Wyndham Vacation Fairfield Resorts, Inc. v. Architects Hawaii Ltd.

703 F. Supp. 2d 1051, 2010 U.S. Dist. LEXIS 22106
CourtDistrict Court, D. Hawaii
DecidedMarch 10, 2010
DocketCv. 08-00236 DAE-LEK
StatusPublished
Cited by1 cases

This text of 703 F. Supp. 2d 1051 (Wyndham Vacation Fairfield Resorts, Inc. v. Architects Hawaii Ltd.) is published on Counsel Stack Legal Research, covering District Court, D. Hawaii primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wyndham Vacation Fairfield Resorts, Inc. v. Architects Hawaii Ltd., 703 F. Supp. 2d 1051, 2010 U.S. Dist. LEXIS 22106 (D. Haw. 2010).

Opinion

ORDER GRANTING PLAINTIFF’S MOTION FOR SUMMARY JUDGMENT AGAINST ARCHITECTS HAWAII LIMITED

DAVID ALAN EZRA, District Judge.

On March 8, 2Ó10, the Court heard Plaintiffs Motion for Summary Judgment against Defendant Architects Hawaii Limited. Judy A. Tanaka, Esq., appeared at the hearing on behalf of Plaintiff; Michael L. Biehl, Esq., and Natalie F. Wilson, Esq., appeared at the hearing on behalf of Architects Hawaii Limited; Frank K. Goto, Jr., Esq., and Jane Kwan, Esq., appeared at the hearing on behalf of Notkin Hawaii, Inc. After reviewing the motion and the supporting and opposing memoranda, the Court GRANTS Plaintiffs Motion. (Doc. # 180.)

BACKGROUND

This matter arises from a breach of contract dispute involving a hotel renovation project. Plaintiff Wyndham Vacation Resorts, Inc., formerly known as Fairfield Resorts, Inc. (“Wyndham”), Defendant and Third-Party Plaintiffs Architects Hawaii Limited (“AHL”), and Third-Party Defendant Notkin Hawaii, Inc. (“Notkin”) generally agree on the basic events leading up to this litigation.

Wyndham is the owner of the construction project known as Fairfield Hawaii at Waikiki Resort (the “Project”), which consists of a timeshare conversion of the Outrigger Hotels’ Ohana Reef Hotel located on Lewers Street in Waikiki, Hawaii. The Project includes converting approximately 420 hotel rooms in two towers, as well as renovations of related public spaces, amenity spaces, and support facilities. (Doc. # 152 at 4.)

Wyndham retained AHL as architectural and design consultant, and contracted with AHL to perform architectural and building engineering design services for the Project. Notkin, a subconsultant of AHL, was retained by AHL as the mechanical engineer for the Project. Defendant and Third-Party Defendant Group Pacific (Hawaii), Inc. (“GPH”), acted as Wyndham’s project manager in 2004 and 2005. (Doc. # 180 at 6.) Defendant and Third-Party Defendant Dick Pacific Construction Co., Ltd. (“DPC”) was the general contractor for the Project. 1

*1054 On or about December 20, 2002, Wyndham, as the owner, and AHL, as the consultant, entered into an “Agreement Between Owner and Consultant” (“Agreement”). Section 2.3.1 of the Agreement required AHL to:

[C]oordinate the services and work product of Subconsultants, and remain fully responsible for the professional quality, technical accuracy and coordination of all designs, drawing, specifications, and other services furnished by Consultant or its Subconsultants, and Consultant shall review and approve any designs, specification, shop drawings, submittals, or other services produced or furnished by a Subconsultant prior to submittal to the Owner. Consultant shall correct or revise any of its errors or deficiencies in the designs, drawings, specifications or other services provided pursuant to this Agreement and shall provide Owner with such corrected or revised designs, drawings, or specifications incorporating such corrections or revisions at its sole cost and expense.

(Doc. # 183 Ex. A at 3-4 (emphasis added).)

