Zelinger v. Mellwin Construction Co.

225 P.2d 844, 123 Colo. 149, 1950 Colo. LEXIS 201
Supreme Court of Colorado·Decided December 18, 1950·No. 16507·Published·Cited by 2 cases

Opinion

Mr. Justice Stone

delivered the opinion of the court.

This matter is before us on motion to dismiss writ of error upon the ground, as asserted, that plaintiff in error in the trial court waived right to seek relief in an appellate court, and is estopped thereby.

Defendant in error, to which we shall refer herein as the Company, brought action against plaintiff in error Zelinger to recover damages arising out of a written contract for the construction of a commercial building and to foreclose a mechanic’s lien thereon. Zelinger filed *151 responsive answer and counterclaim. One Schrepferman, a building contractor, was appointed special master to take evidence, make findings of fact and conclusions of law, and report, the same to the court, together with a transcript of the evidence. After several days of hearings before the special master, it was orally stipulated and agreed between the parties and their counsel that the entire matter in dispute be submitted to arbitration by the special master as sole arbitrator; that his decision on the facts should be final; that he should make report of his findings of fact and recommendations to the court, and that legal questions might be submitted to the court for decision. It was further agreed to waive the “right of appeal” from the decision of the trial judge.

Pursuant to such stipulation, each of the parties presented detailed written statement of claims; the arbitrator then inspected the building constructed under the contract, determined from such inspection and from other evidence tendered and from his own expert knowledge, the items and amounts of damage and counterclaim, and made detailed findings and recommendations to the court.

Upon the filing of said findings, which were denominated “Findings of Fact,” but included also certain conclusions of law, as well as recommendations as to the allowance and amount of allowance of each claim and of the amount for which judgment should be entered, the court ordered “that October 8, 1949, be set as the date for the Court to approve the same.” Thereafter it was ordered that the cause be “set for hearing on October 17, A.D. 1949,” on which date Zelinger filed motion to rescind the order of reference and strike from the files the findings of fact by the special master and set the case down for trial, upon the ground that the order was improvidently entered and contrary to the rules of civil procedure and that the proceedings were contrary both to the order and the rules. This motion was heard on the date of its filing and, on October 21, 1949, was *152 denied. On October 27, 1949, the court entered further order that the special master’s findings of fact be approved and on the same date, upon, motion of Zelinger, it was ordered “that defendants deposit $350.00 in the Registry of the Court for the balance of costs of reporter’s transcript,” and “that the issuance of execution herein be, and the same hereby is, stayed until the 26th day of November, A.D. 1949, and defendants are granted permission up to that time to file petitions for rehearing.”

Thereafter on November 18, 1949, Zelinger filed “Motion for Extension of Time in Which to File Objections to- ‘Findings of Fact By the Special Master,’ ” reciting that the transcript of the evidence taken before the special master had been ordered and payment therefor deposited in the registry of the court, but that it had not yet been received, and that it was necessary to have and study such transcript in order to prepare objections to the findings -of fact. November 21, 1949, the court entered the following order: “Upon application of defendant, without prejudice to the words used in the motion for an extension of time, or former orders and findings of the Court, the Court extends the time heretofore set as November 26, 1949, up to and including December 23, 1949, * *

On November 29, 1949, the reporter’s transcript of proceedings before the special master was filed. Thereafter Zelinger filed “Motion for Extension of Time in Which to File Objections to ‘Findings of Fact By The Special Master,’ ” upon the ground that the transcript of evidence before the master consisted of 567 pages of detailed technical testimony; that the exhibits were voluminous and technical in character, and that counsel had not had opportunity for proper study of the same. This motion was denied on December 21, 1949, and thereupon the court ordered “that Arbitrator and Special Master’s report the judgment of Court, and orders attorney for plaintiff to prepare and submit for the *153 Court’s approval and signature a written Decree and Judgment.” On December 23, 1949, Zelinger filed “Objections To The So-Called ‘Findings of Fact By the Special Master,’ ” which consisted of fifty-six specific objections, including objections both to findings of fact and to legal conclusions of the arbitrator.

•On January 14, 1950, Zelinger filed motion that the cause be reassigned to another judge, on the ground that during a hearing in open court, on December 21, 1949, the judge to whom the case was assigned had stated “that he had participated with ‘Special Master’ Chester M. Schrepferman in the preparation of a document entitled ‘Findings of Fact by the Special Master,’ ” and that thereby he became biased in its favor and could not impartially render judgment thereon. On the same day the matter came on for hearing and the court first signed written findings and entered judgment in the total sum as recommended in the findings of fact of the special master and arbitrator i-n favor of the Company and against Zelinger; then stayed execution for thirty days, and finally granted the motion for reassignment of the cause.

Free access — add to your briefcase to read the full text and ask questions with AI

Zelinger v. Mellwin Construction Co., 225 P.2d 844, 123 Colo. 149, 1950 Colo. LEXIS 201 (Colo. 1950).

225 P.2d 844 (Zelinger v. Mellwin Construction Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Hart v. Orion Insurance
319 F. Supp. 1074 (D. Colorado, 1970)
Mellwin Construction Co. v. Zelinger
259 P.2d 612 (Supreme Court of Colorado, 1953)