Worthington Pump C. Cor. v. Briarcliff Inc.

19 S.E.2d 574, 67 Ga. App. 71, 1942 Ga. App. LEXIS 338
CourtCourt of Appeals of Georgia
DecidedMarch 20, 1942
Docket29342.
StatusPublished
Cited by1 cases

This text of 19 S.E.2d 574 (Worthington Pump C. Cor. v. Briarcliff Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Worthington Pump C. Cor. v. Briarcliff Inc., 19 S.E.2d 574, 67 Ga. App. 71, 1942 Ga. App. LEXIS 338 (Ga. Ct. App. 1942).

Opinion

It appearing that there was a written contract covering the sale of the engine from the plaintiff to the defendant, which contained certain stipulations and warranties by the plaintiff, a recovery by the defendant on a cross-action for damages alleged to have been sustained because of the nonperformance of an breach of conditions and warranties, not contained in the written contract but expressly excluded therefrom, was contrary to law and without evidence to support it. It was error to overrule the plaintiff's motion for new trial.

DECIDED MARCH 20, 1942.
The Worthington Pump and Machinery Corporation brought suit on account against Briarcliff Gardens Inc., to recover a balance of $549.45 alleged to be due for certain machinery and gas-engine parts which were sold on open account by the plaintiff to the defendant as shown by an itemized statement of account attached to the petition. The defendant admitted the correctness of the account sued on but denied liability on the ground that the plaintiff, a non-resident corporation, was indebted to the defendant in an amount in excess of the sum sued for. By way of "set-off or recoupment" the defendant alleged that the plaintiff was indebted to it $17,561.21 as damages growing out of the failure to perform and breach by the plaintiff of a contract under which the defendant purchased a certain gas engine. By the counter-claim the defendant alleged substantially the following facts: On December 17, 1935, the plaintiff sold to the defendant an internal-combustion engine to be operated by natural gas. This engine was purchased for the purpose of operating an electric generator to generate electricity to be used in the operation by the defendant of a laundry, and to furnish current for lights and electric power on the defendant's premises. The plaintiff agreed to furnish to the defendant an expert to supervise the installation of this engine and its parts, and *Page 72 to start the engine off properly. This expert was called an "erector." The plaintiff was informed and knew what such engine and the electric generator were to be used for and knew the character of the business for which the electricity was to be generated. This machinery was installed during the spring of 1936 under the supervision and direction of such "erector." The machinery was put into operation and appeared to be operating properly, and therefore the defendant accepted the machinery and its installation and began making installment payments to the plaintiff on the purchase-price. Thereafter, in the early part of 1937, and after the laundry plant of the defendant had been enlarged so that it required almost the full-rated capacity of such machinery to supply the necessary electric power and current needed, this gas engine began to break down periodically, which would require the operation of the engine to be discontinued until the necessary parts could be obtained and the engine overhauled and repaired. This happened on several occasions until the defendant, in order to obtain the required electric power so as to keep its laundry plant in operation, had to have a line installed and connected with the electric power lines of the Georgia Power Company, so that the defendant could purchase electric current from the Georgia Power Company and thus operate its laundry. The installation of this line from the plant to the Georgia Power Company, so that the defendant's expense, and in order to obtain the necessary current from the power company the defendant was required to contract with the power company to pay to it a minimum monthly charge for electric current for a period of twelve months, and the current which the defendant thus purchased from the power company cost the defendant more than it would have cost the defendant to generate such electric power with the engine and machinery it had purchased from the plaintiff for that purpose had such engine and machinery operated properly and had the engine operated according to its rated capacity.

It was thereafter discovered that the cause of the frequent breakdowns of the engine and the failure of the machinery to properly run the generator was that such engine was not getting a sufficient supply of water to keep it cool which caused the engine to overhead and burn out its values and other parts. Although the plaintiff knew all the time what the trouble with the engine was it *Page 73 did not inform the defendant thereof, and did not tell the defendant how to correct such trouble "until after the defendant had finished paying all of the installments on the machinery." It was then that the plaintiff's representative for the first time told the president of the defendant what the trouble with the engine was and how to correct it. The water supply for cooling the engine was obtained from a large elevated water tank, which the defendant had on its premises adjacent to the house wherein this engine was lodged, and the water passed from this tank into and through the water jackets of the engine by gravity pressure alone. The elevation of this tank was not sufficient enough gravity pressure to keep the water circulating in the engine and to maintain the circulation of the water in the engine so as to keep it cool when it was being operated at or about its full-rated capacity. The "erector" of the plaintiff, who supervised the installation of the machinery, failed and neglected to inform the defendant that this water tank was not elevated sufficiently to furnish the water required by the engine, although he knew that such tank was not sufficiently elevated for this purpose. As soon as the defendant was told by the plaintiff what was causing the failure of this engine to function, the defendant at a nominal cost had this water tank sufficiently elevated, and from that time on the defendant had no trouble with such engine. The whole cause of the engine trouble had been that this water tank was too low to afford sufficient gravity pressure to cause the water to run freely into the engine and circulate through its cooling system. As a result of the improper manner in which the machinery had been installed, under the supervision and direction of the plaintiff by the "erector" of the plaintiff, the defendant had to purchase from the plaintiff parts of machinery to replace those parts which had been burned out, to the amount of $1077.26, and also had to purchase parts from others amounting to $339.50. In order to get the Georgia Power Company to furnish electricity to the defendant's premises it cost the defendant $1121.61 to install the necessary electric lines and fixtures, and the defendant also had to contract to pay to the Georgia Power Company for a period of twelve months a minimum stand-by charge of $105 per month. Also during the period while this engine was broken down the defendant was required and did purchase from the Georgia Power Company electric current at a cost of $3143.36 in *Page 74 excess of what it would have cost the defendant to generate the same amount of electricity had such engine and machinery been skillfully and properly installed so as to function properly, and the defendant has paid the Georgia Power Company $420 of the minimum stand-by charge which the defendant contracted to pay for a period of twelve month, and will be required to pay for the remainder of such twelve months the sum of $840, although since the defendant corrected the improper installation and fault of the engine and machinery by elevating the water tank it is not necessary to use any of the electric current of the Georgia Power Company, all of which loss and damage to the defendant is directly due to the plaintiff's failure to perform its obligations under the contract of purchase to skillfully supervise the installation of the machinery.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lander Motors, Inc. v. Lee Tire & Rubber Co.
78 S.E.2d 839 (Court of Appeals of Georgia, 1953)

Cite This Page — Counsel Stack

Bluebook (online)
19 S.E.2d 574, 67 Ga. App. 71, 1942 Ga. App. LEXIS 338, Counsel Stack Legal Research, https://law.counselstack.com/opinion/worthington-pump-c-cor-v-briarcliff-inc-gactapp-1942.