Zahra Rose Construction

CourtArmed Services Board of Contract Appeals
DecidedApril 13, 2022
DocketASBCA No. 62732
StatusPublished

This text of Zahra Rose Construction (Zahra Rose Construction) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Zahra Rose Construction, (asbca 2022).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of - ) ) Zahra Rose Construction ) ASBCA No. 62732 ) Under Contract No. W91B4N-20-P-0015 )

APPEARANCE FOR THE APPELLANT: Ms. Zahra Noori CEO

APPEARANCES FOR THE GOVERNMENT: Scott N. Flesch, Esq. Army Chief Trial Attorney LTC Abraham Young, JA Trial Attorney

OPINION BY ADMINISTRATIVE JUDGE SMITH

In this appeal, we resolve appellant Zahra Rose Construction’s (Zahra) challenge to respondent Army’s (the government) final decision regarding the termination for convenience after approximately two weeks of Zahra’s two-month $30,000 contract to lease fuel trucks in Afghanistan. The contracting officer’s final decision provided a $15,000 termination settlement under Federal Acquisition Regulation (FAR) 52.212-4(l) while Zahra claims that it is entitled to $30,400 because Zahra paid the owner of the trucks in advance for the full contract term in order to obtain the trucks. In response, the government disavows its $15,000 settlement decision and argues that Zahra is entitled to no settlement because the trucks did not meet the contract’s technical requirements. Alternatively, the government argues that if Zahra is entitled to any termination settlement, it should be no more than $6,300 based upon a 12-day pro-rata calculation. For the reasons discussed below, we find that Zahra is entitled to a termination settlement of $28,800, which Zahra has sufficiently demonstrated it reasonably incurred prior to termination. We sustain the appeal in the amount of $28,800, but deny the appeal for the remainder of Zahra’s claim. FINDINGS OF FACT

After a brief negotiation by email between September 2 and September 4, 2020 (app. supp. R4, tab 1 at 35, 40; tab 10; tab 16; tabs 27-29), Zahra’s sole-source Contract No. W91B4N-20-P-0015 (the contract) was executed on September 4 by Zahra and on September 7 by the government (app. supp. R4, tab 2 at 52; R4, tab 2 at 1). 1 The contract was 16-pages, commensurate with the cost and scope of a $30,000 lease of two fuel trucks (R4, tab 2 at 1, 3). The contract quantity was “2” and the units were “months.” (Id. at 3) The period of performance was also described as “04-SEP- 2020 TO 31-OCT-2020” (id.) and “03 September 2020 to 31 October 2020” (R4, tab 2 at 14). The pre-award price discussions were based on cost per truck per month (app. supp. R4, tabs 10, 27, 29).

In general, the contract required delivery of two 10,000-liter fuel trucks to Camp Antonik, Helmand Province, Afghanistan for use by the government (R4, tab 2 at 14-15; tab 19 at 9). Zahra was responsible for maintenance or repair of the trucks as needed, and retrieval of the trucks at the conclusion of the contract (id. at 3, 15-16).

The contract contained a list of approximately 24 technical requirements for the trucks, some related to fuel delivery functions (fuel pump capacity, specific nozzles, etc.), while others were safety items (seat belts, rear view mirror, etc.) (id. at 15).

The contract was a commercial items procurement, and incorporated the 2018 version of FAR 52.212-4 “Contract Terms and Conditions--Commercial Items” (id. at 4; see also id. at 1).

FAR 52.212-4(a), INSPECTION/ACCEPTANCE, provided:

“The Contractor shall only tender for acceptance those items that conform to the requirements of this contract. The Government reserves the right to inspect or test any supplies or services that have been tendered for acceptance. The Government may require repair or replacement of nonconforming supplies or reperformance of nonconforming services at no increase in contract price. . . . The Government must exercise its post-acceptance rights . . . within a reasonable time after the defect was discovered or should have been discovered . . . .”

FAR 52.212-4(a) (emphasis added).

The contract’s termination provision was FAR 52.212-4(l) and provided:

“The Government reserves the right to terminate this contract, or any part hereof, for its sole convenience . . . . [T]he Contractor shall be paid a percentage of the contract

1 All pertinent events took place in 2020, so for brevity we refer to dates by month and day. 2 price reflecting the percentage of the work performed prior to the notice of termination, plus reasonable charges the Contractor can demonstrate to the satisfaction of the Government using its standard record keeping system, have resulted from the termination. . . . The Contractor shall not be paid for any work performed or costs incurred which reasonably could have been avoided.”

FAR 52.212-4(l). 2

On the day that Zahra executed the contract, September 4, Zahra paid $28,800 in cash to Great America Construction Co. (GACC) for both trucks for two months (R4, tab 6 at 3). Zahra has indicated that, because of the short lease term, GACC required full payment in advance in order to provide the trucks (R4, tab 5 at 1).

Zahra began the delivery process on September 4 but was delayed by formidable procedures for getting vehicles, especially those capable of holding large amounts of fuel, through the security screening of two contiguous military bases in the region of Afghanistan where much of the hostilities occurred throughout the U.S. involvement (R4, tab 3; app. supp. R4, tabs 18-26).

On September 7, after several days in separate Afghan Army and U.S. Army holding areas, Zahra provided the last bit of information needed to complete the delivery (R4, tab 3 at 1). The government’s customer component (the U.S. Marine Corps) took possession of the trucks and inspected them on September 9 (R4, tab 4). A list of deficiencies was communicated internally within the government on the same day (id.), but there is no record that the list, or any concern about the functionality of the trucks, or any written acceptance or rejection of the trucks, was communicated to Zahra. Nor did the government terminate the contract for cause, or promptly invoke the inspection/acceptance provisions of the contract to reject the trucks, or seek to have Zahra remedy the deficiencies, all of which are actions contemplated by the contract for nonconforming items (R4, tab 2 at 4, 14-15; FAR 52.212-4(a)).

Based upon the fact that the trucks changed locations several times during the delivery process, coupled with the results of the government inspection and the two pictures of the trucks in the record (app. supp. R4, tab 15), we find that the trucks were generally operational albeit with the noted deficiencies.

2 The contract also contained an “Acceptance Inspection” clause similar to FAR 52.212-4(a) (R4, tab 2 at 14). The contract also had a “General” clause similar to FAR 52.212-4(l) that provided that the “Government reserves the right to turn in any vehicles deemed unnecessary at any time without penalty.” (R4, tab 2 at 15). 3 After September 9, there was a gap of approximately 13 days, until September 22, where the trucks’ location and use is not contemporaneously reflected anywhere in the record and has not been directly addressed by either party since then (R4, Index; app. supp. R4, Index). In fact, there is no evidence of any communication at all between the parties between September 9 and 22. (Id.)

On September 22, and still without any mention of the inspection or deficiencies, the government emailed Zahra that “[t]his contract is being terminated for convenience of the Government. You will be able to submit a settlement proposal. At this time the vehicles provided are no longer needed please pick up the vehicles as soon as possible.” (App. supp. R4, tab 3 at 1) As of September 22, no contract payment had been made or requested.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jacobs Engineering Group, Inc. v. United States
434 F.3d 1378 (Federal Circuit, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
Zahra Rose Construction, Counsel Stack Legal Research, https://law.counselstack.com/opinion/zahra-rose-construction-asbca-2022.