Woodstock Community Trust & Housing Vermont PRD

CourtVermont Superior Court
DecidedNovember 15, 2008
Docket126-06-07 Vtec
StatusPublished

This text of Woodstock Community Trust & Housing Vermont PRD (Woodstock Community Trust & Housing Vermont PRD) is published on Counsel Stack Legal Research, covering Vermont Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Woodstock Community Trust & Housing Vermont PRD, (Vt. Ct. App. 2008).

Opinion

STATE OF VERMONT

ENVIRONMENTAL COURT

} In re: Woodstock Community Trust } and Housing Vermont PRD1 } Docket Nos. 126-6-07 Vtec (final) and (Appeals of Roy, et al.) } 263-11-06 Vtec (preliminary) }

Decision and Order

In Docket No. 263-11-06 Vtec, Appellants David Roy, Richard Roy, Michael

Hirschbuhl, Tod Minotti, and Mark Stanglin (Appellants) appealed from a decision of

the Development Review Board (DRB) of the Town of Woodstock issued on November

3, 2006. The decision first granted reconsideration of the DRB’s April 7, 2006 denial of

an application submitted by Appellee-Applicants Woodstock Community Trust, Inc.,

and Housing Vermont for preliminary approval of a Planned Development located at

473 Woodstock Road, and then granted preliminary approval of that application. In

Docket No. 126-6-07 Vtec, the same Appellants appealed from a decision of the DRB

issued on June 4, 2007, granting final approval of the application. Appellants are

represented by Kaveh S. Shahi, Esq.; Appellee-Applicants are represented by Daniel C.

Hershenson, Esq.; and the Town of Woodstock is represented by Todd C. Steadman,

Esq.

Two earlier appeals regarding this property have been concluded. The initial

appeal was filed by Applicants from the DRB’s initial denial of the application and

1 Although originally proposed as a Planned Unit Development (PUD) with a community center in the former Grange building, the project as presented at trial is a Planned Residential Development (PRD) proposing only residential units, including three in the renovated former Grange building.

1 received Docket No. 99-5-06 Vtec; it was withdrawn when the DRB took up the

reconsideration of its decision. The next appeal, brought by Appellants, was Docket

No. 152-6-06 Vtec, which was remanded at the request of the DRB pursuant to

V.R.E.C.P. 5(i).

Appellants objected to their having to identify the issues on appeal, despite the

requirement in 10 V.S.A. § 8504(h) and V.R.E.C.P. 5(f) that the scope of the appeal is

defined by the Appellants’ Statement of Questions, and despite this Court’s ruling on

pretrial motions on October 3, 2007, that Appellee-Applicants would nevertheless have

the burden of proof that the application met the requirements of the zoning ordinance.

All questions in the Statement of Questions in Docket No. 263-11-06 Vtec except for

Questions 92 and 10 were resolved by motion decisions dated October 3, 2007, May 10,

2007, and December 5, 2006. Questions 9 and 10 present the merits of the application

for preliminary approval of the proposed project; these questions were consolidated

with the merits of Docket No. 126-6-07 Vtec regarding final approval of the proposed

project.

The restated Statement of Questions filed by Appellants in Docket No. 126-6-07

Vtec contained three questions, numbered as I, II, and III, of which Question I

addressed the merits of whether the application met the requirements of §§ 709, 710,

and 313 of the Zoning Regulations. Question I contained 19 subsections, some of which

contained further subsections. Questions II and III were resolved in the Court’s October

2 Question 9 asked whether the DRB was correct to grant reconsideration and preliminary approval of the project, while Question 10 addressed whether this court in this de novo proceeding should grant preliminary approval. To the extent that Question 9 raised the same issues as Questions 4 and 8 regarding the propriety of reconsideration (as opposed to the merits), it was also resolved in the pretrial motion decisions.

2 3, 2007 motion decision, which also attached a redacted version of the Statement of

Questions in Docket No. 126-6-07 Vtec memorializing those subsections of Question I

agreed by the parties to remain in the appeal.3 In a pretrial conference held on October

12, 2007, the redacted version of the Statement of Questions was confirmed. All

references to the remaining question numbers in this decision are to the various

subsections of Question I that remained in the appeal as of that pretrial conference.

An evidentiary hearing was held in this matter over the course of six days, before

Merideth Wright, Environmental Judge. A site visit was taken before the hearing, with

the parties and their representatives. The parties were given the opportunity to submit

written memoranda and requests for findings. Upon consideration of the evidence as

illustrated by the site visit, and of the written memoranda and requests for findings

filed by the parties, the Court finds and concludes as follows.

Appellee-Applicants are two non-profit corporations, one local to Woodstock

and one operating statewide, which propose an affordable housing development,

having access from U.S. Route 4 in the village of West Woodstock, in a Residential

Medium Density zoning district. Route 4 runs from the northeast to the southwest in

this location. The project property is served by a municipal sewer system and by a

municipal or community water system operated by the Woodstock Aqueduct

Company. The entrance to the Woodstock middle school and high school complex is

3 Question 13(b) refers to an introductory phrase in § 313(C)(3)(b) which requires the applicant to submit a plan ‚clearly showing the following: . . .‛ Each of the required elements of the plan is listed in a separate subsection, from (c) through (j). Each of these except subsection (f) was the subject of a separate subsection of Question 13; this decision therefore will not refer further to Question 13(b).

3 located about 550 feet farther to the southwest along Route 4 to the southwest, on the

opposite side of Route 4.

The project is proposed for an 8.02-acre parcel of land consisting of two tax

parcels: a half-acre parcel containing a former Grange building, with 70 feet of frontage

on the northwest side of Route 4, and a 7½-acre vacant parcel of land, with 22.88 feet of

frontage at the Route 4 end of the deeded access. These parcels are owned by Appellee-

Applicant Woodstock Community Trust, Inc. As well as owning the two lots

comprising the project property on the northwesterly side of Route 4, Appellee-

Applicants have entered into a contract to purchase a one-acre parcel of land on the

southeast side of Route 4, referred to as the Fox parcel, to be used in the proposed

stormwater discharge system for the project.

The vacant parcel consists of a relatively flat field that has been used as a

community playing field with associated parking; the parcel slopes beyond the field

steeply upward towards the west and northwest. Much of the steeply sloping hillside is

also wooded. Part of the way up the hill near the southwesterly side of the property is a

wet area below an old wellhouse. Another frequently wet area is located near the

middle of the northeasterly side of the property. No wetlands appear on relevant maps

or have been delineated on the 8-acre project property.

Absent any alteration of the natural drainage due to the project, the natural

drainage over the property is generally from its far western corner towards its eastern

corner, and thence towards the Ottauquechee River. An existing culvert also drains

across Route 4 onto or near the Fox parcel, from just to the southwest of the former

Grange building.

Other than the former Grange parcel, the project property proposed for the

housing units is located behind those of Appellants' properties which have access

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Armitage
2006 VT 113 (Supreme Court of Vermont, 2006)
In Re Application of Carrier
582 A.2d 110 (Supreme Court of Vermont, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
Woodstock Community Trust & Housing Vermont PRD, Counsel Stack Legal Research, https://law.counselstack.com/opinion/woodstock-community-trust-housing-vermont-prd-vtsuperct-2008.