity, meaning that “the legal effect of conduct should
ordinarily be assessed under the law that existed when the conduct took place.” Landgraf v. USI
Film Prods., 511 U.S. 244, 265 (1994) (citation omitted). Thus, “congressional enactments and
administrative rules will not be construed to have retroactive effect unless their language requires
this result.” Id. at 264 (citing Bowen, 488 U.S. at 208). This anti-retroactivity canon is an
interpretive tool meant to glean a statute’s meaning, rather than a substantive prohibition meant to
categorically limit an agency’s conduct. See Antonin Scalia & Bryan A. Garner, Reading Law:
3 Because the Court finds in any event that the incorporation of FAR 52.204-7 (NOV 2024) in the Solicitation is not impermissibly retroactive, it need not address Credence Dynamo’s argument that FAR 1.108(d)(2) displaces the traditional retroactivity analysis applied in non- procurement cases. See ECF No. 52-1 at 21.
17 The Interpretation of Legal Texts 261 (2012); see also id. at 262 (describing the presumption as “a
canon of interpretation and not a rule of constitutional law”); Landgraf, 511 U.S. at 273 (noting
that the Court sometimes does not apply the presumption, which is “simply a response to the
language of the statute”). For that reason, applying the rule against retroactivity “is not always a
simple or mechanical task.” Landgraf, 511 U.S. at 268; see id. at 270 (“Any test of retroactivity
will leave room for disagreement in hard cases, and is unlikely to classify the enormous variety of
legal changes with perfect philosophical clarity.”). Nonetheless, courts have attempted to define
the boundaries of the presumption. The Supreme Court in Landgraf offered one “influential
definition” by Justice Story: an impermissibly retroactive law is one that “takes away or impairs
vested rights acquired under existing laws, or creates a new obligation, imposes a new duty, or
attaches a new disability, in respect to transactions or considerations already past.” Id. at 268–69
(citing Soc’y for the Propagation of the Gospel v. Wheeler, 22 F. Cas. 756, 767 (C.C.D.N.H. 1814)
(No. 13,156) (Story, J.)). 4
The Federal Circuit has applied the analysis in Landgraf through a two-part test, requiring
a court to determine: (1) whether an application of a rule is a retroactive one, and (2) if so, whether
4 Landgraf cited a long history of cases and secondary sources using the same essential definition as Justice Story. See, e.g., Union Pac. R.R. v. Laramie Stock Yards Co., 231 U.S. 190, 199 (1913) (retroactive statute gives “a quality or effect to acts or conduct which they did not have or did not contemplate when they were performed”); Sturges v. Carter, 114 U.S. 511, 519 (1885) (a retroactive statute is one that “takes away or impairs vested rights acquired under existing laws, or creates a new obligation, imposes a new duty, or attaches a new disability”); Black’s Law Dictionary 1184 (5th ed. 1979) (quoting Justice Story’s definition from Society); see also Society, 22 F. Cas. at 767 (citing Calder v. Bull, 3 U.S. (3 Dall.) 386 (1798); Dash v. Van Kleeck, 7 Johns. 477 (N.Y. Sup. Ct. 1811))). Landgraf went on to state that “[s]ince the early days of this Court, we have declined to give retroactive effect to statutes burdening private rights unless Congress had made clear its intent.” 511 U.S. at 270 (emphasis added) (citing United States v. Heth, 7 U.S. (3 Cranch) 399 (1806)) (declining to retroactively apply a federal statute reducing commissions of customs collectors). Landgraf also stated that the presumption “has consistently been explained by reference to the unfairness of imposing new burdens on persons after the fact.” Id. (emphasis added).
