Zimmerman v. Bogoff

524 N.E.2d 849, 402 Mass. 650
CourtMassachusetts Supreme Judicial Court
DecidedJune 22, 1988
StatusPublished
Cited by97 cases

This text of 524 N.E.2d 849 (Zimmerman v. Bogoff) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Zimmerman v. Bogoff, 524 N.E.2d 849, 402 Mass. 650 (Mass. 1988).

Opinion

Lynch, J.

This case involves the mutual obligations of parties to a joint venture and fellow shareholders in a close corporation. The issue of the proper remedy for a breach of those duties is also present. We also consider whether the plaintiff Atlas Design & Manufacturing Co., Inc. (Atlas Design), makes out a claim for violation of G. L. c. 93A, and whether the judge should have awarded prejudgment interest.

The defendant, Lester H. Bogoff, and the plaintiff, Robert L. Zimmerman, are 50% shareholders in BAB Atlas, Inc. (BAB Atlas), a Massachusetts close corporation, which since has failed. As a result of various disputes between the parties, *652 described in detail below, Zimmerman brought suit in Superior Court against Bogoff alleging, inter alla, that Bogoff had violated fiduciary duties owed to Zimmerman and had violated G. L. c. 93A. Later Atlas Design, Zimmerman’s wholly-owned corporation and a coplaintiff here, brought suit against Bogoff and BAB Atlas in District Court alleging, inter alla, breach of contract, violation of c. 93A, and deceit. The cases were consolidated for trial and heard without a jury in the Superior Court. The judge found in favor of Zimmerman and Atlas Design and ordered Bogoff to pay a total of $284,680.30 in damages plus interest and costs. Judgment was entered accordingly and Bogoff and Atlas Design appealed. 3 We took the case here on our own motion. We affirm.

Proper understanding of this case requires a somewhat detailed recitation of the facts. Zimmerman was at all times relevant here the founder and sole shareholder of Atlas Design, a machine shop located in Agawam. The defendant Bogoff was sole shareholder of two corporations, BAB Transfer, Inc. (BAB Transfer), and BAB Warehouse, Inc. (BAB Warehouse). The former corporation was engaged in the business of trucking and heavy hauling; the latter was a warehousing business. Both businesses operated from a building in Springfield owned by Bogoff.

In 1975, it came to Bogoff’s attention that a concern in Vermont required a certain piece of large machinery. Bogoff’s corporations possessed the space and equipment necessary to assemble and transport the machinery to the customer, but lacked the requisite design expertise and manufacturing capabilities. These latter qualifications, however, were ones which Atlas Design could provide.

Accordingly, Bogoff approached Zimmerman and proposed that the two contribute their own skill and effort and the particular attributes of their respective corporations to accomplish *653 the job. Zimmerman agreed and a new corporation, BAB Atlas, Inc., was formed, in which Bogoff and Zimmerman were each 50% shareholders. Bogoff and Zimmerman constituted the entire board of directors. Officers were Bogoff as president and Zimmerman as treasurer. The order for the Vermont company was completed in 1976.

The parties then resolved to go into the business of manufacturing metal castings. In order to do this, they required a new type of machinery, known as “computerized numerically controlled” (CNC) machinery. It was agreed that Bogoff, through his corporations, would purchase CNC machinery and lease it to BAB Atlas. 4 Bogoff’s corporations were also to carry out administrative work, such as billing, bookkeeping, and collections. As a result, the judge found that Bogoff “control[led] the purse strings of the enterprise . . . .” Atlas Design, for its part, would use its reputation to attract customers and then perform the actual manufacturing work, billing BAB Atlas therefor “at cost” — a term which apparently was never explicitly defined. 5 The metal castings venture did not succeed; BAB Atlas was running at a $41,300 annual deficit by the end of 1978.

At about this time, Bogoff questioned the amounts due from BAB Atlas to Atlas Design for the latter’s “at cost” production of the castings. Zimmerman had been billing BAB Atlas at a “shop rate” (labor costs plus 100% for overhead) of between $12 and $17 per hour. The rate as computed by Bogoff was substantially lower. Beginning in December, 1978, Bogoff caused BAB Atlas to pay Atlas Design using his computation rather than Zimmerman’s. As a result, over the course of the *654 next year, Bogoff caused BAB Atlas to withhold from Atlas Design a total of $100,471.51, reflecting the difference between the amount billed on Atlas Design’s invoice and the amount Bogoff believed he should pay. The judge found that Zimmerman’s calculation of the “shop rate” was “reasonable and realistic.” As of December 1, 1979, Bogoff admitted that BAB Atlas also owed Atlas Design some $80,000 in other charges, but, Bogoff contended, BAB Atlas did not have the funds to pay these charges.

