Woodland Manor III Associates v. Durfee, 89-2447 (1994)

CourtSuperior Court of Rhode Island
DecidedFebruary 10, 1994
DocketC.A. 89-2447
StatusUnpublished

This text of Woodland Manor III Associates v. Durfee, 89-2447 (1994) (Woodland Manor III Associates v. Durfee, 89-2447 (1994)) is published on Counsel Stack Legal Research, covering Superior Court of Rhode Island primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Woodland Manor III Associates v. Durfee, 89-2447 (1994), (R.I. Ct. App. 1994).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]

DECISION
This matter is before the Court on plaintiff's amended complaint seeking declaratory relief pursuant to R.I.G.L. 1956 §9-30-1 (1985 Reenactment) and R.C.P. 57 and injunctive relief pursuant to R.C.P. 65. Plaintiff in this action is one of several interrelated business entities involved in a long term land development project in Coventry, Rhode Island. Following a two-day evidentiary hearing and a review of the entire record this Court finds the pertinent facts to be as follows.

I. BACKGROUND

The facts pertinent to this action span approximately twenty years. In the early 1970s Mapleroot Development Corporation (hereinafter "MDC") a Rhode Island Corporation, purchased an eighty-nine acre parcel of land in the Town of Coventry for development purposes. The envisioned project was a "Planned Unit Development" and was to include buildings of various uses to be combined as an integrated, cohesive whole. Although conceived ultimately to work together as a whole or "unit," the buildings were to be constructed not concurrently but in phases.

For financial and tax purposes many business entities were used in implementing each phase of the project. However, these various entities comprised the same individual persons and operated as coadunate components of the larger business enterprise. Woodland Manor III Associates, the plaintiff in this action, is a Rhode Island limited partnership to which MDC transferred land in completing the final phase of the long term multi-phase project.

Following the original purchase of the land, MDC needed to determine the amount and location of the buildable land as situated upon the eight-nine acre tract. In pursuit of this interest MDC sought to determine the jurisdiction of the Department of Natural Resources (now called the Department of Environmental Management; hereinafter simply "the Department") over the subject parcel. Such jurisdiction derived from the Freshwater Wetlands Act. Pursuant to this statutory scheme as codified in G.L. 1956 § 2-8-8 et seq., in June, 1974, a representative of the MDC filed a "Request for Freshwater Wetlands Applicability Determination" (hereinafter "Request").

At the evidentiary hearing Messrs. Giordano, a general partner in Woodland Manor III Associates, and Peter Janaros, the Supervisor of the Department's Wetlands Division, testified about the Wetlands regulatory process. As part of the preliminary determination the Department first conducts an on-site inspection of the land and "flags" or delineates the wetlands in accordance with applicable regulations. Robert Rocchio, a land surveyor for the developer, testified that Michael Pickering, a Department wetland biologist, went to the site and established the 247.5 contour as the limit of disturbance. The Department then determines whether the proposed development would impact the delineated wetlands such that a "Formal Application" is necessary.

Attached to the Request filed in accordance with this procedure was a site plan prepared by C.E. Maguire, the engineering firm engaged by the developer. In response to this Request the Department sent the developer a letter dated June 17, 1974 which stated in part that:

Provided there is no construction or regrading below the 247.5 foot contour as shown on the above-referenced plan and that final grading and drainage plans and computations are submitted for review and approval of the Department prior to start of construction, it is our conclusion that the Fresh Water Wetlands Act does not, at this time, appear applicable to this proposal.

This language is central to the instant controversy.

Following this statement by the Department, the developer continued the process of presenting the project to the myriad state regulatory agencies whose permissions would eventually be needed in order for the project to reach completion as planned. This process had begun with the creation of a "bubble plan" which illustrated the general features of the entire project. This plan embodied the concept but not the details of the project and was used to assess the feasibility of the proposal. Following discussion, modification, and analysis of the "bubble plan" the developer created a "Master Plan." This plan contained a more detailed site plan of the "bubble plan" and served to provide a basis for coordination among the developer and all the state and local regularity agencies concerned.

One such area of concern was that of the sewage system. At the evidentiary hearing, Antone Giordano, on behalf of the developer, testified regarding the role of the then "Master Plan" in designing a sewage system to serve the project. Mr. Giordano stated that the magnitude of the project together with the localized high water table demanded the installation of a sewage system through the Town of Coventry to the project site. The "Master Plan" defined the scope and nature of the entire project so that the sewage needs could be computed and an appropriate design could be made. Indeed, a 3.5 mile sewer system was eventually sized, designed and installed at substantial expense for the multi-phase project.

In 1978 the developer was ready to begin construction of the first phase of the project, a nursing home entitled Woodland Manor I, and submitted a final grading and drainage plan to the Department pursuant to the 1974 letter. The Department responded to this submission in a letter dated June 29, 1978 which stated in pertinent part:

Under the following provisions: adequate measures are taken to prevent sediments from entering adjacent wetlands . . . it is our conclusion that the fresh water act does not appear applicable to this proposal. (emphasis added).

Similarly, in 1980, the developer submitted a final drainage and grading plan for another phase of the project, a nursing home owned by Coventry Health Center Associates. The Department responded by stating:

Under the following provisions, . . . adequate measures are taken to prevent sediments from entering adjacent wetlands . . . it is our conclusion that this proposal represents an insignificant alteration of a freshwater wetland. Therefore, under the aforementioned provisions, a permit to alter freshwater wetlands will not be required. (emphasis added).

The event precipitating the instant controversy over the scope and import of the 1974 letter occurred after the completion of all but the final phase of construction. In August, 1986, the Department responded to a submission by the plaintiff Woodland Manor Associates (WMA) seeking the approval of the final grading and drainage plan for the last phase of construction pursuant to the 1974 letter. The 1986 letter contained the following language:

Proposed alteration, including filling, vegetative clearing, grading, building construction, tennis court and drainage installation will result in encroachment, significant loss, disturbance and alteration of the natural characteristics of a freshwater wetland, adversely impacting wildlife habitat value, recreational value, and groundwater recharge and quality. Be advised that the public value of the wetland, its outstanding wildlife habitat value and its location within one of this state's primary groundwater reservoirs, require that the wetland receive the highest level of protection. As proposed, this project has the highest probability of being denied by the department's Freshwater Wetlands Section.

The letter further stated that a formal wetland application would be required by law.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ratcliffe v. Coastal Resources Management Counsel
584 A.2d 1107 (Supreme Court of Rhode Island, 1991)
Goodman v. Turner
512 A.2d 861 (Supreme Court of Rhode Island, 1986)
Greenwich Bay Yacht Basin Associates v. Brown
537 A.2d 988 (Supreme Court of Rhode Island, 1988)
Melanson v. Rantoul
536 F. Supp. 271 (D. Rhode Island, 1982)
Ferrelli v. Department of Employment Security
261 A.2d 906 (Supreme Court of Rhode Island, 1970)
Santos v. City Council of City of East Providence
208 A.2d 387 (Supreme Court of Rhode Island, 1965)
Shalvey v. Zoning Board of Warwick
210 A.2d 589 (Supreme Court of Rhode Island, 1965)
Murphy v. Duffy
124 A. 103 (Supreme Court of Rhode Island, 1924)

Cite This Page — Counsel Stack

Bluebook (online)
Woodland Manor III Associates v. Durfee, 89-2447 (1994), Counsel Stack Legal Research, https://law.counselstack.com/opinion/woodland-manor-iii-associates-v-durfee-89-2447-1994-risuperct-1994.