18 the rule expressly demonstrates retroactive intent. Travenol Labs., Inc. v. United States, 118 F.3d
749, 752 (Fed. Cir. 1997). At step one, “whether a statute’s application in a particular situation is
prospective or retroactive depends upon whether the conduct that allegedly triggers the statute’s
application occurs before or after the law’s effective date.” Id. (quoting McAndrews v. Fleet Bank
of Mass., N.A., 989 F.2d 13, 16 (1st Cir. 1993)); see Fed. Performance Mgmt. Sols., LLC v. United
States, No. 23-1802C, 2024 WL 34586, at *5 (Fed. Cl. Jan. 3, 2024) (“[F]or an impermissible
retroactive application to exist, a party must be divested of a right it once had.”). “[I]f the answer
to [the step-one] question is ‘yes,’” the court moves to step two to “search for a clear expression
of congressional intent to apply the law retroactively.” Travenol Labs., 118 F.3d at 752.
Zolon argues that Amendment 12’s incorporation of FAR 52.204-7 (NOV 2024) is
retroactive because it creates “new legal consequences” for the offerors whose SAM registrations
lapsed after initial offer submission. ECF No. 56 at 28 (quoting Landgraf, 511 U.S. at 270). Zolon
points out that before the amendment those offerors were ineligible for award, yet after the
amendment they are eligible. Id. Zolon’s broad reading of the “new legal consequences” language
from Landgraf is not supported by the opinion itself or other precedent. As Landgraf
acknowledged, a statute is not impermissibly retroactive “merely because it is applied in a case
arising from conduct antedating the statute’s enactment, or upsets expectations based in prior law.”
511 U.S. at 269 (internal citation omitted). Rather, the legal consequences that warrant finding a
law “impermissibly retroactive” involve circumstances where the law “‘takes away or impairs
vested rights acquired under existing laws, or creates a new obligation, imposes a new duty, or
attaches a new disability, in respect to transactions or considerations already past.’” Kearfott
Guidance & Navigation Corp. v. Rumsfeld, 320 F.3d 1369, 1374 (Fed. Cir. 2003) (quoting
Landgraf, 511 U.S. at 269).
19 Here, the NGA’s decision to incorporate FAR 52.204-7 (NOV 2024) through Amendment
12 does not create any “new obligation,” impose a “new duty,” or attach a “new disability” to any
offeror, including Zolon. Landgraf, 511 U.S. at 269. As the Government points out, it equally
removes an obligation for all offerors: an obligation to maintain continuous SAM registration
between the time of offer and award. See ECF No. 50 at 34–35. If anything, the new rule makes
it easier for offerors to maintain compliant SAM registrations. Accordingly, any concern about
“the unfairness of imposing new burdens” based on past conduct is absent here. Landgraf, 511
U.S. at 270; see Fed. Performance Mgmt. Sols., 2024 WL 34586, at *5 (finding no impermissible
retroactivity where “the amended regulation made it easier for [joint ventures] to submit additional
proposals”); see also Kearfott, 320 F.3d at 1375 (finding no impermissible retroactive application
where the “FAR [did not] impose any new obligation, duty, or disability with respect to a
transaction previously entered into by [Plaintiff]”); Gen. Elec. Co. v. United States, 112 Fed. Cl.
1, 13 n.12 (2013) (same).
Nor did Amendment 12 divest Zolon of a right it once had. It bears noting that applying
FAR 52.204-7 (NOV 2024) to the ongoing CLOVER procurement will have no impact on the re-
evaluation of Zolon’s proposal, at least based on Zolon’s past conduct. To the Court’s knowledge,
Zolon has continuously had an active SAM registration since the time of its initial offer submission
to the present. The fact that it maintained continuous registration does not harm Zolon in
competing for a CLOVER contract, even though continuous registration is no longer a “minimum
preaward registration” requirement. 89 Fed. Reg. at 89473. Indeed, if anything, Zolon’s past
conduct satisfies the FAR Council’s stated expectation that offerors will maintain continuous,
active registration regardless of any FAR requirement. Id.
20 At oral argument, Zolon asserted that incorporating FAR 52.204-7 (NOV 2024) “impairs
[Zolon’s] rights because those offerors with lapsed SAM registrations were once to be disqualified
and are now being allowed to compete against [Zolon] for the same number of awards.” ECF No.
