Zarrs v. Keck

58 N.W. 933, 40 Neb. 456, 1894 Neb. LEXIS 301
CourtNebraska Supreme Court
DecidedMay 2, 1894
DocketNo. 5466
StatusPublished
Cited by4 cases

This text of 58 N.W. 933 (Zarrs v. Keck) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Zarrs v. Keck, 58 N.W. 933, 40 Neb. 456, 1894 Neb. LEXIS 301 (Neb. 1894).

Opinion

Ragan, C.

On the 25th day of May, 1889, Mrs. Samantha Keck was the owner of certain real estate in the city of Kearney, Nebraska, and upon said date she entered into a written contract with one Arthur Campbell. By the terms of this contract Campbell agreed to furnish all material and labor and erect for Mrs. Keck an annex to her hotel in said city. The hotel was to be completed by the 1st of October, 1889. As a consideration for the performance of his contract Campbell was to be paid $25,800. These payments were to be made in instalments on the first days of July, August, September, and October, each payment to be equal to eighty per cent of the value of the material and labor furnished the preceding month. The contract further provided : “It being understood that the final payment is to be made within twenty days after this contract is completely finished; provided, * * * that before each payment, if required, the contractor shall give the owner good and sufficient evidence that the premises are free from [458]*458all liens and claims chargeable to said contractor; and the owner shall have the right to retain, out of any payment then due or thereafter to become due, an amount sufficient to completely indemnify her against such lien or claim. After all such payments are made, the contractor shall refund to the owner all moneys that the latter may have been compelled to pay in discharging any lien on said premises made obligatory in consequence of the former’s default. The contractor hereby covenants and agrees that all materials and labor used in said building shall be promptly paid for, so that the same shall not become the subject of a lien against said premises; * * * that he will, before each and every instalment shall become due on this contract, and before he shall be entitled to the same, furnish to the owner satisfactory written evidence that all materials furnished for and used in said building up to such time, and all labor performed thereon, has been fully paid for; and the said contractor shall not be entitled to receive, nor shall the owner be required to pay, any instalments of this contract until all obligations for labor and materials which may become the subject of a lien upon said premises shall have been fully paid and settled; * * and the owner shall have the right to retain, out of any payment due or to become due, an amount sufficient to completely indemnify her against any lien or claim for materials or labor.” There was a further provision in the contract that Mrs. Keck should be entitled to damages at the rate of $20 a day for each day that the hotel remained unfinished after the first of October. To secure the faithful performance of this contract on his part Campbell executed a bond to Mrs. Keck in the sum of $25,000, signed by himself as principal and several others as sureties, among them, Henry Zarrs, the appellee in this case. Campbell sublet the excavating, masonry, and stone-work and plastering to the said Henry Zarrs under a written contract between them, in and by which Zarrs agreed to have all [459]*459the work in his contract, except the plastering, wholly completed by August 1, and to have the plastering completed by August 15. Zarrs sublet the plastering to Peterson & Ryan, and they bought of Spooner R. Howell the materials for the plastering.

This suit was brought by Henry Zarrs against the said Samantha Keck, Arthur Campbell, Spooner H. Howell, and Peterson & Ryan to have established, by decree of court, a lien which he claimed against the said hotel for labor and material furnished therefor under his contract with Campbell, and also to establish a lien against the property for some extras which he alleges he furnished for said hotel on an oral contract made with Mrs. Keck. During the progress of the trial, however, it was shown that this claim for extras had been settled and compromised before the bringing of this suit, and it will not be further noticed. Mrs. Keck and Mr. Campbell answered the petition of Zarrs. Peterson & Ryan filed an answer, in the nature of a cross-bill, claiming a balance due them of $760, for labor and material furnished in the erection of the hotel in pursuance of the contract with Zarrs, and prayed that the same might be declared a lien on the premises of Mrs. Keck. Howell filed an answer, in the nature of a cross-bill, claiming a balance due him of $391.94, for material furnished by him to Peterson & Ryan and used by them in the plastering of said building, and prayed that the same might be made a lien upon the premises of Mrs. Keck. Neither Campbell nor Mrs. Keck filed any answer whatever to the cross-petitions of Peterson & Ryan or Howell. The court below rendered a decree in favor of Howell, Peterson & Ryan, and Zarrs, and made the amounts found due those parties liens upon the premises of Mrs. Keck. From this decree Arthur Campbell and Mrs. Keck appeal.

1. We will first dispose of the appeal of Campbell. His objection to the decree is thus stated by his learned counsel in their brief: “We cannot escape the suspicion [460]*460that in the interval which elapsed between the trial of the-case and its final decision the learned judge had forgotten the controversy made by the pleadings and evidence between the plaintiff and the defendant Campbell, and overlooked the same in making his finding.” Zarrs in his petition claimed that there was a balance due him from Campbell, for labor and material furnished, of $3,398, but. on the trial it was clearly made to appear, and conceded by Zarrs, that that amount should be reduced to at least. $2,368. The court, by its decree, allowed Campbell $1,606. The court made no special findings, and the evidence as to-the merits of the respective claims of Zarrs against Campbell and Campbell against Zarrs was conflicting. Campbell resisted, both by his pleadings and evidence, the claim made by Zarrs and sought to set off as against the claims of Zarrs damages for alleged inferior workmanship and material furnished by Zarrs; damages for delay in not completing his work at the time agreed in his contract. He also pleaded certain payments had been made to Zarrs which should go to reduce the amount claimed by the latter, and finally he claimed that instead of his being in debt to Zarrs the latter owed him $1,606, for which he prayed judgment. We cannot say, after a careful reading of this evidence, that the district court was wrong in finding that Campbell was indebted to Zarrs in the sum of $1,606, and since it does not affirmatively appear that this finding is not supported by competent evidence we decline to disturb it.

2. We now proceed to the consideration of the objections urged by Mrs. Keck to the findings and decree. She objects to the decree and finding in favor of the appellee Howell on this ground : That since it appears from the record that the claim of Howell is for material furnished by him to a subcontractor of a subcontractor, therefore Howell is not entitled under the statutes of the state to a lien for the value of the materials so furnished. In Livesey v. Brown, 35 Neb., 111, it is said: “Under the me[461]*461chanic’s lien law of this state, the person who furnishes any material for the construction of a building by virtue of a contract, express or implied, with the owner thereof, is entitled to a lien thereon for the amount due for the same,” upon complying with the statute. And in Pomeroy v. White Lake Lumber Co.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

ASARCO v. Union Pacific Railroad Company
762 F.3d 744 (Eighth Circuit, 2014)
Vince Kess, Inc. v. Krueger Construction Co.
276 N.W.2d 669 (Nebraska Supreme Court, 1979)
Pere Marquette Railroad v. Baertz
74 N.E. 51 (Indiana Court of Appeals, 1905)
James R. Barnacle & Co. v. Henderson
60 N.W. 382 (Nebraska Supreme Court, 1894)

Cite This Page — Counsel Stack

Bluebook (online)
58 N.W. 933, 40 Neb. 456, 1894 Neb. LEXIS 301, Counsel Stack Legal Research, https://law.counselstack.com/opinion/zarrs-v-keck-neb-1894.