Woodruff Construction, LLC v. Steven P. Christensen, Individually and D/B/A Christensen Construction Company

CourtCourt of Appeals of Iowa
DecidedMay 1, 2019
Docket18-0371
StatusPublished

This text of Woodruff Construction, LLC v. Steven P. Christensen, Individually and D/B/A Christensen Construction Company (Woodruff Construction, LLC v. Steven P. Christensen, Individually and D/B/A Christensen Construction Company) is published on Counsel Stack Legal Research, covering Court of Appeals of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Woodruff Construction, LLC v. Steven P. Christensen, Individually and D/B/A Christensen Construction Company, (iowactapp 2019).

Opinion

IN THE COURT OF APPEALS OF IOWA

No. 18-0371 Filed May 1, 2019

WOODRUFF CONSTRUCTION, LLC, Plaintiff-Appellant,

vs.

STEVEN P. CHRISTENSEN, Individually and D/B/A CHRISTENSEN CONSTRUCTION COMPANY, Defendant-Appellee. ________________________________________________________________

Appeal from the Iowa District Court for Dickinson County, David A. Lester,

Judge.

Woodruff Construction, LLC appeals the judgment entered following trial on

the parties’ breach-of-contract claims. AFFIRMED.

Ernest Kersten, Fort Dodge, and Jerry L. Schnurr III of Schnurr Law Firm,

P.C., Fort Dodge, for appellant.

Richard Meyer of Fillenwarth & Fillenwarth, Estherville, for appellee.

Considered by Vaitheswaran, P.J., and Doyle and Mullins, JJ. 2

DOYLE, Judge.

Woodruff Construction, LLC (Woodruff) appeals the district court order

entering judgment in favor of Steven P. Christensen and Christensen Construction

Company (Christensen) on its breach-of-contract counterclaim. Woodruff

challenges the district court’s finding that Woodruff breached its contract with

Christensen. Woodruff also challenges the court’s damage award.

Polaris Industries contracted with Christensen to construct an addition onto

its manufacturing plant in Spirit Lake. Christensen subcontracted with Woodruff to

complete a portion of the work. The parties signed a written agreement that states

Woodruff was to complete a counterfort wall1 by no later than December 2, 2013,

and a retaining wall by no later than December 19. Woodruff did not complete

work on the counterfort wall until January 20, and it never completed the retaining

wall.

In August 2015, Woodruff filed a petition claiming Christensen breached the

contract by failing to pay for the completed work. In May 2016, Christensen filed

an amended answer and counterclaim alleging Woodruff was negligent and that it

breached the contract in failing to complete construction properly and timely

pursuant to the plans and specifications. A two-day bench trial was held in January

and February 2017. The matter was deemed submitted for final ruling after briefing

was completed in March 2017. In January 2018, the district court entered a written

ruling finding that both parties had breached the contract. The court determined

1 A counterfort wall is a retaining wall with counterforts or buttresses on the back or thrust- receiving side. See Webster’s Third New International Dictionary 519 (unbar. ed. 2002). 3

the amount of Woodruff’s damages to be $84,132.86 and the amount of

Christensen’s damages to be $78,813.

On appeal, Woodruff contends there is insufficient evidence to support a

finding that it breached its contract with Christensen. To succeed on a claim of

breach of contract, a party must show:

(1) the existence of a contract; (2) the terms and conditions of the contract; (3) that it has performed all the terms and conditions required under the contract; (4) the defendant’s breach of the contract in some particular way; and (5) that plaintiff has suffered damages as a result of the breach.

Iowa Arboretum, Inc. v. Iowa 4-H Found., 886 N.W.2d 695, 706 (Iowa 2016)

(citation omitted). Because this action was tried at law, our review is for correction

of errors at law. See Iowa R. App. P. 6.907. We are bound by the district court’s

fact findings if supported by substantial evidence. See Iowa R. App. P. 6.904(3)(a).

The district court found each party had proved the first four elements of a

breach-of-contract claim. With regard to Woodruff’s claim, the court found that

Woodruff completed construction of the counterfort wall, “albeit late and not

according to the specifications set forth in the contract.” It noted that Christensen

and Polaris had accepted Woodruff’s work because the addition was completed,

and therefore, it concluded that Christensen’s refusal to pay for the completed work

constituted a breach of the contract. With regard to Christensen’s counterclaim,

the court found that Woodruff “did not come close to meeting” the deadline for

completing the counterfort wall specified in the contract and never constructed the

retaining wall. It further observed that

Woodruff did not comply with the specifications set forth in the contract including the type of forms used, the length of each section of wall that was poured, the providing of a rebar free area and a void 4

in the forms, and putting trash and debris from their work into a dumpster at the site. All of the foregoing, the court concludes, constitutes breaches by Woodruff of the terms of the parties’ written contract.

The bulk of Woodruff’s claims concern its defense that it could not perform

under the deadlines of the contract based on circumstances beyond its control—

namely, the bitterly cold winter weather and Christensen’s conduct.2 In a lengthy

ruling, the district court provided a detailed summary of the evidence presented at

trial and concluded that neither the weather nor Christensen’s performance

excused Woodruff from meeting the contract deadline. Specifically, the court

found that Christensen’s performance “only temporarily delayed Woodruff’s

performance, at most, and does not serve as a basis for excusing Woodruff’s

wholesale failure to meet the deadlines set forth in the contract or to excuse its

failure to perform the work it did in the manner specified in the contract.” It further

2 Woodruff refers to “the principle of force majeure.” “Force majeure” refers to “an event that can be neither anticipated nor controlled.” Pillsbury Co., Inc. v. Wells Dairy, Inc., 752 N.W.2d 430, 440 (Iowa 2008) (quoting Black’s Law Dictionary 657 (7th ed. 1999)). The Iowa cases on this proposition relate to contracts that contain a “force-majeure clause”— a clause that “allocate[es] the risk if performance becomes impossible or impracticable as a result of an event or effect that the parties could not have anticipated or controlled.” Id. (citation omitted). As our supreme court has noted, “A force-majeure clause is not intended to shield a party from the normal risks associated with an agreement.” Id. Even if a contract provides no such clause, “the court may still relieve the party of that duty ‘if performance has unexpectedly become impracticable as a result of a supervening event.’” Am. Soil Processing, Inc. v. Iowa Comprehensive Petroleum Underground Storage Tank Fund Bd., 586 N.W.2d 325, 330 (Iowa 1998) (citation omitted). Referred to as “the doctrine of discharge by supervening impracticability,” it applies when an event that the parties assumed would not occur at the time of contracting arises and makes performance impracticable through no fault of the nonperforming party. DuTrac Cmty. Credit Union v. Radiology Grp. Real Estate, L.C., 891 N.W.2d 210, 217 (Iowa 2017). In its answer to Christensen’s counterclaim, Woodruff alleged its timely performance was impossible due to Christensen’s conduct and the bitterly cold winter weather. Therefore, we analyze Woodruff’s claim under the doctrine of impossibility of performance.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Woodruff Construction, LLC v. Steven P. Christensen, Individually and D/B/A Christensen Construction Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/woodruff-construction-llc-v-steven-p-christensen-individually-and-dba-iowactapp-2019.