WPS, Inc. v. Enervest Operating, LLC

CourtCourt of Appeals of Texas
DecidedMay 28, 2010
Docket01-06-00759-CV
StatusPublished

This text of WPS, Inc. v. Enervest Operating, LLC (WPS, Inc. v. Enervest Operating, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
WPS, Inc. v. Enervest Operating, LLC, (Tex. Ct. App. 2010).

Opinion

Opinion issued May 28, 2010.





In The

Court of Appeals

For The

First District of Texas

____________



NO. 01-06-00759-CV



WPS, INC., Appellant



V.



ENERVEST OPERATING, L.L.C., Appellee



On Appeal from the 127th District Court

Harris County, Texas

Trial Court Cause No. 2004-35036



MEMORANDUM OPINION ON REHEARING On November 23, 2009, the Court issued its opinion and judgment in this case. Appellant, WPS, Inc. ("WPS"), moved for rehearing, and appellee, EnerVest Operating, L.L.C. ("Evervest"), responded. We grant WPS's rehearing motion, withdraw our opinion and judgment of November 23, and issue this opinion and judgment in their stead, although the disposition of the case remains unchanged.

WPS appeals a final judgment, rendered upon trial to the jury and to the bench, in favor of EnerVest for actual damages and attorney's fees. We determine whether (1) the trial court abused its discretion in charging the jury; (2) legally and factually sufficient evidence supported the verdict; (3) various contractual provisions precluded or limited EnerVest's recovery; (4) the trial court correctly concluded that EnerVest provided the insurance required by the parties' contract; and (5) WPS preserved or adequately briefed certain of its appellate challenges. We affirm.

The Parties

EnerVest was an oil-and-gas acquisition company. EnerVest hired Baker Energy ("Baker") to run its day-to-day well operations. WPS made compressor packages--skids, compressors, and related machinery--which compress natural gas to inject into low-pressure oil or gas wells to improve production. EnerVest had a standing "Master Service Contract" (the "MSC"), dated December 2, 2002, with WPS. In December 2003, EnerVest rented a compressor package from WPS for its Garden Island Bay facility. The parties signed two contracts as part of this rental: (1) a "Rental Agreement" to lease the compressor and (2) a "Maintenance Services Contract" for service of the compressor package, along with an addendum thereto.

The Dispute

The WPS compressor was first run on February 5, 2003. Between that date and March 25, 2003, the date of the fire giving rise to this suit, the compressor had many problems and was frequently out of service. The parties dispute which of them was responsible for the problems. On March 25, the Baker contractors at the site heard a large gas leak. They spent 15 to 20 minutes trying to locate the leak. After they had determined that the leak was coming from the area of the WPS compressor, they decided to start the back-up compressor and to shut down the WPS one; however, before they could do so, the gas ignited from the heat of the WPS compressor, causing a fire.

No one disputes that a failed needle valve in the WPS compressor caused the gas leak, but they dispute (1) whether the needle valve failed because it was defective (EnerVest's position); (2) whether, instead, EnerVest improperly installed the compressor, causing vibrations that in turn broke the valve, causing the leak (WPS's position); and (3) whether the Baker contractors caused the fire because they improperly failed to shut off the compressor when they first heard the leak (WPS's position).

The fire burned for hours, destroying the compressor. EnerVest wanted WPS to provide a new compressor, to remove the damaged one, and to reimburse EnerVest its rental pre-payments for the months that the compressor was damaged; WPS wanted EnerVest to pay for the compressor to be fixed.

The Procedural History

The parties eventually sued each other. EverVest sued WPS for (1) breach of the Rental Agreement because WPS "promised a working compressor and delivered a compressor that never performed as warranted and ultimately failed to perform at all"; (2) breach of the MSC's express-warranty provision; and (3) breach of the Maintenance Services Contract addendum's 95%-uptime guarantee. EnerVest sought declarations that (1) WPS was obliged under the MSC to indemnify EnerVest; (2) EnerVest had no obligation to repair or to replace the compressor; and (3) because of the fire, EnerVest has no further obligations to WPS under any contract. WPS counterclaimed for (1) breach of the Rental Agreement, including failure to pay rent, failure to obtain insurance, and failure to repair the compressor, and (2) negligence, including failure to install the compressor properly and to turn off the compressor after the leak. WPS also sought damages under the theory of promissory estoppel for EnerVest's "failing to abide by its promise to obtain insurance acceptable to WPS."

