Zimmerman v. Planning Board
This text of 294 A.D.2d 776 (Zimmerman v. Planning Board) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
Appeal from a judgment of the Supreme Court (Ceresia, Jr., J.), entered January 24, 2001 in Rensselaer County, which, in a proceeding pursuant to CPLR article 78, dismissed the petition as time barred.
[777]*777Petitioners live directly adjacent to a business park developed by respondent British American Capital Corporate Campus LLC in the Town of Schodack, Rensselaer County. In this CPLR article 78 proceeding filed on November 17, 2000, they purport to challenge an October 16, 2000 decision of respondent Planning Board of the Town of Schodack approving the site plan for an office building then proposed for construction on certain lots in the business park. After respondents raised statute of limitations defenses in their respective answers, Supreme Court dismissed the petition and denied a preliminary injunction against construction of the building. In addition to finding other infirmities in the proceeding, the court, in a thorough and well-reasoned decision, dismissed it as time barred. On appeal, we have little to add to Supreme Court’s analysis.
A fair reading of the petition, the affidavits in support thereof and petitioners’ briefs on appeal reveals that the gravamen of their complaint concerns the location of the main access road to the business park and not the site plan of the subject office building, which was proposed for lots on the opposite side of the road from their property.1 Specifically, petitioners contend that the access road has been constructed too close to their residence in violation of the terms of an environmental impact statement adopted by respondent Town of Schodack. It is incontrovertible that the precise location of this road was determined by a subdivision plat which was approved by the Planning Board on January 4, 1999.
Even if we were to assume, arguendo, that the impact of this particular decision was unknown to petitioners, the exact location of the road and its obvious proximity to their home was certainly apparent as early as November 30, 1999, when its construction was substantially complete. Moreover, the record confirms that petitioner Regina Zimmerman had actual knowledge of the road’s location as of June 19, 2000. On that date, she was in attendance at a Planning Board meeting and complained about the glare from cars in her house. Notwithstanding, this proceeding was not commenced until November 17, 2000, over 22 months after the subdivision plat was approved, nearly a year after the road itself was constructed and nearly five months after the Planning Board meeting at which their objections were voiced. Because the alleged harm from [778]*778which petitioners suffer is clearly the location of the access road and because petitioners did not timely contest same, Supreme Court correctly dismissed this proceeding as time barred (see, Town Law § 282; Matter of Save the Pine Bush v Town Bd. of Town of Guilderland, 272 AD2d 689, 692; see also, CPLR 217).2
As a final matter, certain arguments raised for the first time in petitioners’ reply brief are not properly before this Court (see, Fishman v Beach, 237 AD2d 705, 706) and all remaining contentions have been considered and found to be without merit.
Cardona, P.J., Crew III, Spain and Rose, JJ., concur. Ordered that the judgment is affirmed, with costs.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
294 A.D.2d 776, 742 N.Y.S.2d 431, 2002 N.Y. App. Div. LEXIS 5439, Counsel Stack Legal Research, https://law.counselstack.com/opinion/zimmerman-v-planning-board-nyappdiv-2002.