WOODSTONE GROUP, LLC VS. PAUL TREACY (L-0639-17, MORRIS COUNTY AND STATEWIDE)

New Jersey Superior Court Appellate Division·Decided February 5, 2020·No. A-2418-18T2·Unpublished

Opinion

NOT FOR PUBLICATION WITHOUT THE APPROVAL OF THE APPELLATE DIVISION This opinion shall not "constitute precedent or be binding upon any court." Although it is posted on the internet, this opinion is binding only on the parties in the case and its use in other cases is limited. R. 1:36-3.

SUPERIOR COURT OF NEW JERSEY APPELLATE DIVISION

DOCKET NO. A-2418-18T2

WOODSTONE GROUP, LLC, Plaintiff-Respondent,

v.

PAUL TREACY and SARAH TREACY,

Defendants-Appellants.

Argued telephonically December 17, 2019 – Decided February 5, 2020

Before Judges Yannotti and Firko.

On appeal from the Superior Court of New Jersey, Law Division, Morris County, Docket No. L-0639-17.

David M. Miller argued the cause for appellants (Miller and Miller, attorneys; David M. Miller, on the briefs).

Michael Patrick Carroll argued the cause for respondent (Nish & Nish, attorneys; Robert J. Nish, on the brief).

PER CURIAM

Defendants Paul and Sarah Treacy appeal from a judgment entered by the Law Division on January 3, 2019, which awarded plaintiff Woodstone Group, LLC, $33,323.20 plus interest and costs, and dismissed defendants' counterclaims. We affirm.

I.

Plaintiff filed a complaint in the Law Division, alleging that in March 2012, the parties entered into a written contract, which required plaintiff to perform certain work at defendants' home, for a total of $158,100. Plaintiff claimed the parties amended the agreement to include additional work, at a cost of at least $8,188.40.

Plaintiff alleged that after it performed substantially all of the work, defendants terminated the contract "without cause" and refused to permit plaintiff to complete the project. Plaintiff claimed defendants failed to pay the amount due under the contract. Plaintiff asserted claims for breach of contract and quantum meruit. Plaintiff sought damages, interest, attorney's fees, and costs of suit.

Defendants filed an answer, affirmative defenses, and counterclaims.

Defendants asserted claims for violations of the New Jersey Consumer Fraud Act (CFA), N.J.S.A. 56:8-1 to -20, common law fraud, breach of contract,

A-2418-18T2

breach of the duty of good faith and fair dealing, breach of express and impl ied warranties, unjust enrichment, and negligence. Among other things, defendants alleged that plaintiff violated the CFA by failing to comply with regulations adopted pursuant to the CFA, which govern home improvement practices (the HIP regulations), N.J.A.C. 13:45A-16.1 to -16.2. Defendants also claimed that plaintiff performed certain work in a careless, negligent, or unprofessional manner.

The matter was tried before the Law Division judge, sitting without a jury.

Plaintiff's principal Christopher J. Saul testified that on March 9, 2012, the parties entered into a written contract which required plaintiff to make certain improvements to defendants' home in accordance with plans prepared by defendant's architect, Jerry A. Bruno, Jr. The contract required plaintiff to remove a portion of the rear of the house, excavate and build a new foundation, and construct a new eat-in kitchen, pantry, bathroom, and deck.

Saul explained that the initial contract price was about $147,900, and the parties agreed to add "two other components," specifically an upgrade to the electrical system and placement of a stone veneer on the home's foundation. The total agreed-upon contract price was $158,100. The contract required

A-2418-18T2

defendants to make an initial deposit of $29,580, four installment payments of $29,000, and a final payment of $2320 upon completion of the project.

Defendants also were required to pay for, among other things, permit fees, specialty lighting, and appliances. The contract stated that the project "should take approximately [three to four] months to complete" but the completion date could be affected by the weather, availability of supplies, and labor shortages. Defendants made the initial deposit of $29,580.

On March 22, 2012, the Township of Chatham's construction department approved the plans and issued a building permit for the project. Plaintiff began the work in April 2012, and defendants made the first installment payment of $29,000. The work continued and on June 14, 2012, defendants paid the second installment of $29,000. On July 23, 2012, defendants paid the third installment of $29,000. Mrs. Treacy asked Saul to adjust the wall in the kitchen area, and he agreed to make that change without any additional charge.

Saul testified that the fourth installment of $29,000 had been due after the second delivery of the cabinets. Defendants did not make that payment. Towards the end of August 2012, Mrs. Treacy left the United States for a vacation and was away for about two weeks. Saul said that during that time, plaintiff did not have access to the house and performed only a minimum amount

A-2418-18T2

of the work. According to Saul, when Mrs. Treacy returned, she did not complain about the work. He again asked her to pay the $29,000 installment. Defendants did not make the payment.