Upon cross-motions for summary judgment, the trial court ruled that the Rental Agreement's indemnity clause applied and that EnerVest was obligated "to provide insurance to cover the loss in question," although the court verbally altered the latter ruling at the start of trial to be that EnerVest was obliged to procure the insurance required by the Rental Agreement. EnerVest's claim for breach of the MSC's express-warranty provision and its requests for declarations were not submitted to the jury or the trial court. EnerVest's claim for breach of the Maintenance Services Contract addendum's 95%-uptime guarantee was submitted to the jury, which found against EnerVest. The trial court also submitted a jury question on EnerVest's breach of the Rental Agreement--albeit not in broad-form manner and inquiring about an "internal defect" to the compressor--on which the jury found in EnerVest's favor. None of WPS's claims were submitted to the court or jury except for its claim that EnerVest had breached the Rental Agreement by failing to procure proper insurance; the parties submitted this one claim to the trial court, which ruled against WPS. The parties also submitted the issue of attorney's fees to the trial court, which ruled in EnerVest's favor and awarded it fees. The trial court entered findings of fact and conclusions of law and overruled WPS's post-judgment motions. WPS appeals.

Jury Charge Issues

In its issue "A," WPS raises three complaints about the jury charge.

A trial court must give "such instructions and definitions as shall be proper to enable the jury to render a verdict." Tex. R. Civ. P. 277 (emphasis added). An instruction is proper if it assists the jury, accurately states the law, and is supported by the pleadings and the evidence. See Tex. Worker's Comp. Ins. Fund v. Mandlbauer, 34 S.W.3d 909, 912 (Tex. 2000); Tex. R. Civ. P. 278.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ronald Goodman v. Fireman's Fund Insurance Company
600 F.2d 1040 (Fourth Circuit, 1979)
Golden Eagle Archery, Inc. v. Jackson
116 S.W.3d 757 (Texas Supreme Court, 2003)
Wal-Mart Stores, Inc. v. Miller
102 S.W.3d 706 (Texas Supreme Court, 2003)
EMC Mortgage Corp. v. Jones
252 S.W.3d 857 (Court of Appeals of Texas, 2008)
Texas Workers' Compensation Insurance Fund v. Mandlbauer
34 S.W.3d 909 (Texas Supreme Court, 2001)
Oyster Creek Financial Corp. v. Richwood Investments II, Inc.
176 S.W.3d 307 (Court of Appeals of Texas, 2004)
Coldwell Banker Whiteside Associates v. Ryan Equity Partners, Ltd.
181 S.W.3d 879 (Court of Appeals of Texas, 2006)
SMI Realty Management Corp. v. Underwriters at Lloyd's, London
179 S.W.3d 619 (Court of Appeals of Texas, 2005)
Merrell Dow Pharmaceuticals, Inc. v. Havner
953 S.W.2d 706 (Texas Supreme Court, 1997)
Dow Chemical Co. v. Francis
46 S.W.3d 237 (Texas Supreme Court, 2001)
Malcomson Road Utility District v. Newsom
171 S.W.3d 257 (Court of Appeals of Texas, 2005)
Plas-Tex, Inc. v. U.S. Steel Corp.
772 S.W.2d 442 (Texas Supreme Court, 1989)
Croucher v. Croucher
660 S.W.2d 55 (Texas Supreme Court, 1983)
St. Joseph Hospital v. Wolff
94 S.W.3d 513 (Texas Supreme Court, 2002)
Kroger Co. v. Brown
267 S.W.3d 320 (Court of Appeals of Texas, 2008)
City of Keller v. Wilson
168 S.W.3d 802 (Texas Supreme Court, 2005)
King Ranch, Inc. v. Chapman
118 S.W.3d 742 (Texas Supreme Court, 2003)
Wheeler v. Methodist Hospital
95 S.W.3d 628 (Court of Appeals of Texas, 2002)
Howeth Investments, Inc. v. City of Hedwig Village
259 S.W.3d 877 (Court of Appeals of Texas, 2008)
Castleberry v. Branscum
721 S.W.2d 270 (Texas Supreme Court, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
WPS, Inc. v. Enervest Operating, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wps-inc-v-enervest-operating-llc-texapp-2010.