Zimmerman v. United States

43 Ct. Cl. 525, 1908 U.S. Ct. Cl. LEXIS 18, 1907 WL 876
CourtUnited States Court of Claims
DecidedMay 25, 1908
DocketNo. 21911
StatusPublished

This text of 43 Ct. Cl. 525 (Zimmerman v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Zimmerman v. United States, 43 Ct. Cl. 525, 1908 U.S. Ct. Cl. LEXIS 18, 1907 WL 876 (cc 1908).

Opinion

Howrt, Judge,

delivered the opinion of the court:

This is a claim upon two contracts for constructing locks and dams on the Great Kanawha River in West Virginia. The contracts were in the form usually made by the Government with private contractors for large river and harbor improvements, not providing a gross sum for the completion of the whole work, but a fixed sum for a given unit of each kind of work to be performed. There were numerous items, with much conflict of testimony respecting many of them. Judgment was rendered for the claimants on certain of these demands and against them on other items. The questions [561]*561now presented arise on a motion of tlie claimants for a new trial in connection with three of the findings.

Error of fact is alleged in the fifth finding in not finding the amount of deposits removed by the claimants 5 and error of law is said to arise in not rendering judgment for the claimants on this finding.

The provision in the specifications covering the removal of deposits in cofferdams required material washed br left in the cofferdams by freshets to be removed by the contractors, as directed, at their price for excavation. But no payment was to be made for removing material washed into the cofferdams from the coffers themselves or for any deposit made by the contractors beyond or above the work. The provision for the removal of the cofferdams themselves provided that the contractors would be required to remove these and their belongings at their own cost, the time and manner of the removal of the coffers and the place to deposit the material to be prescribed by the engineer. The court accepted the defendants’ contention that the resident engineer ordered the removal of as much of the deposits within the cofferdams as was necessary for the prosecution of the work, and that this quantity was estimated and paid for, but that the portion of the deposits banked against the face of the upper cofferdams was not in the way of construction, and its removal was consequently unnecessary, inasmuch as it was composed of such material as was easily washed away when the cofferdams were removed and the current came into contact with the deposits.

But on this point the court finds upon a careful review of the evidence that directions were given for the removal of certain of the deposits for which the claimants have not been paid. It is true that the provision for the removal of material was left discretionary with the officers in charge, or to leave this material to be washed by the current. The contractors were bound by the directions when given, regardless of whether the deposits could be washed away by the current when the cofferdams were removed. Inasmuch as we find the real fact to be that the orders were given by the government agents and the contractors have not been paid for work [562]*562done pursuant to these orders, we are constrained to reverse ourselves as to the consequences after reexamining the facts and finding that the orders were actually given. The engineer having decided that the deposits banked against the face of the upper cofferdams was in the way of the construction of the work, we are unable in the face of this decision of the officer to find as a fact that it was not in the way of construction, or that these deposits could have been washed out by the current in time to admit of proper progress in construction, if at all. The amended finding of the court leaves only the amount of the deposits to be calculated and the compensation to be awarded. As to the amount there is conflicting evidence. The court has gone over the testimony in detail and finds that 1,213§ cubic yards of deposits were ordered removed at government expense. The result is shown in the conclusion upon the substituted finding.

That provision for the removal of the cofferdams which provided that the coffers “ and their belongings ” should be removed at the cost of the contractors must be construed to exclude the deposits banked against the face of either cofferdam by freshets to such an extent as in the judgment of the engineer interfered with the construction of the work. These accumulations can not be said to be part of the belongings of a cofferdam within the meaning of the contract.

Error of fact and law is alleged in the sixth finding where three inspections of certain stone needed in the work were had, and in support of the motion it is alleged that the inspection referred to as the second preliminary examination was the inspection required by paragraph 111 of the contract and was final; and error of law is alleged in not rendering-judgment for the claimants for the amount of stone delivered and charged to have been accepted at higher classifications and subsequently reinspected and used at lower classifications.

It is contended that the court has adopted in this finding a different theory of inspection from that provided by the contract and has enforced upon the claimants a system of inspection by which they never agreed to be bound; that the contract provided for only one inspection and the results of that inspection are in general binding upon both parties.

[563]*563Paragraph 111 of the contract provided that the Government should keep inspectors on the work, who would receive instructions from the resident engineer, with power to object to any material, work, or workmanship. Any material, work, or workmanship so objected to by the inspector was to be kept out of or removed from the finished work unless in each particular case the objections of the inspector should be overruled by the local or- resident engineer. By paragraph 81 any stone chipped or spalled after being set should be rejected, or measured and paid for at a cheaper classification, as the engineer might elect. Stones having defects concealed by cement or otherwise were required to be rejected on that account alone. By paragraph 115 payments were to be made monthly when funds were available. But no payments were to be made for material until actually in place in the work and after being inspected and accepted.

From the foregoing it will be seen that there were two exceptions to the geheral rule claimed under paragraph 111. These exceptions are set forth under paragraph 115, which were for the benefit of the contractors; the other, under paragraph 81, for the benefit of the Government. But specification 109 provided that the work should be conducted under the direction of the local or resident engineer, who should have power to prescribe the order and manner of executing the same in all its parts; of inspecting and rejecting materials, work, and workmanship which in his judgment did not conform to the drawings that might be furnished from time to time or to the specifications. This was the material, work, or workmanship which when rejected was to be kept out of or removed from the finished work. The finding shows that the resident engineer ordered three inspections made of the stone previous to its being set in place in the walls, and that the first inspection was in the interest of the contractors in order that they might be saved the expense of cutting stone which might afterwards be rejected for the purposes for which it was cut. The second preliminary examination was for the purpose of ascertaining whether the stones had been properly cut and were square and whether any latent defects had been developed [564]*564by the cutting. The third and final inspection was made for the purpose of ascertaining the general fitness of the stone to go into the wall.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hatfield v. Department of Highways
15 Ct. Cl. 295 (West Virginia Court of Claims, 1985)
Electric Fireproofing Co. v. United States
39 Ct. Cl. 307 (Court of Claims, 1904)

Cite This Page — Counsel Stack

Bluebook (online)
43 Ct. Cl. 525, 1908 U.S. Ct. Cl. LEXIS 18, 1907 WL 876, Counsel Stack Legal Research, https://law.counselstack.com/opinion/zimmerman-v-united-states-cc-1908.