WSA Group, PE-PC v. DKI Eng'g & Consulting USA PC

2019 NY Slip Op 9339
CourtAppellate Division of the Supreme Court of the State of New York
DecidedDecember 26, 2019
Docket527709
StatusPublished

This text of 2019 NY Slip Op 9339 (WSA Group, PE-PC v. DKI Eng'g & Consulting USA PC) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
WSA Group, PE-PC v. DKI Eng'g & Consulting USA PC, 2019 NY Slip Op 9339 (N.Y. Ct. App. 2019).

Opinion

WSA Group, PE-PC v DKI Eng'g & Consulting USA PC (2019 NY Slip Op 09339)
WSA Group, PE-PC v DKI Eng'g & Consulting USA PC
2019 NY Slip Op 09339
Decided on December 26, 2019
Appellate Division, Third Department
Published by New York State Law Reporting Bureau pursuant to Judiciary Law § 431.
This opinion is uncorrected and subject to revision before publication in the Official Reports.


Decided and Entered: December 26, 2019

527709

[*1]WSA Group, PE-PC, Appellant- Respondent,

v

DKI Engineering & Consulting USA PC, Respondent- Appellant.


Calendar Date: November 14, 2019
Before: Garry, P.J., Clark, Mulvey, Pritzker and Reynolds Fitzgerald, JJ.

Hodgson Russ LLP, Buffalo (Michelle L. Merola of counsel), for appellant-respondent.

Wilson, Elser, Moskowitz, Edelman & Dicker LLP, Albany (Christopher A. Priore of counsel), for respondent-appellant.



Garry, P.J.

Cross appeals from an order of the Supreme Court (Platkin, J.), entered September 20, 2018 in Albany County, which partially granted defendant's motion to dismiss the complaint.

In March 2012, plaintiff entered into a subcontract with defendant, a professional engineering firm, by which defendant agreed to inspect certain state bridges pursuant to plaintiff's prime contract with the Department of Transportation (hereinafter DOT). The subcontract provided that the time period for defendant's performance was January 1, 2012 through May 31, 2014, and included a provision requiring defendant to indemnify plaintiff for certain costs and expenditures arising from defendant's errors, omissions or negligence. In March 2017, defendant's employee, Akram Ahmad, was convicted of falsifying a 2013 inspection report for one of the bridges covered by the subcontract. As a result, plaintiff incurred costs related to cooperating in the investigation, providing information and appearing and testifying at administrative and judicial hearings, and was required to reimburse DOT for sums paid to defendant for Ahmad's work. Defendant declined plaintiff's request for indemnification of these costs.

In May 2018, plaintiff commenced this action against defendant stating causes of action in negligent supervision and breach of contract, and seeking to recover its expenditures arising from Ahmad's misconduct. Defendant moved to dismiss the complaint as time-barred under CPLR 214 (6). Supreme Court granted the motion in part by dismissing the negligent supervision claim and the breach of contract claim to the extent that it was based upon defendant's failure to properly inspect the bridge. The court partially denied the motion to dismiss the breach of contract claim to the extent that it was based upon defendant's failure to comply with its contractual obligation to indemnify plaintiff for its reimbursement to DOT. To the extent that plaintiff sought indemnification for its counsel fees and costs related to investigations and judicial and administrative proceedings, the breach of contract claim was dismissed, as the court found that these were direct claims subject to the three-year limitations period of CPLR 214 (6), and were therefore time-barred. These cross appeals ensued.

A three-year statute of limitations governs "action[s] to recover damages for malpractice, other than medical, dental or podiatric malpractice, regardless of whether the underlying theory is based in contract or tort" (CPLR 214 [6]; see City of Binghamton v Hawk Eng'g P.C., 85 AD3d 1417, 1418 [2011], lv denied 17 NY3d 713 [2011] ). Although a six-year limitations period ordinarily applies to breach of contract claims, such a cause of action will be construed as a professional malpractice claim subject to the three-year limitations period "to the extent that the allegations are that [the defendant] failed to perform its contractual services in a professional, nonnegligent manner" (New York State Workers' Compensation Bd. v SGRisk, LLC, 116 AD3d 1148, 1150 [2014]). In determining whether a cause of action denominated in tort or contract should be so construed, "[t]he pertinent inquiry is thus whether the claim is essentially a malpractice claim" (Matter of R.M. Kliment & Frances Halsband, Architects [McKinsey & Co., Inc.], 3 NY3d 538, 542 [2004]).