74 at 26:8–11. As an initial matter, neither FAR 52.204-7 (OCT 2018) nor FAR 52.204-7 (NOV
2024) convey a right to any offeror; instead, they impose an obligation on individual offerors. And
although the NGA made FAR 52.204-7 (OCT 2018) part of the RFP’s proposal submission
requirements, which per the RFP would be “strictly enforce[d],” AR 1996, Zolon recognizes that
an agency “typically” has “broad discretion” to amend an RFP to achieve awards on the basis of
best value, ECF No. 45 at 23. The Court recognized the same in Zolon I. 172 Fed. Cl. at 755
(“Ordinarily the Government may amend a solicitation to change or clarify requirements, with the
stated purpose of securing the best value contract.”); see also id. at 756 (noting that a contracting
agency “has broad discretion to amend the solicitation when it determines that such action is
necessary to obtaining the best value contract awards” (emphasis added) (quoting ManTech
Telecomms. & Info. Sys. Corp., 49 Fed. Cl. 57, 73 (2001), aff’d, 30 F. App’x 995 (Fed. Cir. 2002)));
FAR 15.206(a). The Government likewise has broad discretion to amend a solicitation to change
its “terms and conditions.” FAR 15.206(a). Those amended terms may include, at the contracting
officer’s discretion, subsequently issued FAR changes, “provided award of the resulting
contract(s) occurs on or after the effective date” of the FAR change. FAR 1.108(d)(2).
This all goes to show that Zolon had no vested right in the NGA applying FAR 52.204-7
(OCT 2018) to the CLOVER procurement either because of an alleged right acquired under the
prior rule or because of the prior rule’s incorporation in the original RFP. As the Government
correctly asserts, in an ongoing evaluation, where a final contract award has not been made, the
procuring agency’s discretion to amend or even cancel the solicitation means “no party [has] a
21 ‘vested right’ in any particular solicitation provision or contract clause.” ECF No. 50 at 35; see
126 Northpoint Plaza Ltd. P’ship v. United States, 34 Fed. Cl. 105, 107 (1995), appeal dismissed,
73 F.3d 379 (Fed. Cir. 1995) (“[A] contractor is never assured that it will receive an award,” so
“the government retains discretion to reject all bids without liability . . . .”). Because the
incorporation of the new SAM registration requirement in Amendment 12 does not impair Zolon’s
vested rights, create any new obligation, impose any new duty, or attach any new disability to
Zolon (or other offerors) vis-à-vis SAM registration during this procurement, the presumption
against retroactivity does not apply. Thus, the analysis ends at step one of the retroactivity test. 5
3. Amendment 12 Is Not Otherwise Arbitrary and Capricious.
Zolon further contends that even if Amendment 12’s incorporation of FAR 52.204-7 (NOV
2024) was authorized and not impermissibly retroactive, the amendment is still arbitrary and
capricious because none of the NGA’s listed reasons hold up to scrutiny. ECF No. 45 at 12–26.
As the Court previously explained, a legally permissible action may nonetheless be set aside if it
fails under the arbitrary-and-capricious standard. See Zolon I, 172 Fed. Cl. at 757. Here, the NGA
has provided a rational basis for its action.
First, the NGA explained that it was incorporating FAR 52.204-7 (NOV 2024) through
Amendment 12 for the reasons expressed by the FAR Council in the interim rule. Zolon does not
specifically challenge the FAR Council’s reasoning for the rule change, but it is equally applicable
to the CLOVER procurement, as Exacta points out. See ECF No. 53 at 34. Indeed, the FAR
Council cited the Court’s decision in Zolon I, among other bid protest decisions from this court,
5 Since the Court concludes that application of the new FAR rule via Amendment 12 is not impermissibly retroactive under step one, the Court does not reach step two to ask whether FAR 52.204-7 (NOV 2024) clearly expresses the FAR Council’s intent that the new rule be retroactively applied. See Travenol Labs., 118 F.3d at 752.
