Wright v. Woodridge Lake Sewer District, No. 0043504 (Jan. 7, 1992)

1992 Conn. Super. Ct. 1020
CourtConnecticut Superior Court
DecidedJanuary 7, 1992
DocketNo. 0043504
StatusUnpublished

This text of 1992 Conn. Super. Ct. 1020 (Wright v. Woodridge Lake Sewer District, No. 0043504 (Jan. 7, 1992)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wright v. Woodridge Lake Sewer District, No. 0043504 (Jan. 7, 1992), 1992 Conn. Super. Ct. 1020 (Colo. Ct. App. 1992).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.] MEMORANDUM OF DECISION This case was remanded by the Supreme Court for a new trial. Wright v. Woodridge Lake Sewer District, 218 Conn. 144 (1991). Those facts not in dispute are set out in that opinion and need not be repeated here.

Testimony at trial established that until 1980, the capacity of the district's sewage treatment system to handle the sewage generated CT Page 1021 within the district was not a concern. The district was then operating under a permit issued by the Department of Environmental Protection (DEP) in 1977 for treatment of 40,000 gallons per day. That permit was to run until 1982.

In February, 1981, the sewer authority received a request to hook up a planned forty-unit apartment complex. At that time, the average daily flow into the system was reported to be 48,250 gallons. The authority discussed the request at its March 18, 1981 meeting. The authority's counsel explained that they had operated on the basis of being able to guarantee hookup to any owner of a lot within the district. After a discussion of the lack of zoning in Goshen, counsel agreed to look into whether the district, itself, had the power to form a zoning commission within the district. The president of the district who also served as chairman of the authority testified that the authority was concerned about this issue of fairness to landowners outside of the planned unit development in providing access to sewers. The authority ultimately decided against pursuing zoning powers. In the summer of 1981, preparations were being made to apply to DEP to increase the allowed daily flow to between 150,000 and 200,000 gallons per day. At its meeting on August 19, 1981, the authority discussed the effect that future development of vacant land within the district might have on the capacity of the plant. The authority was concerned that if development of the vacant land in the district produced a density equal to that of the planned unit development, the capacity of the plant would be jeopardized. The members decided to request that counsel investigate the possibility of enacting an ordinance limiting hookups to single family dwellings.

At the authority's meeting on September 16, 1981, counsel for the authority reported that the sewer use ordinance could be amended in one of two ways to restrict hookups: either to one dwelling unit per acre or to the equivalent of one dwelling unit per acre. While the district's permit required DEP approval for any permit to hook up except for single family dwellings, the authority was concerned that the DEP might not continue its oversight of applications for multi-family dwellings or might approve such applications without realizing the impact of approval on the sewer system. The board decided to propose a change in the sewer use ordinance which would limit permits to the equivalent of one dwelling unit per acre or smaller lot of record. A dwelling unit equivalent would defined as a use reasonable expected to generate less than 200 gallons per day. Special meetings of both the Woodridge Lake Sewer District and the Sewer Authority were called for November 18, 1981. By vote of the members of both bodies, the proposed amendment, explained as an effort to control the amount of effluent discharged into the system and to protect the capacity of the plant for future homeowners at Woodridge Lake, was adopted.

In 1983, the district applied for a permit to treat 200,000 gallons per day, the designed capacity of the system. When the principal sanitary engineer for DEP toured the facility, he felt that the methods used to CT Page 1022 determine the capacity of the system were inadequate. In 1984, the district and DEP agreed on a plan of testing to provide DEP with evidence in support of the application. In August, 1985, plaintiffs submitted an application to hook up forty-one condominium units in five buildings to the sewer system. The project was proposed for an eight and one quarter acre parcel of land within the district. Plaintiffs submitted proposed plot plans, sewer hook up plans and an elevation plan with their application. At the authority's meeting in October. 1985, the application was voted down on the grounds that it did not comply with the sewer use ordinance.

At the time the ordinance was amended in 1981, the defendants' permit allowed treatment of 40,000 gallons per day. In October, 1981, the average daily flow was 36,600 gallons. Although the district had projected in 1983 a flow of 45,800 gallons per day for 1980 and 63,200 gallons per day for 1990, and 82,000 gallons per day for 2000, reports of average daily flow filed with DEP show that the average daily flow for October, 1991 was 80,000 gallons.

Between 1984 and September 1985, the district did not submit reports of testing adequate to satisfy DEP with regard to the system's capacity. In January, 1986, the principal sanitary engineer for DEP wrote to the district's engineer expressing his concerns regarding the adequacy of the information provided to support a conclusion on the operation of the land application portion of the treatment system. The major concern of the DEP was then the hydraulic capacity of the site for treatment purposes. In 1989, the district and DEP entered into a consent order which allows the district to treat an average daily flow of 100,000 gallons. Under the terms of the order, the district agreed to establish and implement a groundwater monitoring program, to develop and install a system to distribute uniformly the effluent to the ridge and furrow system, to develop a manual for the land application system and to investigate the hydraulic capacity of the system. A schedule was established for accomplishing steps preliminary to full compliance with those undertakings. The district is behind schedule in submitting a hydraulic capacity study, plans and specifications for the distribution system and the manual. At the suggestion of the DEP Sanitary Engineer responsible for oversight of the district's land treatment system, the district requested that action on both the manual and the plans and specifications for the distribution system be tabled until completion of the report on the hydraulic capacity of the system.

At the time defendants adopted the amendments at issue in this case, their engineer had reported on the impact of a 40 unit project on the sewer system under the existing permit. The defendant were then planning to seek a permit to treat 200,000 gallons per day. Although the existing permit was to expire in March. 1982, defendant did not submit its application until August, 1983. That application was not even a complete one. In 1984, a plan of testing was proposed, but a final report was never submitted to DEP. While the defendants' system did exceed its CT Page 1023 permit levels on occasion, the DEP did not view that as critical in light of good water quality test results and the lack of danger to the public health or the environment. Testimony also showed that the defendants submitted only a fraction of the information requested and required in connection with the application. In 1988, a DEP sanitary engineer found that all of the effluent was being discharged into one bed and had been for some time. The distribution of effluent among the beds was based on ad hoc judgments and was not pursuant to any plan. According to the former engineer for the district, the DEP had been asking for hydraulic testing data on the treatment beds since 1975. Finally, in 1989 the consent order was designed to address problems in the distribution of treated effluent among the ridge and furrow beds. As of the date of trial, defendants had still not submitted its proposal for a study of the hydraulic capacity of the system.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Purtill v. Town Plan & Zoning Commission
153 A.2d 441 (Supreme Court of Connecticut, 1959)
Scalo v. Mandanici
425 A.2d 1272 (Supreme Court of Connecticut, 1979)
Finch v. Montanari
124 A.2d 214 (Supreme Court of Connecticut, 1956)
Blue Sky Bar, Inc. v. Town of Stratford
523 A.2d 467 (Supreme Court of Connecticut, 1987)
Cristofaro v. Town of Burlington
584 A.2d 1168 (Supreme Court of Connecticut, 1991)
Wright v. Woodridge Lake Sewer District
588 A.2d 176 (Supreme Court of Connecticut, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
1992 Conn. Super. Ct. 1020, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wright-v-woodridge-lake-sewer-district-no-0043504-jan-7-1992-connsuperct-1992.