Yant Construction Co. v. Village of Campbell

243 N.W. 77, 123 Neb. 360, 1932 Neb. LEXIS 210
CourtNebraska Supreme Court
DecidedJune 10, 1932
DocketNo. 28022.
StatusPublished
Cited by5 cases

This text of 243 N.W. 77 (Yant Construction Co. v. Village of Campbell) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Yant Construction Co. v. Village of Campbell, 243 N.W. 77, 123 Neb. 360, 1932 Neb. LEXIS 210 (Neb. 1932).

Opinion

Good, J.

This is an action to recover a balance alleged to be due on a contract for paving, curbing, guttering and graveling of certain streets in improvement district No. 1, in defendant village. Defendant admitted the making of the contract, part performance by plaintiff, and alleged payment of all the contract price except $1,800; further alleged that, by agreement between the parties, this amount was withheld by defendant until plaintiff should complete performance of the work contemplated by the contract, and that plaintiff never did complete the work it had contracted to perform. Defendant also alleged that'the work was neither commenced nor completed within' the time limit fixed by the contract, and that, by reason of a provision in the contract, defendant was entitled to withhold $200 a month for four months’ delay in completing the work; also that defendant had been compelled to expend *362 more than $1,000 to complete the work which plaintiff should have performed. By way of reply, plaintiff alleged that the contract was completely performed, the work accepted by defendant, and that defendant, having accepted the work, is now estopped to deny that it was completed in accordance with the terms of the contract. The trial resulted in a verdict and judgment thereon for defendant. Plaintiff has appealed.

The total amount that defendant agreed to pay plaintiff for the completed work contemplated by the contract was $20,041.78. The contract was entered into in June, 1925, and contained this clause: “The contractor agrees to start this work on or before July 15, 1925, .and to complete same on or before the 1st day of September, 1925, and to reimburse the Village of Campbell at the rate of $200 per month for any extra time that may be required to complete said work.”

The evidence discloses that plaintiff did not commence the work until about the 1st of September, 1925, and performed none after the latter part of December, 1925. There seems to be no question that the work of paving, curbing and guttering was properly performed. The controversy as to the uncompleted work relates solely to the graveling of certain streets.

There are numerous assignments of error, but plaintiff states in its brief: “The only real questions in this case are — (1) whether the contract at the time Yant left the job was fully performed and completed (notwithstanding that Yant had a man do a little more dragging to satisfy the Board) as shown by the testimony; and (2) whether its certificate of completion and acceptance as is contended estops the defendant from claiming otherwise; and (3) was there any legal authority under the evidence justifying the deduction of $800 of the money due the plaintiff from the provisions of the contract with reference to reimbursement of the Village of Campbell at the rate of $200 per month for any extra time that may be required to complete the work.”

*363 The evidence on behalf of plaintiff tends to prove that the work was completed according to plans and specifications late in December, 1925. Evidence on behalf of defendant tends to prove that a considerable part of the graveling was not leveled and packed, as provided by the contract. The contract called for a completed packed gravel job; that 15 per cent, of clay should be thoroughly mixed with the gravel as a binder, and that it “shall be rolled with a multi wheel roller until thoroughly compacted and the roller makes no appreciable track thereon, and the rolled surface conforms to the proper cross section.” Defendant’s evidence tends very strongly to prove that the greater part of the gravel was not properly rolled until compacted; that the gravel was so loose that a person could put his foot through it to its full depth; that a proper multi wheel roller was not used. There was evidence, too, that plaintiff recognized the work as not meeting the requirements of the contract; that plaintiff agreed to complete the work the following spring; that in the meantime defendant should retain $1,800 of the contract price, until the work was fully completed; that the following spring plaintiff offered to return and complete the work on condition that defendant would discharge its engineers, but would not do so unless the engineering company was discharged. Defendant refused to comply with the demand, and plaintiff did not return to do any further work. This evidence presented an issue of fact for the jury.

It is a well-established.principle that in a law action the finding of the jury, based on conflicting evidence, will not be disturbed unless clearly wrong. Upon consideration of the entire record, we are satisfied that the finding of the jury on this question was amply sustained by the evidence.

December 29, 1925, defendant accepted the work as completed and used the record of acceptance as a basis for the history of a bond issue. Plaintiff contends that this fact now estops the defendant from asserting that *364 the work was not completed according to the terms of the contract, and cites some cases tending to support this view. There is evidence that the acceptance of the work was conditional; that defendant was desirous of issuing bonds bearing 5y2 per cent., to take up warrants previously issued for work done, and which were bearing 7 per cent.; that, in a conversation between an officer of plaintiff and the chief engineer of the defendant, it was agreed that a reasonable amount of the contract price be •retained by the defendant until the work was completed at a later date; that acceptance would be made by the defendant for the purpose of using it as a history for the bond issue, but that, notwithstanding the acceptance, plaintiff was to return and finish the work in the spring of 1926.

If there was an irregularity or fraud in the acceptance of the work before it was completed, may plaintiff, who was a party thereto, take advantage of that irregularity of fraud to enable it to receive compensation for work which it had not performed? Were this an action by the holder of bonds that were issued, and who had purchased them, relying upon the history, it is probable that the defendant would be estopped from showing that the acceptance was conditional. We fail to perceive from the record how' plaintiff was injured by this acceptance or that it had changed its position to its disadvantage by reason thereof. To permit plaintiff to recover in this action for work which it had not performed would be to permit it to profit by a wrong to which it was a party.

The law will not permit one to make a wrong, to which he is a party, the basis for an unjust recovery. The court submitted to the jury the question as to whether the acceptance was conditional for the purpose of issuing bonds, to which plaintiff assented, and, if so found, defendant would not be estopped from showing that the work was not completed, and would be entitled to retain from the contract price an amount sufficient to complete the work in accordance with the contract specifications: *365 The jury determined this question adversely to plaintiff. We think there was no error in the court’s instruction, in this respect.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Graham v. Prescott
Nebraska Court of Appeals, 2024
Kozlik v. Emelco, Inc.
483 N.W.2d 114 (Nebraska Supreme Court, 1992)
Kear v. Hausmann
41 N.W.2d 850 (Nebraska Supreme Court, 1950)
Stanford Motor Co. v. Westman
39 N.W.2d 841 (Nebraska Supreme Court, 1949)

Cite This Page — Counsel Stack

Bluebook (online)
243 N.W. 77, 123 Neb. 360, 1932 Neb. LEXIS 210, Counsel Stack Legal Research, https://law.counselstack.com/opinion/yant-construction-co-v-village-of-campbell-neb-1932.