Wright Contracting Co. v. Saint Paul Mercury Indemnity Co.

151 F. Supp. 179, 1957 U.S. Dist. LEXIS 3527
CourtDistrict Court, W.D. North Carolina
DecidedMay 9, 1957
DocketCiv. No. 1201
StatusPublished
Cited by1 cases

This text of 151 F. Supp. 179 (Wright Contracting Co. v. Saint Paul Mercury Indemnity Co.) is published on Counsel Stack Legal Research, covering District Court, W.D. North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wright Contracting Co. v. Saint Paul Mercury Indemnity Co., 151 F. Supp. 179, 1957 U.S. Dist. LEXIS 3527 (W.D.N.C. 1957).

Opinion

WARLICK, District Judge.

This action is brought by plaintiff to recover of the defendant, Saint Paul Mercury Indemnity Company, the sum of $12;707.81 which it alleges it is entitled to have for that it was compelled to pay that amount in exoneration of its bond, previously executed in connection with a contract it obtained for road work in North Carolina.

The action is laid in this court under the diversity statute. Title 28 U.S.C. § 1332.

■' Plaintiff, Wright Contracting Com■pany, a corporation, is a citizen of the State of Georgia; 'the defendant, Saint Paul Mercury Indemnity Company, is a corporation, and a citizen of the State of Delaware. J. A. Polhill, W. K. Dedmon, ’ and Russell Stroüpe, third-party defendants, are citizens and reside in Lincoln "‘County in the Western' District of North Carolina.

On January 12,’ 1954, plaintiff, Wright Contracting Company, was low bidder and entered into a contract with the North Carolina State Highway and Public Works Commission to do certain road construction work known as State Highway Project No, 4839, in Durham and Wake Counties in North Carolina, and in line with the requirements of North Carolina General Statutes, § 136-28, executed a bond as therein required as principal with the National Surety Corporation of New York as surety in the penal sum of $1,224,390.09, conditioned among other things that plaintiff “shall well and truly pay all and every person furnishing material or performing labor in and about the construction of said project all and every sum or sums of money due him, them or any of them, for all such labor and material's for which the contractor capitalized is liable”.

Under date of February 10, 1954, plaintiff’ entered into a subcontract, which was reduced to writing, with the Lincoln Contractors, Inc., a North Carolina corporation, for certain hauling in connection with said project No. 4839. This subcontract provided among other things as follows:

“A. You, as Hauling Sub-Contractor, agree to furnish and supply all labor, equipment, fuel, tools, supplies and any and all other facilities, whatsoever necessary for doing the hauling hereinafter specified for the prices stipulated.
. “B. Payments are to be made to Hauling Sub-Contractor by Contractor once each month, based on quantities to be determined as hereto- ■ ■fore specified, except that 10% of the total will be retained until the completion of the work involved in this contract, at which time retain-age withheld will be paid to Hauling Sub-Contractor upon presentation of proof that all bills for labor and materials in connection with the work have been paid in fulh' •
“C. In support of this agreement Sub-contractor is to furnish to Contractor a performance and payment bond in the sum of $50,000.00.”

On said date Lincoln Contractors, Inc., as principal and Saint Paul Mercury Indemnity Company as surety executed a performance bond in favor of and delivered same to Wright Contracting Company in the penal amount of $50,000. Among other things said subcontract bond provided as follows:

“Whereas, the Principal and the Obligee have entered into a written contract, a copy- of which is or may be attached hereto, dated the 10th [181]*181day of February, 1954, for furnish- , ing and supplying all labor, equipment, fuel, tools, supplies and any and all other facilities whatsoever necessary for doing certain hauling in connection with the construction of Project No. 4839 SF — 548(8) and F-447(7), Durham and Wake Counties, North Carolina, the hauling specified in Contract Agreement letter, dated February 10, 1954.
“Now, Therefore, the condition of the foregoing obligation is such that if the Principal shall indemnify the Obligee for all loss that .the Obligee may sustain by reason of the Principal’s failure to comply with’ any of the terms of said contract, then this obligation shall be void; otherwise it shall remain in force.”

Before the defendant would agree to execute to the plaintiff its indemnity bond in the said sum of $50,000, conditioned on the full compliance of Lincoln Contractors, Inc., with the terms of the contract, it required that the officials of said Lincoln Contractors, Inc., execute to it an indemnity bond conditioned on the fact that they individually and ás officials of the corporation, would save the defendant, Saint Paul Mercury Indemnity Company harmless from any liability that might arise from the failure of Lincoln Contractors, Inc. to fulfill and complete its subcontract of hauling as entered into with the plaintiff herein, and in compliance therewith, J. A. Polhill as President, and Dedmon and Stroupe as officials of the company, executed under seal, etc., and delivered to the defendant, Saint Paul Mercury Indemnity Company, such bond of indemnity.

Thereafter Lincoln Contractors, Inc. began the performance of its contract with plaintiff and in due season completed' the hauling work in its entirety, paid the payroll of its employees in full, and paid some but not all of the bills of those suppliers who furnished materials and rendered services which were used in the work performed under its said subcontract.

■ On January 8, 1955 Lincoln Contractors, Inc. was adjudicated a bankrupt in the District Court of the United States for the Western District of North Carolina. Thereafter certain creditors of the bankrupt made demand on and filed claims with plaintiff, in the sum of $40,-648.79, and subsequently four separate law suits were instituted against plaintiff in the Superior Court of Wake County, North Carolina. Whereupon the plaintiff, following considerable investigation and under its bond executed to the North Carolina State Highway and Public Works Commission, and the provisions thereof, paid the sum of $17,475.39 to all and every of the creditors of Lincoln Contractors, Inc., in full, and in addition thereto paid legal expenses incurred in the amount of $3,412.80.

At the time Lincoln Contractors, Inc. was adjudicated a bankrupt plaintiff-had in its possession as retained by it under the contract with the bankrupt, the sum of $8,180.38, which amount was credited against the sums paid by plaintiff in settlement of the liabilities of the bankrupt, and in such computation plaintiff has " sustained a loss in the amount of $12,707.81. On ascertaining its net loss ' plaintiff made demand upon the defendant, Saint Paul Mercury Indemnity Company, to be reimbursed for the loss which it had suffered. Thereupon the defendant Saint Paul Mercury Indemnity Company denied liability and refused to indemnify the plaintiff. The last and final payment to the creditors of the bankrupt ' was made by Wright Contracting Company on December 27, 1956.

When the claim was made by plaintiff on the defendant Saint Paul Mercury Indemnity Company for the amount plaintiffs had been compelled to expend for the bankrupt in satisfying those who had furnished supplies and performed services, the Indemnity Company moved that J. A. Polhill, W. K. Dedmon, and Russell Stroupe be made third-party defendants and that it be given full authority to have issued at its request, a summons against the third-party defendants so that the Indemnity Company’s rights [182]*182could be protected in one action.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
151 F. Supp. 179, 1957 U.S. Dist. LEXIS 3527, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wright-contracting-co-v-saint-paul-mercury-indemnity-co-ncwd-1957.