Wrightsman Petroleum Co. v. Martin

1925 OK 742, 239 P. 663, 111 Okla. 279, 1925 Okla. LEXIS 502
CourtSupreme Court of Oklahoma
DecidedSeptember 15, 1925
Docket15598
StatusPublished

This text of 1925 OK 742 (Wrightsman Petroleum Co. v. Martin) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wrightsman Petroleum Co. v. Martin, 1925 OK 742, 239 P. 663, 111 Okla. 279, 1925 Okla. LEXIS 502 (Okla. 1925).

Opinion

Opinion by

THREADGILL, C.

On December 26, 1922, G. N. Martin, defendant in error, as plaintiff, commenced this action against C. J. Wrightsman, Wrightsman Petroleum Company, and Minnetonka Lumber Company, as defendants, to recover $2,500 for building an oil and gas drilling rig and to foreclose the mechanic’s lien on the leasehold. The cause was dismissed as to C. J. Wrightsman and the lumber company, and proceeded to trial against the petroleum company. The parties will be referred to as they appeared in the trial court.

The petition alleged, in substance, that the defendant employed the plaintiff by oral contract to furnish certain materials and perform certain labor for the construction of a “calf wheel rig 80-foot derrick and large house” on N.W.% of S.W.% of section 11. T. 10 N., R. 11 E., in Okfuskee county, upon which the defendant owned an oil and gas leasehold estate, and by the terms of said contract defendant agreed to pay plaintiff the sum of $2,500; that plaintiff furnished the materials and labor and constructed the rig as agreed upon, and the last labor performed was on June 8, 1922. The petition further pleads the lien statement and asks for judgment for $2,500, with interest at 6 per cent, per annum from June 8, 1922, the foreclosure of its lien, and $500 attorney’s fees and costs. After various motions filed and overruled, not necessary to be stated here, defendant answered, in which it stated, in substance, that it made the contract with plaintiff to construct the drill *280 ing rig through its president, C. J. Wrights-man; that the agreement was for a derrick 84 feet high, guaranteed to carry a hole 3,000 feet deep, and the legs to be 12x12, braces 2x10x12, girts 2x12, the 2xl0’s to be doubled all around, and other descriptions not necessary to be recited here, and upon the conditions that said rig and accessories should be completed within four days, and time was understood to be the essence of the contract, “occasioned on account of the offset well to said property draining the same, for which defendant agreed to pay the sum of $2,500.” The answer further states that plaintiff failed to comply with the terms of the contract, and then various defects are recited on account of which it is alleged the drilling contractor was delayed to June 13, 1922, in commencing the work of drilling, and during which time the Transcontinental Oil Company well was-draining the property of defendant, and, because of plaintiff’s failure to comply with the said contract, the defendant asks " that the action be dismissed. Then followed a’ cross-petition pleading breach of contract and damages for expenditure of $200 to properly complete the drilling rig outfit, and damages for 13 days’ drainage by the offsetting well in the sum of $3,000, and for all of which it prays judgment. Plaintiff filed his reply consisting of a general denial. The issues were tried to a jury February 6, 1924, and resulted in a judgment for plaintiff for the amount sued for, and foreclosure of the lien, and the defendant has appealed asking for a reversal and new trial.

The first proposition urged by defend- . ant is that the evidence is not sufficient to ’ reasonably support the verdict and judgment. The principal evidence introduced was the conversation between plaintiff and C. J. Wrightsman on May 20, 1922, in which the contract was made. According to the record plaintiff testified as follows:

“Q. Tel! the jury what was said between you? A. He wanted me to build a rig and asked what I would build it for and told me to call him up in an hour or so and I did so. He told me he wanted to build an 80-foot derrick, standard length belt house, and outside forge house and casing rack. I called him up and told him I took the contract for the Transcontinental Oil Company for two rigs for $2,371. Q. You mean $2,371 each? A. Yes, sir, for each one, $2,371; and he wanted me to build this one fo,t that and I told him! I couldn’t do that on account of the additional work. Q. What was the additional work? A. The outside forge house and an 80-foot derrick. Q. What were the other rigs? A. 72-foot derrick with a 22-foot bunting pole. Q. Did it have a forge house? A. No, sir, nofi an outside forge house. Q. Did it have a casing rack? A. It did not. Q. What price did you make him for building this derrick? A. $2,500. Q. What did he say to that? A. He said go ahead and don’t spare no time.” ■

He further testified to the two days it took to clear the place of trees and brush before he could commence building the derrick and said this was no part of his work under the contract, and he turned in a claim for it for $25, which was refused by the defendant, and he testified as to the work and materials in constructing the rig and equipment, and this testimony covered the issues as to the defects complained of by the defendant’s answer, and the facts he stated tended to contradict the statement of facts as to defects and material and construction as set out in defendant’s answer. He stated facts from which the jury could infer that he had fulfilled the contract as to the construction of the- drilling rig and as to the time in which he was to complete it.

Then O. J. Wrightsman gave his version of the telephone conversation and agreement as follows:

“Q. Are you familiar with the land on which the plaintiff erected a derrick in behalf of your company, and with reference to his contract for the same? A. I am. Q. State the circumstances, and what was said, if anything, between you and the plaintiff in reference to the construction of a derrick on said property about the time alleged in plaintiff’s petition? A. I telephoned the plaintiff from my office at Tulsa, reaching him. I think, at Henryetta. The substance of that conversation was that I desired to erect a derrick on said land offsetting a producing well then just brought in by the Transcontinental Oil Company, and in my conversation -stated that the element of time was extremely essential to protect my land from drainage which was resulting from said offset well. In the matter of compensation, he informed me that he had constructed derricks on the adjoining land for the Transcontinental Oil Company, and I then agreed verbally with him to pay him the same amount, with the express understanding that he was to receive a bonus of $200 additional to complete the derrick within four days as a rush job inducement for such quick action. As I recall, I instructed him to have the location made and to look after all details in the matter of getting upon the property.”

The witness further testified that his office manager, R. J. Reinke, was present at -his end of the telephone during the conversation, and heard what he said and made notes on the same at the time; then he *281 proceeded to tell that plaintiff failed to complete the derrick within the time agreed upon. Said he called him over the phone and vigorously protested against his failure, neglect, and delay in finishing the derrick; said the company had never changed the agreement or modified its terms; said he had offered to pay him the $2,500, amount of the contract agreed upon, less the bonus which he did not earn, because of failure to build the derrick within four days, and less certain repairs. He explained this was a compromise proposition, and, at the same time, he was complaining of the drainage and loss caused, by the failure of plaintiff to complete the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
1925 OK 742, 239 P. 663, 111 Okla. 279, 1925 Okla. LEXIS 502, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wrightsman-petroleum-co-v-martin-okla-1925.