Zaun v. Christman

CourtVermont Superior Court
DecidedDecember 22, 2025
Docket23-cv-1770
StatusUnknown

This text of Zaun v. Christman (Zaun v. Christman) is published on Counsel Stack Legal Research, covering Vermont Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Zaun v. Christman, (Vt. Ct. App. 2025).

Opinion

7ermont Superior Court Filed 10/27/25 Caledonia Unit

VERMONT SUPERIOR COURT ¥ Ek CIVIL DIVISION Caledonia Unit Case No. 23-CV-01770 1126 Main Street Suite 1 St. Johnsbury VT 05819 802-748-6600 .vermontjudiciary.org

Peter Zaun et al v. John Christman

FINDINGS, CONCLUSIONS, AND ORDER In this case, plaintiffs Peter and Dorene Zaun have brought a claim against defendant John Christman arising from John's allegedly defective work on a renovation project at plaintiffs' residence in West Burke. Plaintiffs seek damages for the cost to repair and complete the work, as well as attorney's fees. Following a site visit, the case came before the court for a two-day bench trial on June 17 and 18, 2025, after which the parties submitted post-hearing memoranda. For the reasons set forth below, the court will enter judgment for plaintiffs for $62,745. Plaintiffs' request for attorney's fees is denied.

Findings of Fact Plaintiffs have a "double-wide" home on property they own located at 822 Old Farm Road in West Burke. John is a contractor doing business as John Christman Construction, out of North Concord. In late 2020 or early 2021, plaintiffs contacted John to discuss a substantial renovation project for their home. Plaintiffs wanted to renovate their existing space and build an addition to add bedrooms for four grandchildren plaintiffs had recently adopted.

On or about January 11, 2021, John submitted a "work proposal" for the project, which entailed adding a two-car garage, an expanded living area above the garage with the additional bedrooms, an enlarged kitchen, and an expanded porch. The initial proposal quoted a price of $146,500. The proposal was never signed by the parties. The parties agreed John would perform the work and plaintiffs paid John a $15,000 down payment in March 2021. Before the work began, the parties agreed to expand the scope of the project to include removing and replacing the roof on the existing structure so that the entire living room and kitchen area would be covered by a new vaulted timber-frame ceiling. The parties also agreed that the interior walls of the home would be finished using shiplap. Peter, who is a logger, insisted on using lumber that he cut for the timber framing on the project, which he supplied to the job site. The lumber was sawed from trees cut the previous year. Plaintiffs had no significant construction experience and relied on John to perform the work in a professional manner. After some delays, plaintiffs paid JJohn a further deposit of $60,000 in late September 2021, and JJohn began work on the project several weeks later. Work continued with some stops

Findings, Conclusions, and Order Page 1 of 7 23-CV-01770 Peter Zaun et al v. John Christman and starts through December 2022. Although both parties contributed to the delays, a primary source of delay was plaintiffs’ need to sell a property that Peter had inherited so they could use the proceeds to pay John. Plaintiffs lived in the home while the project was underway. In advance of and continuing through John’s work on the project, John communicated primarily and extensively with Dorene through Facebook Messenger. Additional details about the project were discussed in these communications. By November 2021, the parties had agreed that the anticipated cost of the project had increased to $175,000, but John indicated that amount would not include any work in the basement or renovating the existing bedrooms and bathroom. On November 26, 2021, Dorene indicated that after the $175,000 was paid, she would “need a number” from John in order “to go to the bank” and get the money to “finish the whole house.” Def.’s Exh. A at 85. Approximately a month later, shortly after Christmas, Dorene confirmed with John that Peter was willing to spend money from his inheritance on the project and that plaintiffs wanted to finish the whole house. Around this time, Dorene also confirmed that plaintiffs wanted to install a large picture window facing Burke Mountain. Plaintiffs paid John $50,000 in November 2021 and an additional $50,000 in January 2022, which brough the total amount paid John to $175,000. John told Dorene this would likely be enough money to keep him working on the project through April. In or about March 2021, John built beds for plaintiffs’ grandchildren in the new addition at no additional charge. In May, Peter sawed out and delivered additional timber for the project. Although there was no formal agreement, the parties discussed in early 2022 that the cost to complete the project would be an additional $80,000 above the $175,000 already paid. Plaintiffs paid John and additional $20,000 or about May 22, and approximately one month later, John wrote to Dorene, “So you were at $80,000 and you gave me 20k so you are at $60k and yes I could use some more please?” Def.’s Exh. A. at 48. Plaintiffs paid John an additional $10,000 at the end of June 2022. Dorene noted that was all plaintiffs could afford at that time as they were still waiting to receive Peter’s inheritance. 1 Work on the project continued through the summer of 2022. In July, while the roof was under construction and tarped, water came into the house during a storm. John promptly addressed the issue. During this period John regularly checked in to see of Dorene was satisfied with the project, and Dorene consistently expressed satisfaction with the work being done. Things changed in September. The roof was not yet completed and was continuing to leak, causing mold and water damage on the interior of the house. Plaintiffs’ concerns began to mount. On September 29, 2022, Dorene reached out to John and requested a meeting to discuss completing the job, along with an accounting or itemization of the remaining $50,000 that the

1 Plaintiffs’ payment summary indicates an additional $10,000 payment was made to John on August 15,

2022, but the circumstances of that payment are not clear from the record.

Findings, Conclusions, and Order Page 2 of 7 23-CV-01770 Peter Zaun et al v. John Christman parties had previously discussed as being needed to complete the job. Dorene followed up on October 2 and raised additional concerns relating to the progress of the job, the motivation of John’s workers, and approaching winter without the roof being completed. Dorene reached out to John again on October 18, stating that the project needed to be completed as soon as possible and accused him of avoiding her. John continued to work on the project for the next several weeks, but then stopped, apparently because plaintiffs had not paid him. On November 13, Dorene wrote John that she thought Peter would be receiving his inheritance shortly and stated that she really wanted John to “finish trim in house, doors and siding,” and that if John gave her “a work schedule,” she would “get the money.” Def.’s Exh. A at 9. John said he agreed and had “figured once the closing was done and you guys had the money then I jump right back on it.” Id. at 8. On November 18, Dorene reached back out complaining about four windows John installed that were not locking or shutting completely and noted that it was getting too cold to install vinyl siding outside before winter, but that plaintiffs still wanted John to complete other work on the project, including inside trim and electrical work. She asked John how much money he needed to come back to work, and he responded that he “would like to get half of the 50k and then we can finish the siding in the spring.” Id. at 7. Plaintiffs paid John an additional $20,000 on or about November 25, 2022. After some delays related to COVID concerns, John and his crew completed the roof, and performed some electrical and other interior work, before stopping work for the winter in December 2023. John did not install the exterior siding, although he covered the plywood in membrane and taped the seams to protect from the weather.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Birchwood Land Company, Inc. v. Ormond Bushey & Sons, Inc.
2013 VT 60 (Supreme Court of Vermont, 2013)
VanVelsor v. Dzewaltowski
385 A.2d 1102 (Supreme Court of Vermont, 1978)
Rothberg v. Olenik
262 A.2d 461 (Supreme Court of Vermont, 1970)
Fletcher Hill, Inc. v. Crosbie
2005 VT 1 (Supreme Court of Vermont, 2005)
Lamell Lumber Corp. v. Newstress International, Inc.
182 Vt. 282 (Supreme Court of Vermont, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
Zaun v. Christman, Counsel Stack Legal Research, https://law.counselstack.com/opinion/zaun-v-christman-vtsuperct-2025.