Here, Supreme Court determined that plaintiff's claim for negligent supervision and also its claim for breach of contract — to the extent that it is based upon defendant's failure to properly perform the bridge inspection — sound in the nature of professional malpractice, and are therefore subject to a three-year limitations period. Plaintiff does not directly challenge that finding, but rather challenges Supreme Court's determination that these claims are untimely. Relying on precedent addressing negligence and breach of contract claims that do not involve professional malpractice, plaintiff asserts that neither claim accrued until all elements of each cause of action, including damages, could be alleged (see e.g. Bond v Progressive Ins. Co., 82 AD3d 1318, 1320-1321 [2011]). Plaintiff asserts that the claims are timely because they could not be pleaded until the damages resulting from Ahmad's actions in 2017 were in fact incurred, and that the payments of those costs, fees, and expenses were made less than three years before commencement of this action in 2018.

We reject this argument, as it disregards the well-established rule that "a claim for professional malpractice against an engineer or architect accrues upon the completion of performance under the contract and the consequent termination of the parties' professional relationship" (Town of Wawarsing v Camp, Dresser & McKee, Inc., 49 AD3d 1100, 1101-1102 [2008]; accord City of Binghamton v Hawk Eng'g P.C., 85 AD3d at 1418; see 797 Broadway Group, LLC v Stracher Roth Gilmore Architects, 123 AD3d 1250, 1252 [2014]; Mary Imogene Bassett Hosp. v Cannon Design, Inc., 84 AD3d 1524, 1525 [2011]). The operation of this principle is not altered by the fact that the extent of damages resulting from professional malpractice may not be known at the time of the termination of the professional relationship between the parties (see e.g. City of Binghamton v Hawk Eng'g P.C., 85 AD3d at 1417-1418). We are constrained to find that a contrary rule would vitiate the purposes of the 1996 amendments to CPLR 214 (6). The amendments altered the former rule in nonmedical professional malpractice actions that had relied upon the proposed remedy rather than the theory of liability in determining the statute of limitations. These amendments were intended "to reduce potential liability of insurers and corresponding malpractice premiums, and to restore a reasonable symmetry to the period in which all professionals would remain exposed to a malpractice suit" (Matter of R.M. Kliment & Frances Halsband, Architects [McKinsey & Co., Inc.], 3 NY3d at 542 [internal quotation marks and citations omitted]; see Ackerman v Price Waterhouse, 84 NY2d 535, 541-542 [1994]). Thus, to the extent that plaintiff's claims sound in professional malpractice, they are deemed to accrue when such a claim would accrue. Here, the subcontract specified a completion date in May 2014 and did not contemplate any continuing professional responsibilities beyond that date.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Germantown Central School District v. Clark, Clark, Millis & Gilson
791 N.E.2d 398 (New York Court of Appeals, 2003)
Ackerman v. Price Waterhouse
644 N.E.2d 1009 (New York Court of Appeals, 1994)
797 Broadway Group, LLC v. Stracher Roth Gilmore Architects
123 A.D.3d 1250 (Appellate Division of the Supreme Court of New York, 2014)
McDermott v. City of New York
406 N.E.2d 460 (New York Court of Appeals, 1980)
Town of Wawarsing v. Camp, Dresser & McKee, Inc.
49 A.D.3d 1100 (Appellate Division of the Supreme Court of New York, 2008)
Bond v. Progressive Insurance
82 A.D.3d 1318 (Appellate Division of the Supreme Court of New York, 2011)
Mary Imogene Bassett Hospital v. Cannon Design, Inc.
84 A.D.3d 1524 (Appellate Division of the Supreme Court of New York, 2011)
City of Binghamton v. Hawk Engineering P.C.
85 A.D.3d 1417 (Appellate Division of the Supreme Court of New York, 2011)
Varo, Inc. v. Alvis PLC
261 A.D.2d 262 (Appellate Division of the Supreme Court of New York, 1999)
Germantown Central School District v. Clark
294 A.D.2d 93 (Appellate Division of the Supreme Court of New York, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
2019 NY Slip Op 9339, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wsa-group-pe-pc-v-dki-engg-consulting-usa-pc-nyappdiv-2019.