22 as the impetus for the change. According to the FAR Council, it never intended FAR 52.204-7
(OCT 2018) to create a continuous SAM registration requirement and, equally important, it
believes such rule creates “an unwitting barrier to entry and significant disruption” in the federal
procurement system. AR 20890 (quoting 89 Fed. Reg. at 89474). In the FAR Council’s judgment,
perpetuating a continuous registration rule would, among other things, harm offerors (especially
small businesses) by “[i]ntroduc[ing] significant risk of lost income . . . due to temporary lapses in
registration often for minor and technical reasons” as well as procuring agencies by
“complicat[ing] the ability of the Government to meet its mission needs with best-value solutions.”
Id. Policy-based determinations such as these fall comfortably within the FAR Council’s
congressional mandate and rulemaking authority. See 41 U.S.C. § 1302(a) (establishing the FAR
Council “to assist in the direction and coordination of Government-wide procurement policy and
Government-wide procurement regulatory activities in the Federal Government”); id. § 1303
(authorizing the FAR Council to “issue and maintain . . . a single Government-wide procurement
regulation, to be known as the [FAR]”).
Zolon has failed to establish that the NGA’s adoption of the FAR Council’s reasoning in
the very procurement that spurred the FAR Council to change the rule lacks rationality.
Incorporating FAR 52.204-7 (NOV 2024) into Amendment 12 prevents the type of losses for
small-business offerors and the type of complications for agency-mission needs that FAR 52.204-
7 (OCT 2018) unintentionally imposed. The MFR coherently and reasonably explains this basis
by incorporating the FAR Council’s rationale.
In addition, the MFR explains that incorporating FAR 52.204-7 (NOV 2024) carries out
the NGA’s “original intent” for SAM registration, AR 20891, and will permit the Agency to make
awards to “offerors that provide the best value to the Government based on the stated evaluation
23 criteria, without limiting the pool of potential awardees due to a superfluous, and now non-existent
administrative requirement,” AR 20892. In what it characterizes as “a strong sense of déjà vu,”
Zolon argues that the Agency is merely recycling reasons for its current action that the Court
previously rejected in Zolon I. ECF No. 45 at 11. Zolon does not appreciate that this protest
presents a very different set of facts from its prior protest. In Zolon I, the Court found that the
NGA’s one-time deviation from FAR 52.204-7 (OCT 2018), though otherwise legally permissible,
was not rationally supported by the reasons documented in the Agency’s deviation decision. 172
Fed. Cl. at 757. In the instant case, the NGA does not seek to deviate from a mandatory FAR
requirement that would otherwise eliminate best-value offerors for temporary SAM registration
lapses, but rather to follow the current FAR requirement which was specifically changed to reflect
a policy against eliminating best-value offerors for that reason. The Court’s rulings in Zolon I are
therefore not dispositive here.
For example, the Agency states that FAR 52.204-7 (NOV 2024) fits with how the NGA
“had always intended” the SAM registration requirement to apply. AR 20891. In Zolon I, the
Court found a similar original-intent justification lacking because the Agency’s intent to provide
itself with discretion to waive non-compliance with the RFP’s requirements was “inconsistent with
the plain language of FAR 52.204-7(b)(1) [(OCT 2018)],” a mandatory provision that the NGA
lacked discretion to waive. 172 Fed. Cl. at 754. It was also inconsistent with the NGA’s
representation to the GAO that on corrective action it would apply the FAR rule based on the
language in the RFP. Id.
The record in this protest shows that the NGA did not interpret FAR 52.204-7 (OCT 2018)
as imposing a continuous SAM registration requirement. Indeed, the MFR explains that around
the same time that the Agency was preparing the decision memo justifying the deviation, “NGA’s
24 Senior Procurement Executive, Kelly Pickering, requested the DoD representative to the FAR
Council clarify that a lapse in active registration on SAM.gov did not render that offeror ineligible
under FAR 52.204-7 as long as the offeror was active at the time of proposal submission and time
of award.” AR 20891. Although the Agency’s reading was a misinterpretation of the plain
language of the prior rule, see Zolon I, 172 Fed. Cl. at 754, the request led to the FAR Council
clarifying that it did not intend FAR 52.204-7 (OCT 2018) to impose a continuous requirement.
