Wright v. Bateson

122 N.W.2d 683, 370 Mich. 660, 1963 Mich. LEXIS 428
CourtMichigan Supreme Court
DecidedJuly 17, 1963
DocketCalendar Nos. 24, 25, Docket Nos. 49,597, 49,611
StatusPublished

This text of 122 N.W.2d 683 (Wright v. Bateson) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wright v. Bateson, 122 N.W.2d 683, 370 Mich. 660, 1963 Mich. LEXIS 428 (Mich. 1963).

Opinion

Carr, C. J.

This case has resulted from contracts entered into for the construction of a section of the Ohio turnpike in 1955. Said section comprised approximately 11-1/2 miles of highway and was des[662]*662ignated as projects C-53, C-54, and C-55. The general contractors for the work were Terry & Wright, Inc., and Calumet Paving Company. The plans contemplated two 24-foot strips of Portland cement concrete with a 10-foot bituminous paved shoulder on the outside of each strip and an 8-foot paved shoulder on the inside of each strip of concrete. The concrete work was performed by Calumet Paving Company and is not here involved.

In the construction of the shoulders to the concrete strips there was placed a base of porous material for the purpose of affording drainage as well as support. This portion of the project was performed by Terry & Wright. The added construction .required was taken over by plaintiff in the present case, doing business as Wright Construction Company. The contract required the placing of a layer of heavy stone, No. 2 size, on top of the porous base which was required to be properly compacted. Bituminous material was specified, in the contract with the Ohio Turnpike Commission, to be applied to the stone, with a spreading of stone chips and a seal coat. The completion of the work required rolling to leave each shoulder with a smooth surface.

Plaintiff herein was the owner of 49% of the stock in Terry & Wright, Inc. A request for a copy of the contract between him and the general contractors was rejected by his counsel with a statement that there was no written contract. Testimony on the trial by the general superintendent, Orland Jones, of Terry & Wright, was to the effect that the contract was in writing; and. witness Belsheim, the project engineer on the section of the Ohio turnpike in question, likewise so testified, stating in substance that he had approved the contract. The duties and obligations of plaintiff Wright under said contract, whether written or oral, were not shown on the trial of the case.

[663]*663Under date of June 25, 1955, plaintiff entered into a subcontract with W. E. Bateson Company, a co-partnership consisting of William E. Bateson and his wife, Ethel I. Bateson, for the spreading of the bituminous material on the stone required to be laid by plaintiff. Defendant Fidelity & Casualty Company obligated itself as surety on the bond given for the faithful performance of the agreement. Said partnership, hereinafter referred to as Bateson, was required to furnish all equipment necessary for the doing of the work. The agreement further specified that Bateson as subcontractor should schedule the trucks furnished by plaintiff and should remedy any defects in the work performed under the contract. Subdivision 5 of the agreement read as follows:

“There is a maximum or minium amount of bituminous material, choke stone and cover stone set forth in principal contractors’ units of work. All quantities used over average will be charged back against subcontractor in their full value.”

The agreement did not set forth the maximum and minimum amounts of material referred to in the language quoted, nor do we find it elsewhere in the appendix filed in this Court on appeal. The agreement declared that time of performance was of the essence thereof, and that the work assumed by Bateson should be completed not later than September 1, 3955. However, for reasons that are in dispute, the Bateson subcontract was not fully performed on the date specified. Apparently the general contractors (and the Ohio Turnpike Commission as well) felt that the portion of the project covered by the contract between them and the plaintiff was not progressing satisfactorily. On August 17, 1955, a meeting was held in the office of engineer Belsheim to discuss the situation. Criticism of the progress of the work, and of details in connection [664]*664therewith, with particular reference to the stone that had been laid, was met with assurances by Wright as to his intentions to make certain changes and to obtain more adequate supervision. On August 31st following a second meeting was held by representatives of the Turnpike Commission, Mr. Wright, and others. Bateson was not present at either of these conferences. An agreement was reached that, because of the lack of satisfactory progress, the work would be placed entirely under the supervision of Terry & Wright, Inc., and Wright Construction Company would be relieved of responsibility insofar as supervision was concerned. Thereafter Terry & Wright had charge, with its general superintendent, Mr. Jones, acting in behalf of the general contractors until the completion of the work on September 27, 1955.

On September 6, 1955, plaintiff and Bateson entered into a supplemental contract, to which the defendant Fidelity & Casualty Company of New York was a party, referring to supervision of the remaining work by Terry & Wright and further specifying that Bateson, with the partnership equipment and employees, should remain on the job until all work had been finished. Under this supplemental agreement plaintiff Wright was required to furnish such equipment as might be necessary to finish the job by the completion date established by the Ohio Turnpike Commission. Subdivision 4 of this agreement is significant in the instant controversy. It reads as follows:

“Wright shall pay Bateson in accordance with the minimum application unit prices set forth in the subcontract between Wright and Bateson. Bateson shall carry the costs of any ‘overrun’ over and above the required application. Materials shall not be charged to Bateson. The payments made by Wright to Bateson shall be made on the earned amount per[665]*665formed by Bateson, under the terms of the subcontract, but there shall first be deducted from said payments, equipment rental, cost of supervision and miscellaneous expenses. Payment shall be made weekly. Fidelity & Casualty Company shall pay any deficiencies of costs.”

The supplemental agreement also declared that except as modified thereby the subcontract between Wright and Bateson should remain in force and effect. As before noted, the work was completed on September 27, 1955. Thereafter, under date of December 21, 1955, plaintiff presented to Bateson and to claim agents of defendant Fidelity & Casualty Company a list of claims against Bateson aggregating $7,503.45. Included therein Avere various items apparently covering payments made by plaintiff and' also items charged by Terry & Wright, Inc. It appears from the testimony of the representatives of defendant Fidelity & Casualty Company that the claims of plaintiff as set forth in his statement of account were not admitted by Bateson, or by them on behalf of their company. Apparently they had no authority to make any agreement binding their principal. In any event, plaintiff’s apparent attempt to procure a voluntary settlement of moneys that he claimed were owing to him by Bateson, or from the surety on Bateson’s bond, ended in failure.

The instant suit was started August 27, 1956, plaintiff seeking to recover damages on the theory of breach of contract. Prior to the bringing of the action William E. Bateson died, and Mrs. Bateson, as surviving partner, was named as a defendant with the Fidelity & Casualty Company of New York.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gilmer v. Miller
29 N.W.2d 264 (Michigan Supreme Court, 1947)

Cite This Page — Counsel Stack

Bluebook (online)
122 N.W.2d 683, 370 Mich. 660, 1963 Mich. LEXIS 428, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wright-v-bateson-mich-1963.