Yellowstone Valley Electric Cooperative, Inc. v. Montana Power Co.

822 P.2d 102, 251 Mont. 91, 48 State Rptr. 1068, 1991 Mont. LEXIS 303
CourtMontana Supreme Court
DecidedDecember 4, 1991
Docket91-374
StatusPublished

This text of 822 P.2d 102 (Yellowstone Valley Electric Cooperative, Inc. v. Montana Power Co.) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Yellowstone Valley Electric Cooperative, Inc. v. Montana Power Co., 822 P.2d 102, 251 Mont. 91, 48 State Rptr. 1068, 1991 Mont. LEXIS 303 (Mo. 1991).

Opinion

JUSTICE HARRISON

delivered the Opinion of the Court.

This is an appeal from the Thirteenth Judicial District Court’s order permanently enjoining the Montana Power Company (MPC) from providing electricity to ZooMontana of Billings, Montana. Involved is the District Court’s interpretation of Montana’s Territorial Integrity Act. The Territorial Integrity Act was adopted in 1971 to aid in the resolution of disputes between electric utilities and electric cooperatives in the event a question arose over which company would provide electrical service to new customers. We affirm.

The appellant, MPC, raises the following issue:

Did the District Court err in enjoining MPC from providing electricity to ZooMontana under Montana’s Territorial Integrity Act?

This Court is revisited with a question thought long ago well buried by the passage of the 1971 Montana Territorial Integrity Act. For some twenty years, commencing with Sheridan County Elec. Coop. v. Montana-Dakota Util. Co. (1954), 128 Mont. 84, 270 P.2d 742, to Montana Power Co. v. Sun River Elec. Coop., Inc. (1971), 157 Mont. 468, 487 P.2d 307, this Court struggled with numerous cases between the privately-owned electric companies and the electric cooperatives in Montana. The Territorial Integrity Act, now codified as §§ 69-5-101 et seq., MCA, was enacted to settle and bring to an end these types of cases in the courts of Montana. Like many pieces of legislation, the Territorial Integrity Act was a product of compromise and seemed to serve that purpose for some twenty years between the time when the last case was before this Court and the present time with the instant case.

The underlying facts of this case are the following:

ZooMontana is a non-profit corporation formed to build and operate a zoo on property located just west of the city limits of Billings, Montana. Following years of fund raising, ZooMontana began the actual construction of the zoo by erecting the education building on its land. Eventually, ZooMontana intends to build a number of buildings and animal exhibits on the property. The construction was to proceed in stages as the funding permitted.

On May 3,1991, MPC officials met with Yellowstone Valley Electric Cooperative, Inc., officials (the Cooperative) to discuss a number of issues. During that meeting, MPC informed the Cooperative that *93 ZooMontana had requested MPC to provide three-phase power for the education building. MPC stated it intended to supply the power because it had the right to do so under the Territorial Integrity Act of 1971. The Cooperative officials disagreed with MPC’s interpretation of the Act.

On May 8, 1991, the Cooperative’s general manager sent a letter to MPC which stated in part: “Our measurements show that our Cooperative’s electric facilities are closer to the proposed education building than MPCo’s.” There being no response to the letter, on May 24, 1991, MPC began extending its three-phase line to ZooMontana property. This construction was observed by a Cooperative official for nearly a week and when the line extension was completed to Zoo-Montana, the Cooperative, on May 30, 1991, obtained from the District Court an ex parte temporary restraining order and order to show cause which enjoined MPC from further construction of its facilities to ZooMontana.

The parties agree to the following: (1) that neither MPC nor the Cooperative would master meter the entire ZooMontana property at the entry point of each party adjacent to its respective three-phase service; (2) that ZooMontana property would utilize in excess of 400 kilowatts within two years and that the project eventually would use over 800 kilowatts; (3) that ZooMontana is a “commercial and industrial premises;” and (4) that the basic issue is the cost to each party of the three-phase line extension.

The District Court heard this matter in two hearings. After the first hearing it was agreed by both parties that the engineering firm of Schmidt, Smith and Rush (SSR Engineers, Inc.) would be appointed to determine the cost of the extension. SSR Engineers, Inc., submitted its report to the court dated June 14, 1991, wherein it set forth the estimated costs.

The District Court found in its Findings of Fact No. 7 as follows:

“7.Pursuant to Section 69-5-106(2) MCA, the parties agreed to an independent consultant engineer, SSR Inc. Engineers, to determine whether [the Cooperative] or MPC can extend its lines to the customer, ZooMontana, at the least cost. SSR’s report (Plaintiff’s Exhibit 3) was made with several presumptions and concluded that:
“(a) the cost to MPC to extend its three phase line prior [sic] from an extension of that line commenced by construction on May 24,1991, and restrained by [the District Court] by order dated May 31, 1991, to the education building is $24,136.43;
*94 “(b) the cost to MPC to extend its three phase line from the ending point after the extension referred to in paragraph 7(a) to the education building is $14,622.46;
“(c) the cost to MPC to extend its three phase line to the Zoo-Montana property line is $16,319.49;
“(d) the cost to [the Cooperative] to extend its three phase line to the education building is $28,348.86;
“(e) the cost to [the Cooperative] to extend its three phase line to the ZooMontana property line is $6,092.45.”

The District Court in its Conclusions of Law Nos. 3 and 4 stated:

“3. Since the parties agree that the ZooMontana property is a commercial premises with a need of 400 kilowatts or larger within two years and since either party can extend its lines to the user without any cost for the extension, the issue is whether MPC as an electric utility is entitled to priority because it can under the statute ‘... extend its lines to such industrial or commercial premises at less cost to the electric utility ...’.
“4. Section 69-5-102(7) MCA. defines ‘premises’ as:
“ ‘Premises’ means a building, residence, structure, or facility to which electricity is being or is to be furnished; provided, that two or more buildings, structures, or facilities which are located on one tract or contiguous tracts of land and are utilized by one electric consumer for farming, business, commercial, industrial, institutional, governmental, or trailer court purposes shall together constitute one premises, except that any such building, structure, or facility, other than a trailer court, shall not, together with any other building, structure, or facility, constitute one premises if the electric service to it is separately metered and the charges for such service are calculated independently of charges for service to any other building, structure, or facility.”
“The premises of the ZooMontana property within the meaning of this statute is the property line of the property.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Montana Power Co. v. Sun River Electric Cooperative, Inc.
487 P.2d 307 (Montana Supreme Court, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
822 P.2d 102, 251 Mont. 91, 48 State Rptr. 1068, 1991 Mont. LEXIS 303, Counsel Stack Legal Research, https://law.counselstack.com/opinion/yellowstone-valley-electric-cooperative-inc-v-montana-power-co-mont-1991.