Wright v. Stevens

445 So. 2d 791
CourtMississippi Supreme Court
DecidedJanuary 4, 1984
Docket53941
StatusPublished
Cited by20 cases

This text of 445 So. 2d 791 (Wright v. Stevens) is published on Counsel Stack Legal Research, covering Mississippi Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wright v. Stevens, 445 So. 2d 791 (Mich. 1984).

Opinion

445 So.2d 791 (1984)

Robert B. WRIGHT, Jr., d/b/a Snapco Pools, Appellant,
v.
Ronald A. STEVENS and Sharon L. Stevens, Appellees.

No. 53941.

Supreme Court of Mississippi.

January 4, 1984.

*792 Russell D. Thompson, Ocean Springs, for appellant.

William H. Myers, Gordon, Myers & Gordon, Pascagoula, for appellee.

Before PATTERSON, C.J., and HAWKINS and ROBERTSON, JJ.

ROBERTSON, Justice, for the Court:

I.

This case arises out of a contract to build a swimming pool in the Plaintiffs Stevens' backyard in Ocean Springs, Mississippi. The contractor failed timely to complete the work. The Stevens hired a new contractor to complete the job and brought suit against the original contractor to recover all damages over and above that which they had originally contracted to pay.

A petit jury of the Circuit Court of Jackson County returned a verdict in favor of the homeowner Stevens. We affirm on liability although, for the reasons explained below, we must reduce the damage award.

II.

A.

Robert B. Wright, Jr., Defendant below and Appellant here, does business as a swimming pool contractor under the trade name of Snapco Pools, and is hereinafter referred to as "Wright". Ronald A. Stevens and Sharon L. Stevens, Plaintiffs below and Appellees here, own a residence in Ocean Springs, Mississippi. The Plaintiffs Stevens are hereinafter collectively referred to as "Stevens" or "the Stevenses".

On June 1, 1980, Wright and Stevens entered into a swimming pool contract. For a consideration of $10,750 to be paid as the work progressed, Wright obligated himself to construct a swimming pool in the Stevens' backyard. Wright agreed that he would complete the swimming pool "in a substantial and workmanlike manner according to accepted trade practices". Wright warranted "all materials, equipment and workmanship for a period of two years".

The contract called for completion of the swimming pool within sixty (60) days, to-wit:

The contractor is responsible for completion within a reasonable time period herein stated to be sixty (60) days.

The same paragraph of the contract further provided that:

The contractor shall not be responsible for damage or delay due to inclement weather, civil disturbances, acts of God, or other causes beyond his control.

The essence of the contract was that Wright would construct on the Stevens' premises a completed, usable and serviceable swimming pool and that he would do so in a timely and workmanlike manner, beginning June 1, 1980.

The topography of the Stevens' backyard was unusual. Much of the area where the swimming pool was to be located consisted of a severe slope which dropped approximately one foot for every horizontal foot. Wright had inspected the premises before entering into the swimming pool construction contract.

*793 Upon signing the contract on June 1, Stevens paid Wright $1,000.00. For two and a half weeks, Wright was not heard from. Then Wright called and asked for a $3,000.00 payment so he could pay for the pool sides. Stevens gave Wright this amount, and on June 23 or June 24, Wright delivered the pool sides to the Stevens' backyard. Wright then disappeared for another eight to ten days.

Shortly after the first of July, Wright returned to the site with a bulldozer and backhoe and began to dig. In due course, Wright asked Stevens for the $6,000.00 that was to become due when the site was excavated and all materials were present. Stevens objected, claiming that excavation was not complete nor were all materials present. Wright, however, convinced Stevens to part with $3,000.00, with the agreement that Stevens would pay the remaining $3,000.00 when the rest of the materials were brought to the site.

About a week later, Wright brought most of the pool accessories listed in the contract onto the premises. At this time Stevens paid Wright an additional $2400.00. The $600 was withheld because Wright had not yet acquired the Polaris vacuum sweep. The $2400.00 check in hand, Wright disappeared again.

On July 23, 1980, Stevens contacted Wright to find out when the pool was going to be completed. Wright assured him that the August 1 deadline would be met. Again nothing happened. On July 29, 1980, Stevens addressed a letter to Wright advising that it was apparent that the August 1 deadline would not be met and that the parties should negotiate an extension of time for the completion of the contract. Wright did not respond.

