W.W. Webber, L.L.C. v. Harris County Toll Road Authority

324 S.W.3d 877, 2010 Tex. App. LEXIS 8258, 2010 WL 4013662
CourtCourt of Appeals of Texas
DecidedOctober 14, 2010
Docket14-09-00513-CV
StatusPublished
Cited by12 cases

This text of 324 S.W.3d 877 (W.W. Webber, L.L.C. v. Harris County Toll Road Authority) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
W.W. Webber, L.L.C. v. Harris County Toll Road Authority, 324 S.W.3d 877, 2010 Tex. App. LEXIS 8258, 2010 WL 4013662 (Tex. Ct. App. 2010).

Opinion

OPINION

KENT C. SULLIVAN, Justice.

The trial court dismissed, for want of jurisdiction, a lawsuit filed by appellant, W.W. Webber, L.L.C. (“Webber”), against a governmental entity, appellee Harris County Toll Road Authority (“HCTRA”), for breach of contract and quantum meru-it. On appeal, Webber contends HCTRA waived its governmental immunity by conduct. Because the Texas Supreme Court has already rejected waiver by conduct under similar facts, we affirm.

I.

BACKGROUND

This lawsuit arises from a contract dispute relative to the construction of two sections of the Westpark Tollway, a limited-access toll road serving portions of western Harris County and northeastern Fort Bend County. Construction on the tollway began in 2001.

That year, HCTRA, on behalf of Harris County, solicited and accepted bids for the construction of certain portions of the tollway. Two of the bids HCTRA accepted were submitted by Webber, a construction *879 contractor that agreed to build two sections of the tollway, covering a total of roughly 1.17 miles of road. Accordingly, Webber and HCTRA entered into two contracts, each addressing a different section of the tollway.

At the time, HCTRA intended to open the tollway no more than two years later, in May 2003. Therefore, the parties agreed to a strict deadline for completion of Webber’s portions of the project. Under both contracts, Webber was obligated to complete both sections within 365 calendar days, plus six holidays. Both contracts specified that “time is of the essence,” and therefore authorized Webber to work for twenty-four hours a day, and seven days per week — except for the six designated holidays — to enable Webber to complete the project on time.

In addition, both contracts imposed liquidated damages of $2,500 per day should Webber fail to complete the project within the time allotted. Those clauses generally provided:

Time is of the essence of this Contract. If the Contractor fails to complete his undertaking acceptably to the Authority within the time specified in his bid and Contract, the Authority will be damaged. The exact amount of damage is and will be difficult of exact ascertainment. Such damages shall be at the rate or the amount hereinafter fixed. The Contractor specifically binds and obligates himself to pay such damages to the Authority on demand; or, at its option, the Authority may withhold the amount thereof from any sums due the Contractor under this or any other Contract, or from any other obligation of any kind owing the Contractor by the Authority.

As of the date of the contracts, Harris County had not fully secured all necessary rights of way from the surrounding landowners, and also had not reached agreement to relocate all utilities that might stand in the way of construction. While those events were expected to delay construction to some extent, Webber was strongly urged, in light of the strict deadline, to anticipate and work around these expected delays to complete the projects on time.

Webber did not complete either construction project within the deadline imposed by the contracts. Therefore, HCTRA invoked the liquidated-damages provisions and withheld a portion of the original contract price. Ultimately, HCTRA paid slightly more than ninety-seven percent of the original contract price to Webber.

However, Webber — which attributed its untimely performance to HCTRA’s delay in securing the rights of way and relocation of utilities — demanded full payment of the contract amount. After Harris County failed or refused to accede to Webber’s demands, Webber filed suit for breach of contract and quantum meruit. HCTRA, as a governmental entity, asserted immunity in a plea to the jurisdiction, and also filed a motion for summary judgment. The trial court sustained HCTRA’s plea and granted summary judgment, prompting this appeal.

II.

Analysis

Webber raises seven issues on appeal. The first five issues are devoted to the portion of the trial court’s order that dismissed Webber’s suit for want of jurisdiction. We will address each of those issues, albeit not in the same order in which they appear in appellant’s brief.

We conclude that Webber has failed to demonstrate the trial court’s subject-matter jurisdiction to hear this case. There *880 fore, we hold the trial court properly dismissed Webber’s lawsuit for want of jurisdiction. Accordingly, we need not reach appellant’s sixth and seventh issues, in which Webber complains about the propriety of the trial court’s order granting summary judgment to HCTRA. See Tex.R.App. P. 47.1.

A. Completion of Jurisdictional Discovery

In its fourth issue, which we address first, Webber argues that the trial court should have deferred any ruling on HCTRA’s jurisdictional plea until after the depositions of five Harris County employees. In response, HCTRA contends (1) Webber waived this complaint by failing to file a supporting affidavit or verified motion for continuance; and (2) Webber did not diligently pursue these depositions, which were not requested until (a) more than a year after suit was filed, (b) more than four months after HCTRA filed its plea, and (c) more than two weeks after the trial court’s hearing on the plea.

We review the denial of a motion for continuance 1 for an abuse of the trial court’s discretion. See Joe v. Two Thirty Nine Joint Venture, 145 S.W.3d 150, 161 (Tex.2004); Daugherty v. Jacobs, 187 S.W.3d 607, 618 (Tex.App.-Houston [14th Dist.] 2006, no pet.). In this context, a trial court abuses its discretion only if its ruling was arbitrary, unreasonable, and lacking in reference to any guiding rules or principles. See Daugherty, 187 S.W.3d at 618.

A motion for continuance is governed by Texas Rule of Civil Procedure 251 and, to the extent the request is prompted by a perceived need to obtain testimony, Rule 252. See Tex.R. Civ. P. 251, 252. Both of these rules generally require the moving party, here, Webber, to supply either an affidavit or a verified motion reasonably explaining the need for a continuance. 2 See id.; Tenneco Inc. v. Enter. Prods. Co., 925 S.W.2d 640, 647 (Tex.1996). If the movant fails to comply with that requirement, we must presume the trial court did not abuse its discretion by denying the requested continuance. See Villegas v. Carter, 711 S.W.2d 624, 626 (Tex.1986); Waste Water, Inc. v. Alpha Finishing & Developing Corp., 874 S.W.2d 940, 942 (Tex.App.-Houston [14th Dist.] 1994, no writ).

Here, Webber failed to comply with Rules 251 and 252 because its continuance request was not verified or supported by an affidavit explaining the need for a continuance. See Tex.R. Civ. P.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
324 S.W.3d 877, 2010 Tex. App. LEXIS 8258, 2010 WL 4013662, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ww-webber-llc-v-harris-county-toll-road-authority-texapp-2010.