Woodmont, Inc. v. Daniels

274 F.2d 132
CourtCourt of Appeals for the Tenth Circuit
DecidedDecember 23, 1959
DocketNos. 6041, 6042
StatusPublished
Cited by22 cases

This text of 274 F.2d 132 (Woodmont, Inc. v. Daniels) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Woodmont, Inc. v. Daniels, 274 F.2d 132 (10th Cir. 1959).

Opinion

MURRAH, Chief Judge.

This is an appeal and cross appeal from a judgment in a diversity action for damages based upon actionable misrepresentations in the execution of a contract. Federal jurisdiction is concededly present. By the terms of the contract of June 20, 1955, as amended, the plaintiffappellee, Daniels Construction Company, agreed with appellant, Woodmont, Inc., to excavate approximately 2,500,000 cubic yards of overburden for the strip mining of a uranium ore mine in Utah for 290 per cubic yard. Appellant, Continental Materials Corporation, the parent company of Woodmont, guaranteed Woodmont’s performance of the contract. The contract pertinently provided that the contractor “is not relying upon any representations or promises of the Company except those contained in this agreement” ; and that “There are no previous or contemporary representations or warranties of the Company or the contractor not set forth herein.” The contract also pertinently provided for heavy penalties for failure to complete the contract on the specified date.

The first part of the work progressed as expected, but about the first of December, the contractor encountered unanticipated rock or sandstone, and thereupon indicated that it would expect additional compensation, but made no formal demands in that respect. About the middle of February, it was definitely determined that the last sixty to ninety feet of material was hard sandstone rock which could be removed only by systematic drilling and blasting. About this time, apparently both parties became concerned with the possibility that the contractor would not be able to complete the contract on time. The contractor was concerned with the heavy penalties involved, and the Company was apparently concerned lest ore would not be available for its projected mill.

In any event, after negotiations, the parties amended their original contract to provide that the contractor would concentrate on the excavation of one-half of the pit area to insure the availability of ore on the completion date; and that the contractor would be allowed one day additional time for each day he complet[135]*135ed that part of the pit area ahead of the date fixed for the completion of the contract. The contractor also agreed to drill, blast and remove additional sandstone adjacent to but outside the original pit area not contemplated by the original contract; and the Company agreed that in addition to the 29 é provided for in the contract, it would pay $1.03 per foot of hole drilled; and it was further agreed that “no additional amount shall be payable for any blasting other than that provided for in this paragraph.”

The amendment, drafted by the Company’s legal department, was signed by its field manager Pruess on March 17, 1956, and was signed by partner Daniels for the appellees on March 20. On that date, Daniels mailed to the Company a letter previously prepared by his legal counsel in which it was stated that “our contract price was of course fixed upon the assumption that the data which you furnished us regarding the formation here was correct. We of course realize that you were under the impression that your data was also correct and we do not mean to intimate any question of bad faith on your part.” And, further, that “The presence of this bedrock has, as you know, materially increased the cost of our operation, and although we are going ahead with the removal of the overburden pursuant to your orders, we wish it clearly understood that we are doing this with the reservation of our rights to call on you for additional compensation in a reasonable amount to compensate us for this increased cost.” The letter went on to state that appellees had been advised that in cases of this kind where it had been a “mutual mistake of fact,” they were within their legal rights in insisting upon additional compensation “in excess of the unit price specified in our contract.”

On the following April 11, the legal department for Continental replied, expressing surprise at the letter in view of the provisions of the March 17 amendment, to which they consented “in order to settle the very claims which you are now reopening in your letter of March 20, 1956;” that “we find ourselves in the position of having once settled what we considered a groundless claim and now having the claim asserted once again * * -»»

The claims with respect to additional compensation for excavation were not pressed further and the contractor continued to remove the overburden in accordance with the amendment and to accept payment by monthly check with an attached voucher reciting that it was “in full settlement of accounts below. If not correct return without alterations and state differences.”

In October 1956, the original contract was again amended to provide for additional stripping caused by a landslide, at 50¡é per cubic yard instead of 29¿\ When the contract was completed, the final check in payment of the contract price was accompanied by a letter, calling attention to a paragraph in the contract providing that acceptance of the final payment by the contractor would constitute a release and waiver of all claims by the contractor against the Company. The contractor returned the check and later accepted it only when the Company had agreed that the acceptance would not effect a release or waiver. This suit was brought to recover the loss of bargain caused by the additional cost of excavating the hard rock which the contractor did not anticipate when the contract was executed.

The claim was stated on several different theories, but the trial court’s judgment is based upon actionable misrepresentations of responsible agents of the appellant companies to the contractor to the effect that with the exception of the designated boulder area, the overburden to be excavated was capable of being moved by the use of heavy dirt-moving equipment without drilling or blasting. The claim stated, and the trial court found, that in reliance upon these representations, the contractor bid 29if, per cubic yard for the excavation work, that after removing approximately two-thirds of the material, and in the early part of 1956, it encountered sandstone [136]*136or hard rock necessitating drilling and blasting; that at that time it became aware of the inaccuracy of the misrepresentations, but did not know that they had been deceitfully made; that proceeding on the theory of mutual mistake, it pursued their contract at great cost after having asserted its intention to claim extra compensation for the removal of the hard rock; and that it did not know the representations were knowingly false until revealed by discovery proceedings after the institution of this suit.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nelson v. United States
256 F. Supp. 3d 1136 (D. Colorado, 2017)
Helf v. Chevron U.S.A. Inc.
2015 UT 81 (Utah Supreme Court, 2015)
Dynegy, Inc. v. Yates
345 S.W.3d 516 (Court of Appeals of Texas, 2011)
United States v. Philip Morris USA Inc.
566 F.3d 1095 (D.C. Circuit, 2009)
Gutter v. E.I. Dupont De Nemours
124 F. Supp. 2d 1291 (S.D. Florida, 2000)
Lihosit v. I & W, INC.
913 P.2d 262 (New Mexico Court of Appeals, 1996)
FIEDLER v. McKEA CORPORATION
605 F.2d 542 (Tenth Circuit, 1979)
Fiedler v. McKea Corp.
605 F.2d 542 (Tenth Circuit, 1979)
United Securities Corporation v. Franklin
180 A.2d 505 (District of Columbia Court of Appeals, 1962)
Woodmont, Inc. v. S. Daniels
290 F.2d 186 (Tenth Circuit, 1961)
Woodmont, Inc. v. Daniels
290 F.2d 186 (Tenth Circuit, 1961)

Cite This Page — Counsel Stack

Bluebook (online)
274 F.2d 132, Counsel Stack Legal Research, https://law.counselstack.com/opinion/woodmont-inc-v-daniels-ca10-1959.