On August 1, 1980, Stevens posted the property. A controversial telephone conversation occurred between Stevens and Wright wherein Wright claims that Stevens declared the contract terminated. Stevens denied this. Thereafter Wright acknowledges that there was an agreement for an "undefined continuation" between the parties whereunder Wright was to return to the premises and "complete the work".

At this point the lawyers for the parties got into the act. One issue was that Stevens had still not paid the final $600 of the sums due when excavation had been completed and all materials had been delivered to the job site. Stevens had continued to withhold payment because the Polaris vacuum sweep still had not been delivered. The parties negotiated an agreement under which the disputed $600 was placed in escrow to be paid to Wright upon delivery of the vacuum. The agreement was consummated when Wright delivered the vacuum to the Stevens' home on August 13, 1980.

Wright returned to the premises on August 20 and worked for approximately one hour and a half. He then disappeared not to be heard from again until after Stevens had filed suit, his declaration being lodged with the Circuit Clerk of Jackson County on October 6, 1980.

In late October, Stevens negotiated with two other swimming pool contractors, William R. Boyd and Fred Hinckel, for the completion of the swimming pool. Boyd ultimately contracted with Stevens for this completion work. When Stevens made his contract with Boyd, it had been 65 days since Wright had been heard from.

Boyd testified that when he arrived at the site it appeared as though approximately one-third of the labor on the pool had been completed and that 40 to 50 percent of the necessary materials were on the site. Hinckel testified that when he saw the job site in October of 1980 the pool was 20 to 25 percent complete.

As Wright abandoned the project, the sides of the pool were standing in "bare air". The cement had been poured for the bottom of the pool. Still, the sides of the pool were threatening to come loose from the base and one actually did before the pool was completed. Stevens' primary incentive for hiring a new contractor was the threat of the pool rolling down the hill into a bayou that bordered the back of his property.

*794 Boyd completed the swimming pool on November 5, 1980. The costs of completion are:

  Completed swimming pool
  construction                          $5,250.00
  Repair damage to pool                    190.00
  Additional dirt                        1,524.25
  Spreading dirt, packing, bringing
  to grade, sodding                      1,621.00
  Labor and materials in retaining
  wall                                   1,340.00
                                       __________
                                        $9,925.25

In fact, the retaining wall was installed some two months later when it appeared as though the dirt was going to wash away.

B.

On October 6, 1980, Stevens commenced this action by filing his declaration in the Circuit Court of Jackson County.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Li v. Wooten
S.D. Mississippi, 2021
Wilson v. DiCosola
815 N.E.2d 975 (Appellate Court of Illinois, 2004)
Clark v. Illinois Cent. R. Co.
872 So. 2d 773 (Court of Appeals of Mississippi, 2004)
Southland Enterprises, Inc. v. Newton County
838 So. 2d 286 (Mississippi Supreme Court, 2003)
Sumrall Church of the Lord Jesus Christ v. Johnson
757 So. 2d 311 (Court of Appeals of Mississippi, 2000)
New Bellum Homes, Inc. v. Keith Giffin
Mississippi Supreme Court, 1998
Ciba-Geigy Corp. v. Murphree
653 So. 2d 857 (Mississippi Supreme Court, 1995)
New Hampshire Ins. Co. v. Sid Smith & Assoc., Inc.
610 So. 2d 340 (Mississippi Supreme Court, 1992)
Warwick v. Matheney
603 So. 2d 330 (Mississippi Supreme Court, 1992)
Haden v. Krupp Asset Management Corp.
776 F. Supp. 1151 (S.D. Mississippi, 1990)
Andrew Jackson Life Ins. Co. v. Williams
566 So. 2d 1172 (Mississippi Supreme Court, 1990)
Burley v. Homeowners Warranty Corp.
773 F. Supp. 844 (S.D. Mississippi, 1990)
Short v. Columbus Rubber and Gasket Co.
535 So. 2d 61 (Mississippi Supreme Court, 1988)
Schwegmann Giant Super Markets v. Golden Eagle Insurance
693 F. Supp. 478 (E.D. Louisiana, 1988)
Hood v. Oakley
519 So. 2d 1236 (Mississippi Supreme Court, 1988)
Aetna Cas. & Sur. Co. v. Day
487 So. 2d 830 (Mississippi Supreme Court, 1986)
Vickers v. First Mississippi Nat. Bank
458 So. 2d 1055 (Mississippi Supreme Court, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
445 So. 2d 791, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wright-v-stevens-miss-1984.