Saul stated that, in September 2012, plaintiff only had certain "miscellaneous carpentry, trim and details" to complete. On September 7, 2012, Bruno inspected the work and, several days later, he provided plaintiff with a punch list of work to be completed. Saul testified that plaintiff completed most of the items on the list.

Saul stated that at this time, Mrs. Treacy asked plaintiff to complete the project without payment because she wanted to obtain a home equity line of credit to pay for the work. Saul denied the request. He said plaintiff could not work without getting paid. On September 18, 2012, Mr. Treacy gave Saul a check for $10,000.

In October 2012, Saul ordered replacement cabinets, at Mrs. Treacy's request, and plaintiff paid $2,283.44 for the new cabinets. Defendants did not pay plaintiff for the replacement cabinets. Saul stated that, in addition to the unpaid installments, plaintiff was seeking payment for the time lost while Mrs. Treacy was away, the building permits, and a window upgrade. Plaintiff's total claim was $42,166.44.

A-2418-18T2

On cross-examination, Saul acknowledged that during the summer of 2012, plaintiff removed the chimney and installed a pipe through the wall to vent the furnace and water heater. He also acknowledged that on October 18, 2012, a municipal official came to the property and issued a notice of violation, which stated that the chimney had been removed without a permit, a fire permit was required for venting the furnace, and the furnace and water heater were not vented properly. The notice also stated that the vent connector was too close to "combustibles."

Mrs. Treacy testified for defendants. She denied that defendants needed a home equity line of credit to pay plaintiff. She stated that after the municipal official issued the notice of violations in October 2012, she did not want plaintiff back at her home for safety reasons. She claimed that as a result of the improper venting of the furnace and water heater, defendants and their children were exposed to dangerous health conditions.

Mrs. Treacy asserted that plaintiff did not complete the work in a timely manner. She stated that plaintiff ordered the wrong-sized door, and defendants were forced to pay to correct deficiencies in the ventilation of the furnace and water heater. She said the plans did not require plaintiff to remove the existing chimney, and plaintiff failed to obtain the necessary permits for the work. Mrs.

A-2418-18T2

Treacy claimed the improper venting of the furnace and water heater made the home uninhabitable. She asserted that plaintiff never obtained written change orders and did not complete the plumbing work. She denied that her absence interfered with the work.

Free access — add to your briefcase to read the full text and ask questions with AI

WOODSTONE GROUP, LLC VS. PAUL TREACY (L-0639-17, MORRIS COUNTY AND STATEWIDE), (N.J. Ct. App. 2020).

WOODSTONE GROUP, LLC VS. PAUL TREACY (L-0639-17, MORRIS COUNTY AND STATEWIDE) (WOODSTONE GROUP, LLC VS. PAUL TREACY (L-0639-17, MORRIS COUNTY AND STATEWIDE)) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

R. KREVOLIN & CO., INC. v. Brown
89 A.2d 255 (New Jersey Superior Court App Division, 1952)
Bosland v. Warnock Dodge, Inc.
964 A.2d 741 (Supreme Court of New Jersey, 2009)
Power-Matics, Inc. v. Ligotti
191 A.2d 483 (New Jersey Superior Court App Division, 1963)
Cesare v. Cesare
713 A.2d 390 (Supreme Court of New Jersey, 1998)
El-Sioufi v. ST. PETER'S UNIV.
887 A.2d 1170 (New Jersey Superior Court App Division, 2005)
Matter of Trust Created by Agreement Dated December 20, 1961
944 A.2d 588 (Supreme Court of New Jersey, 2008)
Cox v. Sears Roebuck & Co.
647 A.2d 454 (Supreme Court of New Jersey, 1994)
Manalapan Realty v. Township Committee of the Township of Manalapan
658 A.2d 1230 (Supreme Court of New Jersey, 1995)
Jardine Estates, Inc. v. Donna Brook Corp.
126 A.2d 372 (New Jersey Superior Court App Division, 1956)
Allen v. v. AND a BROS., INC.
26 A.3d 430 (Supreme Court of New Jersey, 2011)
Seidman v. Clifton Savings Bank
14 A.3d 36 (Supreme Court of New Jersey, 2011)
Tahir Zaman v. Barbara Felton (072128)
98 A.3d 503 (Supreme Court of New Jersey, 2014)
Reese v. Kline Building & Construction Co.
149 A. 826 (Supreme Court of New Jersey, 1930)
Perez v. Professionally Green, LLC
73 A.3d 452 (Supreme Court of New Jersey, 2013)