And consistent with its authority, the FAR Council removed the language that led courts to
interpret the SAM registration rule in that way. Now, instead of the plain language of the SAM
registration rule being at odds with the NGA’s intent, the current rule fits with what the NGA
intended from the start. The Court sees nothing incoherent or irrational about the Agency’s choice
to incorporate a FAR change that conforms the language of FAR 52.204-7 to the shared intent of
the NGA and the FAR Council. See Dell, 906 F.3d at 992 (citation omitted).
Similarly, the MFR explains that the NGA’s decision to incorporate FAR 52.204-7 (NOV
2024) through Amendment 12 was based on its judgment that awards to the best-value offerors
based on the criteria of the Solicitation is the best way to meet its needs. AR 20891. Conversely,
eliminating offerors for “an administrative issue that has absolutely no practical impact on the
Government” does not, in the Agency’s view, help meet its needs. AR 20892. The NGA made a
similar argument in Zolon I. The Court found that this rationale presented “a closer question”
under the standard of review, but ultimately rejected it because the NGA’s basis for deviating
“from a mandatory regulatory provision” was that enforcing the requirement “prevent[ed] the
agency from awarding the contract to an otherwise successful offeror.” Zolon I, 172 Fed. Cl. at
757. This rationale did not support the deviation because “[t]hat reasoning lacks a limiting
25 principle and would allow the Government to sidestep any and all mandatory FAR requirements
whenever a requirement operates to exclude a putative awardee.” Id.
The facts in the instant protest differ from Zolon I. Here, the NGA seeks not a deviation
from a mandatory FAR requirement but an amendment to incorporate a FAR change. The FAR
change specifically adopts the same policy judgment about the SAM registration requirement. The
FAR Council stated that although “continuous, active, registration is the anticipated normal state
expected of offerors . . . , the Government is now directing that the minimum preaward registration
compliance” does not require continuous SAM registration. 89 Fed. Reg. at 89473. Characterizing
elimination for a lapsed SAM registration as a “severe ramification[] for offerors,” the FAR
Council also specifically determined in its judgment that such rule “[u]nnecessarily complicate[s]
the ability of the Government to meet its mission needs with best-value solutions.” Id. at 89474.
Again, this is not a scenario where the Agency is attempting to side step a FAR rule so that best-
value offerors survive in the competition, it is attempting to follow a FAR rule that was specifically
changed so that best-value offerors are not unnecessarily eliminated. That reasoning is neither
arbitrary nor capricious.
To be sure, it would be “of concern” if the NGA were changing the RFP just to ensure
certain offerors will win. Zolon I, 172 Fed. Cl. at 755. However, sustaining such a concern
typically requires that the protestor establish bad faith on the agency’s part. Id. (citing EP Prods.,
Inc. v. United States, 63 Fed. Cl. 220, 225–26 (2005)). “There is a ‘strong presumption that
government contract officials exercise their duties in good faith,’” and to defeat that presumption
“a protestor must present ‘well-nigh irrefragable proof’ that the government officials did not act
in good faith.” BAE Sys., 163 Fed. Cl. at 238 (internal citations omitted). Zolon has disclaimed
any arguments of bad faith, see ECF No. 45 at 38; but even if it had not, as the Court found in
26 Zolon I “there is no ‘irrefragable proof’ that [certain] offerors [in the CLOVER procurement] are
‘preferred’ or ‘pre-selected,’ or that the corrective action [at issue here] is a sham.” 172 Fed. Cl.
at 758.
Therefore, the Court applies only the arbitrary and capricious standard. Under that
deferential standard of review, the NGA did not act arbitrarily in deciding to amend the Solicitation
to incorporate FAR 52.204-7 (NOV 2024). Upon reviewing Amendment 12 and the MFR, and
considering the entirety of the record, the NGA “provided a coherent and reasonable explanation
of its exercise of discretion.” Dell, 906 F.3d at 992 (citation omitted).
* * *
In sum, the NGA has the discretion in this case to include new FAR rules in the existing
RFP, and doing so is neither a violation of the presumption against retroactivity nor an irrational
exercise of discretion.
C. Because Amendment 12 Is Not Arbitrary and Capricious, the NGA Did Not Breach its Implied Duty to Fairly and Honestly Consider Zolon’s Proposal.
