This text of Xodus Medical, Inc. v. The Soule Co. (Xodus Medical, Inc. v. The Soule Co.) is published on Counsel Stack Legal Research, covering District Court, M.D. Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
UNITED STATES DISTRICT COURT MIDDLE DISTRICT OF FLORIDA TAMPA DIVISION
XODUS MEDICAL, INC., ALESSIO PIGAZZI, and GLENN KEILAR,
Plaintiffs, v. Case No. 8:18-cv-1152-AAS
THE SOULE CO.,
Defendant.
______________________________________/
ORDER
The parties requested a telephonic status conference to clarify whether the issue of indefiniteness should be addressed during claim construction briefing. (Doc. 93). The court held a hearing on August 21, 2019 and ordered the parties to brief the issue. (Doc. 99). Both parties timely submitted briefs. (Docs. 100, 101). The standard for indefiniteness is different than the standard for claim construction. See Phillips v. AWH Corp., 415 F.3d 1303, 1327 (Fed. Cir. 2005). Many district courts1 have recognized “the Federal Circuit’s statements that indefiniteness is intertwined with claim construction mean only that the Court must attempt to
1 See also Capstan AG Sys., Inc. v. Raven Indus., Inc., No. 16-cv-4132, 2018 WL 953112, at *15 (D. Kan. Feb. 20, 2018); Capital Sec. Sys., Inc. v. NCR Corp., No. 14-cv-1516, 2016 WL 3517595, at *4 (N.D. Ga. June 28, 2016); Forta Corp. v. Surface-Tech, LLC, No. 13-cv1608, 2015 WL 3756187, at *1-2 (W.D. Pa. June 11, 2015); Indus. Tech. Research Inst. v. LG Elecs. Inc., No. 13-CV-2016, 2014 WL 6907449, at *2 (S.D. Cal. Dec. 8, 2014); Takeda Pharm. Co. v. Handa Pharms., LLC, C–11–00840 JCS, 2012 WL 1243109, at *16 (N.D. Cal. Apr. 11, 2012). 1 determine what a claim means before it can determine whether the claim is invalid for indefiniteness, and not that the Court must determine indefiniteness during the claim construction proceedings.” ASM Am., Inc. v. Genus, Inc., No. C-01-2190-EDL,
2002 WL 1892200, at *15 (N.D. Cal. Aug. 15, 2002). This district concluded “it would be more appropriate and logical to defer the full consideration of any potential indefiniteness challenges to the summary judgment stage, after all fact and expert discovery has been completed.” Uretek Holdings, Inc. v. YD West Coast Homes, Inc., No: 8:15-cv-472-T-36JSS, 2016 WL 3021880, at *3 (M.D. Fla May 26, 2016); see also Johnson & Johnson Vision Care, Inc. v. Ciba Vision Corp., 540 F. Supp. 2d 1233, 1243
(M.D. Fla. 2008) (finding the issue of indefiniteness is not properly before the court when construing claims). Therefore, the parties are not to brief indefiniteness in their respective claim construction briefs. Briefing on the issue of indefiniteness is deferred until the summary judgment stage. After consideration, it is ORDERED that: 1. The plaintiffs’ motion to have indefiniteness removed from the claim
construction briefs (Doc. 99) is GRANTED. 2. The Supplemental Case Management Report’s claims construction briefing deadlines (Docs. 84, 88) are extended as follows: a. By October 14, 2019, the parties must file their claim construction briefs.
2 b. By November 18, 2019, the parties must respond to the opposing party’s claim construction brief. ORDERED in Tampa, Florida on September 10, 2019. Aranda. Saou. AMANDA ARNOLD SANSONE United States Magistrate Judge
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
Xodus Medical, Inc. v. The Soule Co., Counsel Stack Legal Research, https://law.counselstack.com/opinion/xodus-medical-inc-v-the-soule-co-flmd-2019.