Youngstown Steel Erecting Co. v. MacDonald Engineering Co.

154 F. Supp. 337, 1957 U.S. Dist. LEXIS 3091
CourtDistrict Court, N.D. Ohio
DecidedSeptember 17, 1957
DocketCiv. A. 32540
StatusPublished
Cited by1 cases

This text of 154 F. Supp. 337 (Youngstown Steel Erecting Co. v. MacDonald Engineering Co.) is published on Counsel Stack Legal Research, covering District Court, N.D. Ohio primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Youngstown Steel Erecting Co. v. MacDonald Engineering Co., 154 F. Supp. 337, 1957 U.S. Dist. LEXIS 3091 (N.D. Ohio 1957).

Opinion

WEICK, District Judge.

This action originated in the Common Pleas Court of Cuyahoga County and was removed to this Court on the ground of diversity of citizenship.

The complaint sets forth a cause of action for damages for breach of contract.

The case was tried by the Court without a jury.

The defendant asserted two defenses, viz., (a) that there was no contract and (b) plaintiff suffered no damage.

Defendant was a Delaware corporation engaged in the designing and erecting of various types of structures. It was the general contractor under a contract with Bessemer Limestone & Cement Company for the design and construction of nine cement storage silos at Bessemer, Pennsylvania. The contract provided that defendant was to be paid the actual cost of construction plus a fixed fee.

Plaintiff was an Ohio corporation engaged in steel construction work with its principal place of business in Youngstown, Ohio. It had previous experience in the placing of steel reinforcing rods in concrete.

Plaintiff learned of the Bessemer job from Dodge construction reports to which it was a subscriber. It was interested in bidding on the subcontract for placing reinforcing steel rods in concrete. On or about July 1, 1954, plaintiff’s chief officers George Townsend and Albert De Perro called on defendant at the site of the construction work in Bessemer, Pennsylvania. They conferred with James W. MacDonald, President of the defendant company and Binar Bergman, its field superintendent.

After discussing the job and the experience of plaintiff’s chief officers, Mr. MacDonald furnished to Messrs. Townsend and De Perro the plans and specifications for their examination so that plaintiff might submit a bid for the [339]*339placing of the steel reinforcing rods. The work to be performed under the subcontract was principally labor. The material was to be furnished by defendant.

Plaintiff’s officers examined the plans and specifications and on July 6, 1955 mailed to defendant a written proposal for a subcontract “to place all the rods connected with Bessemer Lime Stone Co. [job] including the unloading. For the sum of $55.00 per ton. The Gen. Contractor to furnish all rods, wire, and chairs, also all other accessories.”

Defendant answered the proposal by letter, under date of July 8, 1955, as follows:

“We have your proposal for reinforcing steel on the Bessemer Limestone and Cement Company job covering the reinforcing in the silos. It is understood that we will furnish you the use of our hoist but you will operate it. We will also let you use our crane when available manned with an engineer and oiler but you will furnish all ground crews. In furnishing the rods, wire and chairs it is not contemplated that we will furnish the supports for the foundation slab steel. Whatever you want to support this steel you will furnish. We will furnish all other chairs and supports.
“Please advise us if this is your understanding.”

Plaintiff replied thereto on July 10, 1955 as follows:

“We accept all terms stated in your letter of July 8, 1955, covering the Bessemer Limestone & Cement Co. job. Bessemer, Pa. Thank you for your business.”

This letter was sent by registered mail and was received by defendant.

The above constituted the entire correspondence between the parties.

After receipt of the letter of July 10, 1955, and without notice to plaintiff, defendant proceeded to and did award the subcontract for placing the rods to Bruce Campbell Construction Company of Youngstown.

Plaintiff claims that the writings constituted a binding contract and that defendant breached it by awarding the subcontract to Bruce Campbell Construction Company and that it lost profits as a result thereof for which it claimed damages in the amount of $19,798.33.

It is elementary that in order to constitute a binding contract there must have been a manifestation of assent by the parties thereto. Restatement of the Law of Contracts § 19. There must have been a definite offer and an unequivocal acceptance of it. Restatement of the Law of Contracts § 32, § 58; 1 Williston on Contracts § 37, § 72.

All of the correspondence must be considered in determining whether a contract existed. Zehr v. Wardall, 6 Cir., 134 F.2d 805. Also the surrounding facts and circumstances should be taken into account for whatever light they might shed on the intention of the parties.

Plaintiff’s proposal of July 6, 1955 did constitute an offer. It was sufficiently definite so that an acceptance would have ripened into a binding contract.

Defendant’s letter of July 8,1955 was not’ an acceptance of plaintiff’s offer, but was a counter offer. Restatement of the Law of Contracts § 38, § 60; 1 Williston on Contracts § 77. It acknowledged receipt of plaintiff’s proposal and then stated “It is understood” that defendant would furnish its hoist, but plaintiff was to operate it. Permission was granted to plaintiff to use defendant’s crane together with the engineer and oiler when available, but plaintiff was to furnish all ground crews. Defendant further stipulated that in furnishing rods, wires and chairs it was not contemplated that defendant would furnish the supports for the foundation slab steel and that plaintiff would furnish whatever it wanted to support the steel. Defendant agreed to furnish other chairs and supports.

[340]*340Surely, defendant would not have enumerated all these items as constituting its understanding of the work which was to be performed if it was not otherwise accepting plaintiff’s proposal. While its letter enlarged the work to be performed, no question was raised about the contract price. Since defendant’s letter imposed additional terms, it was necessary that the counter offer be accepted before any contract would result. Defendant’s letter called for a reply as to whether this was plaintiff’s understanding.

Plaintiff promptly accepted the counter offer by its letter of July 10 and thanked defendant for the business.

If these letters did not constitute an agreement, as defendant now contends, defendant had ample opportunity to respond to plaintiff’s letter of July 10, and point out plaintiff’s alleged error in treating defendant’s letter of July 8 as constituting a counter offer. Defendant did not so respond, but remained silent and led plaintiff to believe that it had a contract.

Plaintiff did not learn otherwise until it visited the site of the job in order to find out when to start the work. It finally discovered that defendant had, without notice, awarded the subcontract to Bruce Campbell Construction Co.

Mr. MacDonald testified that the letter of July 10 arrived during his absence and that one of his subordinates put it in the file and he did not see it.

Mr. MacDonald further testified that when he received plaintiff’s letter of July 8, he concluded that the proposal was so low that plaintiff did not know what it was doing and he instructed his subordinates to award the subcontract to Bruce Campbell.

It is difficult to understand why defendant wrote the letter of July 8 if it had already determined to award the contract to another person.

Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Eaton v. Continental General Insurance
147 F. Supp. 2d 829 (N.D. Ohio, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
154 F. Supp. 337, 1957 U.S. Dist. LEXIS 3091, Counsel Stack Legal Research, https://law.counselstack.com/opinion/youngstown-steel-erecting-co-v-macdonald-engineering-co-ohnd-1957.