Wyoming National Bank of Wilkes-Barre v. United States

292 F.2d 511, 154 Ct. Cl. 590, 1961 U.S. Ct. Cl. LEXIS 122
CourtUnited States Court of Claims
DecidedJuly 19, 1961
DocketNo. 445-54
StatusPublished
Cited by6 cases

This text of 292 F.2d 511 (Wyoming National Bank of Wilkes-Barre v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wyoming National Bank of Wilkes-Barre v. United States, 292 F.2d 511, 154 Ct. Cl. 590, 1961 U.S. Ct. Cl. LEXIS 122 (cc 1961).

Opinion

Laramore, Judge,

delivered the opinion of the court:

This is a suit brought by The Wyoming National Bank of Wilkes-Barre, Pennsylvania, the successor corporation to the named assignee of a Government contract, the First National Bank of Plymouth, Pennsylvania. The suit is brought to recover sums allegedly wrongfully withheld as liquidated damages.

The questions presented, as set forth in plaintiff’s brief, are

(1) Whether the refusal by the Armed Services Board of Contract Appeals to grant plaintiff’s predecessor’s request for intervention constituted a denial of plaintiff’s predecessor’s rights under the “Delays — Liquidated Damages” clause of the contract so as to entirely disallow the Government’s claim for any liquidated damages on the grounds that they have failed to comply with the conditions of the contract;

(2) Whether under a liquidated damages provision in a contract, where the only portion of the provision which fixes the amount of the liquidated damages is made applicable to the situation where the contractor refuses or fails to make delivery of the materials or supplies within the time specified, or any extension thereof, the Government is entitled to liquidated damages for that part of the contract which has been terminated.

The facts are summarized as follows: Plaintiff in 1958 purchased all the assets of the First National Bank of Plymouth, Pennsylvania, the assignee of the Bo-Jack contract.

[592]*592The contract involved in this action, W30-280-qm-5947, dated October 30, 1947, was between the Bo-J ack Manufacturing Corporation and the War Department. It provided that Bo-Jack would manufacture for the Government 270,000 pairs of baker’s and cook’s white trousers for $1.99 per pair, the total contract price being $537,300. The contract also provided that the contractor would furnish all materials and the contract was executed on behalf of Bo-Jack by David Bose, President.

The delivery schedule, as amended, called for deliveries over the period December 31, 1947, to September 30, 1948. The contractor became delinquent in delivery under the contract. As of September 24, 1948, six days prior to the date on which deliveries of all 270,000 garments were to have been completed, the contractor had shipped only 92,190 pairs. The contractor asked for but did not receive extension of time to avoid assessment of liquidated damages as provided in the contract, and on October 1, 1948, the successor contracting officer terminated the contract for default as to 163,658 undelivered units. The work in process was not terminated. Bo-Jack completed and delivered a total of 106,342 pairs of trousers.

On October 26, 1948, Bo-J ack, represented by counsel, appealed the action of the contracting officer in terminating the contract and stated that failure to make deliveries was occasioned by acts of the defendant in not making a prompt award of the contract. A request was made for an extension of delivery date so as to eliminate liquidated damages, which request summarized the reasons therefor. The principal reason asserted for the extension was an alleged shortage of the cotton drill out of which the trousers were to be manufactured. On February 14, 1949, the aforesaid request for an extension of time was denied by the successor contracting officer. The appeal was, at the request of Bo-Jack’s attorney, placed on the suspense docket, and on October 18, 1949, the Appeals Board granted a Government motion to remove the case from the suspense docket and set it for hearing on December 6, 1949. Notice was sent to Bo-Jack’s attorney by registered mail and a return receipt acknowledged its delivery.

[593]*593Mr. Schwag, Bo-Jack’s attorney, wrote the Board advising it that Mr. David Bose, the President and only witness of the appellant company, was sentenced to serve a term in the Federal penitentiary, and again requested that the matter be placed on the suspense docket. On December 1, 1949, the Board notified Mr. Schwag that the case should proceed as set and that, if necessary, testimony of Mr. Bose could be taken by deposition.

Mr. Schwag then advised the Board on December 2, 1949, that neither he nor his client would be present at the hearing and that under the rules the matter could proceed ex -parte, and that he was requesting leave to take Mr. Bose£s deposition. There is no evidence that the deposition was ever taken or that any attempt was made to take it.

The Armed Services Board of Contract Appeals hearing was held on December 6, 1949. On this same day by letter Mr. Max Bosenn wrote the recorder of the Board referring to a telephone conversation of the previous day and enclosed notice of appearance on behalf of himself and a Mr. Boberts for the First National Bank of Plymouth, Pennsylvania, indicating an intention to file a petition to intervene. This letter was received by the Board on December 9,1949.

Under date of January 14,1950, Mr. Bosenn sent his petition to the Board and requested to be heard on it. In due course the petition was denied.

'Subsequently on July 27, 1950, the Armed Services Board of Contract Appeals rendered its written opinion and decision sustaining the action of the contracting officer and denied the petition to intervene.

In 1954 plaintiff filed its petition in this court. Defendant moved to summon Bo-Jack, the contractor, to appear as a third party, to defend its interest and to answer defendant’s claim against it. This motion was allowed and Bo-Jack is now a party to these proceedings.

The Government assessed liquidated damages against Bo-Jack in the amount of $193,805.37. Of this sum it has collected $54,201.99 by setoff against sums otherwise due under the contract, and makes claim against Bo-Jack in this suit for the balance of $139,603.38.

[594]*594In tbe instant suit Bo-Jack is represented by counsel and answered tbe defendant’s claim. Neither tbe contractor nor its counsel appeared at tbe trial although duly notified thereof.

Neither the contractor nor the plaintiff offered evidence at the trial on the issues before the Board other than the record of that proceeding.

Respecting the issue of the shortage of cotton drill, the evidence here discloses that the contractor’s supplier was ready, willing and able to supply all of this type of cloth that Bo-Jack needed to perform its contract with the Government. As a matter of fact, it has been shown that at the time the contractor was contending there was a short supply of the cloth in the textile markets, the contractor was actually selling a substantial quantity of tins same material to another company.

Respecting plaintiff’s contention that the refusal of the Armed Services Board of Contract Appeals to allow the First National Bank of Plymouth to intervene and that the refusal results in disallowment of the liquidated damage claim, the facts clearly show that any dispute under the contract was between Bo-Jack and the Government. The Board denied intervention, ruling that its jurisdiction was limited to ruling on the matter of the assessment of the liquidated damages and that it had no jurisdiction to determine the priority of the Government to payment of such claim for liquidated damages as against an assignee of the appellant. In this we think the Board was clearly correct. The dispute was a factual one with the contractor and involved facts relating to the performance of the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rochester Gas & Electric Corp. v. United States
65 Fed. Cl. 431 (Federal Claims, 2005)
Holland v. United States
62 Fed. Cl. 395 (Federal Claims, 2004)
Standard Federal Bank v. United States
51 Fed. Cl. 695 (Federal Claims, 2002)
Thomas Funding Corp. v. United States
35 Cont. Cas. Fed. 75,556 (Court of Claims, 1988)
International Electronics Corp. v. United States
646 F.2d 496 (Court of Claims, 1981)
Produce Factors Corp. v. United States
467 F.2d 1343 (Court of Claims, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
292 F.2d 511, 154 Ct. Cl. 590, 1961 U.S. Ct. Cl. LEXIS 122, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wyoming-national-bank-of-wilkes-barre-v-united-states-cc-1961.