The type of bathtubs to be installed in the rooms was described in the “Resort Development Standard Manual” (“Project Manual”), which was provided to AHL before preparing Project plans, drawings, and specifications. (Doc. # 180 at 7; Doc. # 197 at 1.) Section 5.9.1 of the Project Manual provides that “[a] Master Bathroom with luxury bathing accommodations is required in all guest units,” and Section 5.9.2 requires that “whirlpool” jetted bathtubs be installed in all master bathrooms. (Doc. # 183 Ex. B at 1.) Wyndham claims that AHL breached its contract by installing, or allowing subconsultants to install, non-jetted bathtubs instead of whirlpool jetted bathtubs at the Project site.

An email correspondence dated September 24, 2004, was sent by Joe Davis, then Vice President of Project Development for Wyndham Vacation Ownership, to Mark Tuner of GPH, specifically commenting, “The whirlpool tub in the master bath is a Fairfield ‘sacred cow.’ Substitution of a standard tub is NOT acceptable.” (Doc. # 183 Ex. C at 2.) The email was subsequently forwarded to Alain Gerónimo of AHL, among others. (Id. at 1.)

On or about December 31, 2004, AHL prepared and/or approved architectural and mechanical drawings requiring: (1) non-jetted bathtubs (hereinafter “TUB 1”) to be installed in One-Bedroom Units of the Plantation Wing; and (2) jetted bathtubs (hereinafter “TUB 2”) to be installed in master bathrooms of Two-Bedroom and Presidential Units. (Doc. # 180 at 9.) Contrary to these Project specifications, AHL approved specifications (“Plumbing Fixture Schedule Mechanical Sheet M-004”) prepared by subconsultant Notkin that also called for non-jetted tubs in TUB 2 locations (i.e., Two-Bedroom and Presidential Units). Wyndham asserts that neither of the specifications should have called for non-jetted tubs. (Id. at 8-10). The end result is that both TUB 1 and TUB 2 were non-jetted bathtubs, despite the original directive from Wyndham that all tubs were to be jetted bathtubs.

Wyndham asserts, but Defendants AHL and Notkin deny, that Wyndham first discovered that non-jetted bathtubs were being installed during a progress walkthrough on or about January 10, 2006. (Id. at 11; Doc. # 197 at 2; Doc. # 190 at 5.) On January 17, 2006, an Instruction Notice was sent by AHL to DPC, the general contractor, directing it to promptly stop installing the non-jetted tubs and replace them with whirlpool jetted tubs. (Doc. # 180 at 11.)

As a result, 136 non-jetted bathtubs were replaced with jetted ones at a total cost of $591,135.00. (Doc. # 152 at 7; Doc. *1055 # 180 at 11.) Wyndham paid that amount to DPC and sought reimbursement from AHL. (Doc. # 180 at 11.) AHL has not reimbursed Wyndham, thus leading to Wyndham’s present action against AHL for breach of contract.

On May 21, 2008, Wyndham filed its original Complaint in this Court against AHL, asserting jurisdiction based on diversity of citizenship. (Doc. #1.) On June 15, 2009, Wyndham filed a First Amended Complaint (“First Amended Complaint” or “FAC”). (Doc. #152.) The FAC was brought against AHL, GPH, and DPC. Count I is a breach of contract claim against AHL. Counts II and III are claims against GPH for breach of contract and negligence, respectively. Counts IV and V are breach of contract and negligence claims against DPC. Because DPC was dismissed from this action via stipulation between all parties, only Counts I, II, and III remain to be litigated. Wyndham seeks damages in an amount to be proven at trial.

The defendants and third party plaintiffs have filed various Cross Claims and Counter Claims not immediately relevant to the instant motion before this Court. On February 19, 2010, all parties stipulated to dismiss with prejudice all claims against DPC. (Doe. # 220.) On the same day, the parties also stipulated to dismiss without prejudice Notkin’s Cross Claim against GPH and GPH’s Cross Claim against Not-kin. (Doc. # 221.)

On December 16, 2009, Wyndham filed the instant Motion for Summary Judgment against AHL, Count I of the FAC. (Doc.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hele Ku KB, LLC v. BAC Home Loans Servicing, LP
873 F. Supp. 2d 1268 (D. Hawaii, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
703 F. Supp. 2d 1051, 2010 U.S. Dist. LEXIS 22106, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wyndham-vacation-fairfield-resorts-inc-v-architects-hawaii-ltd-hid-2010.