Zimmermann v. Jourgensen

24 N.Y.S. 170, 70 Hun 222, 77 N.Y. Sup. Ct. 222, 54 N.Y. St. Rep. 13
CourtNew York Supreme Court
DecidedJune 30, 1893
StatusPublished
Cited by3 cases

This text of 24 N.Y.S. 170 (Zimmermann v. Jourgensen) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Zimmermann v. Jourgensen, 24 N.Y.S. 170, 70 Hun 222, 77 N.Y. Sup. Ct. 222, 54 N.Y. St. Rep. 13 (N.Y. Super. Ct. 1893).

Opinion

O’BRIEN, J.

This is the second time this action has come before this general term for review. It was brought on a building contract between plaintiffs, as contractors, and defendant, as owner, to recover a balance claimed by plaintiffs to be due for making •alterations and additions to defendant’s building in Maiden Lane, "in this city, under such written contract. By its terms the contract provided for the payment to plaintiffs of the sum of $14,199 for the entire work, in the fallowing manner: $4,000 when the third tier of beams was placed in position, $4,000 when the roof was on, •and the balance, $6,199, 10 days after the entire work was completed. Although no time was specified in the contract, it was insisted by defendant that May 1,1890, was agreed upon as the date of completion; but the referee has found against this contention, holding that no time was agreed upon between the parties within which the said work should be finished. Upon the execution of the contract, which wras made in March, 1890, the plaintiffs com.menced work thereunder, and continued until August 20th, when [172]*172íbe defendant, availing himself of a clause in the contract, entered into possession of the premises, and elected to complete the work himself for and on account of plaintiffs, claiming that they had neglected to supply a sufficiency of material and workmen. The-first two installments, $4,000 each, having been paid, there would have been due, had the plaintiffs fully completed their contract,. $6,199, in addition to an unpaid balance of $355, which, as found by the referee, was due plaintiffs for extra work performed at defendant’s request. The plaintiffs allege that defendant would be entitled to an allowance on the final payment Of $1,118 for completing the work; and it is the entire balance, together with pay for the extra work, less such allowance to defendant, for which plaintiffs demand judgment. The plaintiffs, in their complaint, allege that the work was substantially finished when defendant took possession of the premises, and it is seemingly their theory that it is the entire contract price, less what would be the reasonable value of completion, which should determine the amount for which they are entitled to judgment. We think, however, that there can be no dispute, upon the evidence as furnished by the plaintiffs themselves, that when the defendant, after service of a notice upon the plaintiffs, assumed the right to take up the work and complete it himself, it was not substantially finished. The testimony shows that upon that date the premises were unfit for occupancy, glass flooring half laid, floor and ceilings wanting, and portions of the building exposed to the weather. If the plaintiffs had abandoned their work at that stage, we fail to see how they would have been entitled to recover anything, because, upon such facts, showing that the cost of completion, according to plaintiffs’ own theory, would be more than $1,000, and according to the defendant’s more than $6,000, there would have been no such substantial completion as, under the authorities, would have entitled the plaintiffs to recover the contract price, less the amount required to complete the building. The familiar case of Woodworth v. Fuller, 80 N. Y. 312, states under what circumstances a recovery may be had on a contract without a literal or exact performance of it in the following language:

“Where a builder has in good faith intended to comply with the contract, and has substantially complied with it, although there may be slight defects, caused by inadvertence or unintentional omissions, he may recover the contract price, less the damage on account of such defects. The defects must not run through the whole, nor be so essential as that the object of the parties to have a specified amoxmt of work done in a particular xvay is not accomplished.” »

In addition to the work which then remained to be done, there was imperfect work, which had to be done over, and Which, as found by the referee, cost defendant $175. The existence of this condition of affairs, showing that a portion of plaintiffs’ work had been imperfectly done, requiring the expenditure of time and money by the defendant, raises a serious question as to plaintiffs’ right to maintain the action at all. We do not, however, decide that this is an insuperable bar to a recovery, but will proceed to dispose [173]*173-of the case upon the merits as they were presented before the referee; but it is proper that the matter should be adverted to, .as it is also that we should endeavor to ascertain from the complaint itself the theory upon which the plaintiffs base their right to recover. As already remarked, we must discard the theory in -one part of the complaint presented, that plaintiffs are entitled to recover because, having substantially performed their contract, they should receive the entire amount thereunder provided to be paid, less what was necessary to be expended by the defendant to entirely finish the work. In another paragraph of the complaint it is alleged that, after commencing, the plaintiffs continued the work “conscientiously, diligently, and with all possible speed, .and used their best endeavors to get prompt and sufficient supplies of the building material to be used in the construction of the said work until August 20, 1890, when the defendant refused to permit the plaintiffs to complete the said work, and prohibited them, their agents and servants, from entering the said buildings ISTos. 96 and 98 Maiden Lane, and notified the plaintiffs that he would finish the said building, and deduct the expense thereof from the amount still due and owing to the plaintiffs under the said contract.” Had the plaintiffs succeeded in sustaining these allegations, then they would have been entitled to recover damages as against the defendant for a breach of the contract on his part, because the charge thus made is the exact equivalent of saying that the defendant wrongfully broke his contract. Upon such facts the plaintiffs would have had three remedies in law: First, they could treat the contract as at an end, and claim damages for its breach; second, they could recover on a quantum meruit for all work done by them up to the breach which remained unpaid for; or, third, they could recover the full contract price if the contract was substantially performed. It is evident from the testimony that plaintiffs did not elect to proceed upon either the first or the second of the remedies above mentioned, and we are therefore left to assume that recovery was sought upon the theory that the contract was substantially performed. For reasons already given, it is difficult to see how a recovery could be had upon this ground; but, as the case was fully tried out, it is perhaps right that we should treat it as the parties themselves did seemingly upon the trial, by examining into the questions in dispute between them, regardless of the issues as made by the pleadings, determine whether, upon the facts - as proved and found by the referee, the conclusions of the latter were sound. Upon conflicting evidence, the referee has found (and we see no reason to disturb :such findings) as follows:

“Sixth.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bayfield County v. Ogren
177 N.W. 591 (Wisconsin Supreme Court, 1920)
Wilson v. Curran
190 A.D. 581 (Appellate Division of the Supreme Court of New York, 1920)
Spence v. . Ham
57 N.E. 412 (New York Court of Appeals, 1900)

Cite This Page — Counsel Stack

Bluebook (online)
24 N.Y.S. 170, 70 Hun 222, 77 N.Y. Sup. Ct. 222, 54 N.Y. St. Rep. 13, Counsel Stack Legal Research, https://law.counselstack.com/opinion/zimmermann-v-jourgensen-nysupct-1893.