Wooton v. McAdoo

293 P. 694, 110 Cal. App. 48, 1930 Cal. App. LEXIS 113
CourtCalifornia Court of Appeal
DecidedNovember 24, 1930
DocketDocket No. 139.
StatusPublished
Cited by6 cases

This text of 293 P. 694 (Wooton v. McAdoo) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wooton v. McAdoo, 293 P. 694, 110 Cal. App. 48, 1930 Cal. App. LEXIS 113 (Cal. Ct. App. 1930).

Opinion

BARNARD, J.

These two actions were consolidated for trial and from a judgment entered as applying to each case, this appeal is taken.

The plaintiffs in each case are the owners of a lot twéntyfive feet wide and fifty feet deep, on the outskirts of the Huntington Beach oil-field. The two lots adjoin, and taken together, formed a unit of land large enough to hold a derrick for drilling, but not of sufficient size to hold such a derrick and also the boiler and other equipment necessary to operate the same. The defendants in these two eases were the owners of a lease upon another lot situated 117 feet from the lots owned by these plaintiffs, upon which *51 they drilled what is referred to in the lease contracts here in question, as the first well. The defendants undertook to lease the two lots separately owned by the plaintiffs, and to drill for oil thereon by using power brought from their power plant installed in connection with the first well. The first lease with plaintiffs Wooton was signed on July 24, 1926, and a second or substitute lease with the same plaintiffs was signed on September 28, 1926. The lease with plaintiff Seeger was signed on August 6, 1926. Bach of these leases referred to the above-mentioned first well, and then to a second well to be drilled upon the lots owned by these plaintiffs. Neither of the leases contains any provision as to when the first well is to be commenced or completed, but each lease provides that the second well is to be commenced after the discovery of oil in paying quantities in the first well, and thereupon, the lessees are “to commence drilling operations within ninety days thereafter and continuously operate one string of tools until said second well has been drilled with due diligence to a depth of 4,000 feet unless oil in paying quantities is discovered at a lesser depth”. Bach of the leases also contains the following provision: “The lessee may at any time before discovery of oil on the demised premises quitclaim the real property or any part thereof to the Lessor, his successors or assigns, and thereupon all rights and obligations of the parties hereto one to the other, shall thereupon cease and determine as to the premises quit-claimed.”

Bach of the leases provides for a royalty to the lessor of a certain percentage of the oil that might be produced from the second well, together with a bonus of a percentage royalty interest in the first well. As such bonus, out of the proceeds from the first well the plaintiffs received over $4,100. The defendants subleased the property to one Gather, and thereafter, Gather, together with defendants and their respective wives, made another sublease to one Fred W. Roberts. Roberts entered upon the property and sunk a well theron to a depth of 400 feet, when the work was abandoned. The court found that the work was abandoned for the reason “that prior to the time that the. respective leases required the defendants to drill and complete the well on the leased property, the field had been *52 intensively drilled by other operators and the oil supply therein practically exhausted”. These actions were filed, seeking to recover damages for alleged breach of agreement in failing to drill on time, and also for alleged misrepresentations. After a trial before the court without a jury, judgment was entered in favor of the defendants, and this appeal followed.

Each complaint sets forth five causes of action. A motion for a nonsuit was granted as .to the fourth cause of action. No appeal followed that order, leaving four causes of action to be considered here.

The first cause of action is for damages for failure to use due diligence in carrying on drilling operations to a depth of 4,000 feet. Appellants point out that when the Wooton lease was signed on July 24, 1926, it referred to the property on which the first well was located, saying: “Operations for drilling an oil well have already been commenced thereon.” It is pointed out that there was evidence that it took sixty-four days to complete the first well, that it was spudded in on September 12th and brought in November 15th. It is then argued that had the first well been started on July 24, 1926, as represented by the clause in the lease last above quoted, this well would have come in by September 26, 1926. This is the first breach of contract relied upon. Not only does it appear that it required both of these lots to make room for the installation of a derrick and that the Seeger lease was not signed until August 6th, but we are unable to put any such interpretation upon the contract. To say that operations for drilling an oil-well have already been commenced, is far from an assertion that drilling has already been commenced. Many things are necessary to be done in getting ready to drill an oil-well. The contract is silent as to when the first well was to be begun. If, as argued by appellants, it is a necessary implication that the first well was to be drilled and completed as soon as possible, nothing appears herein to indicate that the beginning of actual drilling on September 12th was an unreasonable delay.

With the assumption that the first well should have been completed on September 26, 1926, it is next argued that the second well should have been begun immediately thereafter, and that the same would have been completed *53 in sixty-four days, or by December. 27, 1926, at the latest. The argument is made that the real intention of the parties was to provide that the second well should be drilled as soon as the first one came in; that the ninety-day period for commencing the second well was intended to apply only in the event the production in the first well should be so small that such time would be required to determine whether or not it was a paying well; and that it is necessarily implied by law that when the first well came in with a good production, the lessees did not have the ninety days provided for in the contract within which to commence drilling the second well. To state this contention is almost to answer it. Not only does the contract govern, but it is self-evident that it requires some time to assemble sufficient equipment to drill an oil-well. Even if we could discard the contract and apply the reasonable time rule, we are unable to say that ninety days was an unreasonable time, in the absence of any evidence upon that point.

That the work on the well was later abandoned because production in surrounding wells decreased to an extent that made drilling seem unprofitable, is undisputed. Appellants’ cause of action is based upon the theory that the delay of respondents in drilling deprived them of an income that would otherwise have been available before this portion of the field became depleted. By the reasoning referred to, it is insisted that the second well should have been brought in by December 7, 1926. Appellants quote a witness as giving the opinion that a well on their lots would have been profitable until February, 1927, and that in May, 1927, an average production of 100 barrels a day from such a well could have been expected. Reference is also made to a number of surrounding wells, which are said to have been brought in successfully in January, 1927. Based upon production in some other wells, appellants estimate that they would have received from the second well over $11,000, between December 7, 1926, and October 31, 1928.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Black Light Corp. v. Ultra-Violet Products, Inc.
195 Cal. App. 2d 473 (California Court of Appeal, 1961)
Seeger v. Odell
148 P.2d 901 (California Court of Appeal, 1944)
Lewis v. Nance
66 P.2d 708 (California Court of Appeal, 1937)
Oakley Co. v. Butler
59 P.2d 826 (California Court of Appeal, 1936)
Bacigalupi v. Western MacHinery Co.
26 P.2d 701 (California Court of Appeal, 1933)
Gibbs v. Seeger
19 P.2d 514 (California Court of Appeal, 1933)

Cite This Page — Counsel Stack

Bluebook (online)
293 P. 694, 110 Cal. App. 48, 1930 Cal. App. LEXIS 113, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wooton-v-mcadoo-calctapp-1930.