Zequeira v. Municipal Housing Authority

83 P.R. 847
CourtSupreme Court of Puerto Rico
DecidedNovember 22, 1961
DocketNo. 12378
StatusPublished

This text of 83 P.R. 847 (Zequeira v. Municipal Housing Authority) is published on Counsel Stack Legal Research, covering Supreme Court of Puerto Rico primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Zequeira v. Municipal Housing Authority, 83 P.R. 847 (prsupreme 1961).

Opinion

Mr. Justice Belaval

delivered the opinion of the Court.

We are agreed with the trial court that in this case contractor Zequeira was bound to make the finishings on the concrete surfaces of the buildings of Luis Lloréns Torres project, pursuant to the interpretative letter of September 15, 1950 and not in accordance with the contract signed by the parties on September 12, 1950. The finding of fact that “when the contractor terminated the construction of the walls ■of buildings C-E, 9-E, and 10-B and submitted them to the •defendant Authority for inspection and acceptance and in ■order that it could certify that the corresponding work was terminated, the supervising engineer of the construction and ■defendant’s representative in that project informed the plaintiff that he could not accept them, and that before accepting [849]*849them they had to be finished as required in the description of the interpretative letter of September 15, 1950,” is the most correct version of the evidence admitted on this point. The plaintiff proceeded to make the finishings on the concrete surfaces of the remaining buildings as required by the defendant.

We are likewise agreed with the trial court that this action has not prescribed, regardless of whether we consider the time limitations provided in the contract for the different claims or the periods of ordinary civil prescription for actions derived from the implied obligations or from the unjust enrichment.

We are further agreed with the trial court that pursuant to § 1240 of the Civil Code of Puerto Rico, 81 L.P.R.A. § 3478, “the interpretation of obscure stipulations of a contract must not favor the party occasioning the obscurity,” particularly in the case of the so-called adhesion contracts, i.e., those contracts in which only one of the parties prescribes the conditions of the contract to be accepted by the other, a situation typical of a public-works contract in which the general conditions are embodied in a model or form prepared beforehand by the property owner.

The fact that this is the contract between the State and an individual is no exception. According to the holding in the case of Rodríguez v. Municipality, 75 P.R.R. 449, 464 (Belaval, 1953), “When a government has a contract with an individual, it must be construed as if it were one between individuals: United States v. Smoot, 15 Wall. 36, 21 L. Ed. 107 (Miller), (1873); The Amoskeg Manufacturing Company v. United States, 17 Wall. 592, 21 L. Ed. 715 (Miller), (1873); Reading Steel Casting Co. v. United States, 268 U.S. 186, 69 L. Ed. 907 (Butler), (1925)”. See, also, Lynch v. United States, 292 U.S. 571, 579, 78 L. Ed. 1434, 1440 (Brandeis, 1934); S.R.A. v. Minnesota, 327 U.S. 558, 564, [850]*85090 L. Ed. 851, 857 (Reed, 1946); Woodbury v. United States, 192 F.Supp. 924, 935 (Kilkenny, 1961).

We know that an adhesion contract presents the phenomenon of a reduction of the contractual bilaterality to the minimum. Or, as stated by Castán:

“The modern doctrine, as of Saleilles, has labelled adhesion contracts those contracts in which the contents, i.e., the regulatory conditions, are the doings of only one party, so that the other contracting party contributes nothing to the formation of the contractual contents, thereby substituting the usual bilateral determination of the contents of the bond by the mere act of accepting or adhering to the unilaterally predetermined plan.
“This type of contracts is linked to the economic phenomenon of the privileged position which, for different reasons (for example, in order to exercise a monopoly of law or of fact), one of the parties has with respect to the other. In this sense Messineo defines the contract of adhesion as a contract in which the economically strongest party imposes specific conditions or the full scheme of the contract, to his advantage and in detriment to the other contracting party who, being economically weaker, has no freedom of choice other than to accept those conditions or scheme or refuse to enter into the contract.
“Contracts of insurance, transportation, water, gas and electricity services, banking contracts, etc., are very frequent cases of adhesion contracts.
“With respect to such contracts, on which there is abundant literature, the problem of their juridical nature and of their effects and interpretation has been object of great concern.
“With respect to their nature, there have been doubts as to whether the adhesion contract is a true contract or rather a unilateral act or an act of a nonunitarian structure. However, the prevailing opinion decides the question in the former sense, based correctly on the fact that the adhesion implies consent and is sufficient for the formation of the contract.
“With respect to the effects, it is sought to determine — inasmuch as the grave dangers which, as compared with the indubitable advantages derived by the enterprises and even the general economy, by reason of celerity, uniformity, etc., the adhesion contracts cause the public are notorious — what pre[851]*851ventive measures or juridical, legislative, or judicial reaction may prevent the iniquities to which this type of contracts lends itself, securing the contractual equilibrium which the economic hegemony of the large enterprises tends to destroy.
“Modern legislation give us already an example of that legislative intervention by enacting general provisions limiting the effectiveness of the clauses unilaterally pre-established by the enterprises (see § § 1,341 and 1,342 of the new Italian Civil Code), or, simply, special provisions for specific contracts (for example, provisions on administrative fiscalization of insurance).
“It is more doubtful whether the judges have means, once the adhesion contracts are executed, to prevent the injustice done by them. It has been held that in such contracts the judge has an exceptional power of interpretation authorizing him not to apply the clauses of the contract except in consideration of the particular situation of the parties, and also^ the power to review which would authorize him to modify the contract in the portion which may appear to be unfair. But it would be very venturesome to presume that, in view of the silence of the law, a proper juridical nature may be attributed to adhesion contracts which will prevent the nonapplication to them of the general conditions of the contracts. Fortunately, in our law there 'is basis in the Civil Code for applying to the contracts in question a special rule of construction. Since the enterprise which prescribed the conditions of the contract is probably responsible for the inaccuracy or vagueness in its clauses, such enterprise must bear the consequences according to § 1288 (our § 1240).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Smoot's Case
82 U.S. 36 (Supreme Court, 1873)
Manufacturing Company v. United States
84 U.S. 592 (Supreme Court, 1873)
Reading Steel Casting Co. v. United States
268 U.S. 186 (Supreme Court, 1925)
Lynch v. United States
292 U.S. 571 (Supreme Court, 1934)
S. R. A., Inc. v. Minnesota
327 U.S. 558 (Supreme Court, 1946)
Woodbury v. United States
192 F. Supp. 924 (D. Oregon, 1961)

Cite This Page — Counsel Stack

Bluebook (online)
83 P.R. 847, Counsel Stack Legal Research, https://law.counselstack.com/opinion/zequeira-v-municipal-housing-authority-prsupreme-1961.