The impact of these unpaid amounts on Atlas Design was severe. By the end of 1979, Atlas Design had fallen behind in payment of its withholding taxes to the Internal Revenue Service and in its loan payments on its machinery and equipment. The Internal Revenue Service threatened to padlock the shop and the bank threatened to foreclose its security interest in Atlas Design’s machinery and equipment. Had these threats been carried out, the judge found, Atlas Design would have lost approximately $300,000 worth of work in progress.

In order to avoid these problems and to complete the work in progress, on December 8, 1979, Bogoff and Zimmerman met and agreed as follows: that the CNC machines leased to BAB Atlas and any necessary “back-up” machinery owned by Atlas Design would be moved out of Atlas Design’s shop to Bogoff s building in Springfield; that BAB Atlas would rent the Atlas Design-owned machinery from Atlas Design at a rental sufficient to stave off foreclosure from Atlas Design’s bank; that BAB Atlas would employ as many of Atlas Design’s workers as necessary to complete the work in progress; and that the dispute over the proper formula for calculating the “shop rate” would be negotiated.

As a result of this agreement, the Atlas Design operation was moved to Bogoff s building in Springfield, some of Atlas Design’s employees were taken on to finish the work in progress, and Bogoff caused BAB Transfer to loan sufficient funds to BAB Atlas to keep it in operation. However, Bogoff reneged on his agreement to have BAB Atlas pay rent for Atlas Design’s machines, and negotiations over the “shop rate” failed. Without the rentals from BAB Atlas, Atlas Design was unable to meet its *655 bank payments and, at a meeting involving the principals, their attorneys and Atlas Design’s bank, the bank announced that it was accelerating the due date of the principal amount of the loan. Attempts to reach an accommodation with the bank failed.

On February 20, 1980, while Bogoff was in Puerto Rico, Zimmerman removed Atlas Design’s machinery from the Springfield location and sold it at auction. The proceeds were distributed among the bank, the Internal Revenue Service, and

Atlas Design’s other creditors. Zimmerman himself received nothing. Upon his return from Puerto Rico, Bogoff purchased new equipment, and resumed the work in progress after a month’s delay.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Williamson v. Barlam
Massachusetts Appeals Court, 2024
Clemente v. Martinelli
102 N.E.3d 1030 (Massachusetts Appeals Court, 2018)
Koshy v. Sachdev
477 Mass. 759 (Massachusetts Supreme Judicial Court, 2017)
Butler v. Moore
246 F. Supp. 3d 466 (D. Massachusetts, 2017)
Wodinsky v. Kettenbach
22 N.E.3d 960 (Massachusetts Appeals Court, 2015)
Weiler v. PortfolioScope, Inc.
469 Mass. 75 (Massachusetts Supreme Judicial Court, 2014)
Estate of Moulton v. Puopolo
5 N.E.3d 908 (Massachusetts Supreme Judicial Court, 2014)
Selmark Associates, Inc. v. Ehrlich
467 Mass. 525 (Massachusetts Supreme Judicial Court, 2014)
Weiler v. PortfolioScope, Inc.
982 N.E.2d 555 (Massachusetts Appeals Court, 2013)
A.C. Vaccaro, Inc. v. Vaccaro
955 N.E.2d 299 (Massachusetts Appeals Court, 2011)
Targus Group International, Inc. v. Sherman
922 N.E.2d 841 (Massachusetts Appeals Court, 2010)
One to One Interactive, LLC v. Landrith
920 N.E.2d 303 (Massachusetts Appeals Court, 2010)
Pointer v. Castellani
455 Mass. 537 (Massachusetts Supreme Judicial Court, 2009)
McLaughlin v. Schenck
2009 UT 64 (Utah Supreme Court, 2009)
Cespedes v. C&C Construction Corp.
25 Mass. L. Rptr. 85 (Massachusetts Superior Court, 2008)
Renovator's Supply, Inc. v. Sovereign Bank
892 N.E.2d 777 (Massachusetts Appeals Court, 2008)
Massachusetts Property Insurance Underwriting Ass'n v. Georgaklis
24 Mass. L. Rptr. 266 (Massachusetts Superior Court, 2008)
McCormick v. Dunn & Black, PS
167 P.3d 610 (Court of Appeals of Washington, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
524 N.E.2d 849, 402 Mass. 650, Counsel Stack Legal Research, https://law.counselstack.com/opinion/zimmerman-v-bogoff-mass-1988.