Yehle v. Stamey-Tidd Construction Co.

94 P.2d 328, 150 Kan. 440, 1939 Kan. LEXIS 306
CourtSupreme Court of Kansas
DecidedOctober 7, 1939
DocketNo. 34,381
StatusPublished
Cited by7 cases

This text of 94 P.2d 328 (Yehle v. Stamey-Tidd Construction Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Yehle v. Stamey-Tidd Construction Co., 94 P.2d 328, 150 Kan. 440, 1939 Kan. LEXIS 306 (kan 1939).

Opinions

The opinion of the court was delivered by

Dawson, C. J.:

This action originated as a proceeding under the workmen’s compensation act. On March 10, 1937, the respondent construction company was engaged in digging a sanitary sewer. The appellant, one of its workmen, was employed in operating its excavator. By some mishap a crane carrying a load of tile was swung over his head; then something broke and he was hit on the head and knocked unconscious, and his collar bone, right shoulder and back were injured.

Without any ado his employer began paying him compensation at the rate of $14.40 per week and so continued until June 2, a period of [441]*44112 weeks, a total of $172.80. On June 4 appellant filed a formal claim for compensation. A hearing was held thereon on July 15, at which time respondent paid him five weeks’ additional compensation, $72. The examiner for the commission found that claimant was still suffering from his injuries and was under temporary total disability and entitled to compensation at the rate of $9 per week for a further period of 26 weeks, which aggregated compensation payments for 43 weeks altogether. This award was made accordingly by the compensation commission on July 27, 1937.

A month later a stipulation and agreement on behalf of claimant and respondents was filed with the commission reciting in brief the substance of the foregoing award and alleging that—

“The claimant is desirous of making a lump-sum settlement of 95% of the balance ($153) still due and owing on said award, and the respondent and the insurance carrier are willing to pay 95% of said $153 balance of award” — to wit, $145.35.

It was further stipulated that this lump-sum settlement was being made at the request of the claimant.

On August 28, 1939, the compensation commission made an order incorporating these antecedent details, and continuing thus:

"Now, therefore, the commissioner being duly advised in the premises, is of the opinion that the award heretofore made on July 27, 1937, should be modified in accordance with the agreement of the parties.
“Wherefore, the award heretofore made on July 27, 1937, be and the same is hereby modified to an award of one hundred forty-five and 35/100 ($145.35) dollars, and the agreement of the parties that same be paid in one lump sum is hereby approved; the award of July 27, 1937, to otherwise remain in full force and effect.”

Pursuant to this order, respondent paid the balance due thereon, also the hospital and medical expenses, $62.40, the regular fees of the commission, $25, and of its reporter, $48.50. The requisite receipts pertaining thereto were filed on September 8, 1937.

Some five months thereafter, on February 3, 1938, claimant filed with the compensation commission an application to reopen the proceedings summarized above and to set them aside on alleged grounds of mutual mistake, inadequacy of the award and his continued incapacity. This application was denied on February 10, 1938. The order of that date contains the following:

“The judgment of the commissioner is that at this time he has no jurisdiction in this matter, as the modification of award issued on August 31, 1937, became a finality when no appeal was taken within twenty (20) days.”

[442]*442On February 24, 1938, a second application was filed with the commission, in which claimant alleged that the stipulation and agreement which he signed on August 28, 1937, pursuant to which the compensation commissioner had entered the order modifying the award, was the result of a mutual mistake of fact, and that the lump sum paid him by respondents in accordance therewith and for which he had given a receipt was wholly inadequate; that instead of a temporary total disability of 43 weeks, as found by the commission, claimant was still totally disabled and would continue so to be for the rest of his life. Claimant’s application concluded with a prayer that the matter be set down for hearing touching the mutual mistake of fact, and for an award for total disability.

Respondents met this application with a motion to dismiss, giving a recital of all the antecedent proceedings, invoking the provisions of G. S. 1935, 44-528, and challenging the jurisdiction of the commission.

On March' 28, 1938, the commission, although adhering to its ruling of February 10,1938, laid aside for the time being the question of its further jurisdiction, and granted a hearing on claimant’s second application filed on February 24. By agreement of the parties the entire antecedent record and files of the claim, including the transcript of the evidence, were to be considered by the commission in this belated hearing. Claimant gave testimony of his continued total incapacity. Dr. Hunter Duvall testified that he had recently examined the claimant and had discovered no improvement in claimant’s physical condition, which, he said, was “pretty good evidence that (he, the witness) was wrong,” when at the previous hearing he had testified that claimant “would be well within a period of about six months.” At the earlier hearing Doctor Duvall had testified that the duration of claimant’s injury could not then be predicted. His earlier testimony had been: “The chances are the motion will increase as time goes on.” Also, at the earlier hearing, a Doctor Butler had testified that he thought claimant would be permanently disabled to some extent.

Two other doctors, who had given testimony at the former hearing, also testified to the claimant’s continued incapacity. But neither of the latter had given a positive opinion at the earlier hearing that claimant would fully recover in six months.

Respondents introduced no testimony further than what was in-[443]*443eluded by the stipulation that all the antecedent record was to be considered.

On April 6, 1938, the compensation commission denied the application of February 24, but in its order to that effect it added this recital:

“The evidence . . . discloses that claimant has not recovered from the injury received March 10, 1937, and is unable to return to his usual work or perform manual labor at this time; and claimant testifies that he had heard the testimony given by the doctors on July 15, 1937, and took their testimony and diagnosis of the case as correct, and felt that possibly within three to six months he would be able to return to his usual work, and entered into a lump-sum settlement.”

From this order denying claimant’s second application to set aside the original award and its modification and the lump-sum settlement, claimant appealed to the district court. Respondents filed a motion to dismiss, reciting all the pertinent facts and invoking G. S. 1935, 44-528.

In an opinion and decision rendered on January 12,1939, the trial court construed the statute in favor of claimant, but also held that “there is nothing before this court upon which it can base a finding of fact as to the (alleged) mutual mistake.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State ex rel. Arn v. Consumers Cooperative Ass'n
183 P.2d 423 (Supreme Court of Kansas, 1947)
Everett v. Kansas Power Co.
165 P.2d 595 (Supreme Court of Kansas, 1946)
Calonder v. F. H. Freeto Construction Co.
126 P.2d 209 (Supreme Court of Kansas, 1942)
Bailey v. Skelly Oil Co.
110 P.2d 746 (Supreme Court of Kansas, 1941)
Farr v. Mid-Continent Lead & Zinc Co.
98 P.2d 437 (Supreme Court of Kansas, 1940)
Clemons v. Wilson
98 P.2d 423 (Supreme Court of Kansas, 1940)

Cite This Page — Counsel Stack

Bluebook (online)
94 P.2d 328, 150 Kan. 440, 1939 Kan. LEXIS 306, Counsel Stack Legal Research, https://law.counselstack.com/opinion/yehle-v-stamey-tidd-construction-co-kan-1939.