Finally, Zolon argues that the Agency’s continued attempts to amend the Solicitation “to
allow for the re-selection of offerors who should have been deemed ineligible due to lapsed SAM
registrations” violated its duty to fairly and honestly evaluate Zolon’s proposal. ECF No. 45 at 36.
As Zolon acknowledged at oral argument, its implied-breach argument is largely derivative of its
arbitrary-and-capricious argument. See ECF No. 74 at 143:22–25. This is an appropriate
concession because the standard for implied breach to fairly and honestly consider a bid “is
whether the government’s conduct was arbitrary and capricious.” Southfork Sys., Inc. v. United
States, 141 F.3d 1124, 1132 (Fed. Cir. 1998). And although an implied-breach claim may warrant
the Court awarding an additional remedy not otherwise available under the arbitrary-and-
capricious standard, the claim cannot survive in the absence of an irrational agency action. See
27 ECF No. 74 at 143:22–25 (“[T]he reason why that count matters is because there’s a specific type
of relief associated with it, which is, namely, bid preparation and proposal costs.”). Therefore,
because the Court concludes that Zolon’s arbitrary-and-capricious claim fails, it also concludes
that Zolon’s implied-breach claim fails.
D. Zolon Is Not Entitled to Injunctive Relief.
Zolon requests that the Court permanently enjoin the NGA from proceeding with
Amendment 12 and order the NGA to rescind the amendment, disqualify any offerors who failed
to maintain continuous SAM registration under FAR 52.204-7 (OCT 2018), re-evaluate all
remaining proposals, and render a new award decision. ECF No. 45 at 44. To obtain permanent
injunctive relief, Zolon must show that: (1) it prevailed on the merits; (2) it will suffer irreparable
harm if injunctive relief is not granted; (3) the balance of hardships weighs in favor of granting
injunctive relief; and (4) injunctive relief is in the public interest. See PGBA, LLC v. United States,
389 F.3d 1219, 1228–29 (Fed. Cir. 2004). Under this standard, “[n]o one factor, taken
individually, is necessarily dispositive. . . . [T]he weakness of the showing regarding one factor
may be overborne by the strength of the others.” FMC Corp. v. United States, 3 F.3d 424, 427
(Fed. Cir. 1993). 6 “At the very least, however, a protestor must actually succeed on the merits and
demonstrate irreparable harm.” Zolon I, 172 Fed. Cl. at 761 (citing CliniComp Int’l, Inc. v. United
States, 134 Fed. Cl. 736, 746 (2017), aff’d, 904 F.3d 1353 (Fed. Cir. 2018)); see also Altana
Pharma AG v. Teva Pharms. USA, Inc., 566 F.3d 999, 1005 (Fed. Cir. 2009).
6 Although FMC concerns the award of a preliminary injunction, “[t]he standard for a preliminary injunction is essentially the same as for a permanent injunction,” except the plaintiff must show actual success, rather than a likelihood of success, on the merits to obtain a permanent injunction. Amoco Prod. Co. v. Village of Gambell, 480 U.S. 531, 546 n.12 (1987).
28 As explained above, Zolon has not prevailed on the merits. For that reason, injunctive
relief is not warranted in this case. See Mitchco Int’l, Inc. v. United States, 26 F.4th 1373, 1384
n.7 (Fed. Cir. 2022).
IV. CONCLUSION
For these reasons, the Court GRANTS the Government’s Motion to Complete (ECF No.
49), DENIES Plaintiff’s Motion for Judgment on the Administrative Record (ECF No. 45), and
GRANTS the Government’s and Defendant-Intervenors’ Cross-Motions (ECF Nos. 50, 47, 48,
52, 53). Exacta’s Motion to Dismiss (ECF No. 53) and the Government’s Motion to Modify
Protective Order (ECF No. 65) are DENIED AS MOOT. The Clerk is directed to enter judgment
accordingly.
SO ORDERED.
Dated: April 30, 2025 /s/ Kathryn C. Davis KATHRYN C. DAVIS Judge