Woodland Manor, III Assoc. L.P. v. Reisma, 89-2447 (2003)

CourtSuperior Court of Rhode Island
DecidedFebruary 24, 2003
DocketC.A. No. PC89-2447.
StatusPublished

This text of Woodland Manor, III Assoc. L.P. v. Reisma, 89-2447 (2003) (Woodland Manor, III Assoc. L.P. v. Reisma, 89-2447 (2003)) is published on Counsel Stack Legal Research, covering Superior Court of Rhode Island primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Woodland Manor, III Assoc. L.P. v. Reisma, 89-2447 (2003), (R.I. Ct. App. 2003).

Opinion

DECISION
The Court heard this matter without a jury. The plaintiff, Woodland Manor, III Associates, L.P. (Woodland), brought this claim against the defendant, the Director of the Department of Environmental Management (DEM), alleging that the DEM's demand that Woodland submit a new application in connection with its development of Section 8 housing constituted a taking. The plaintiff seeks just compensation for the damages that allegedly flowed from the taking. This Court finds that the defendant's actions constituted a taking and that the defendant is thus required to pay just compensation to the plaintiff.

FACTS AND TRAVEL
The long history of this case is well documented. See Woodland ManorIII Assoc. v. Keeney, 713 A.2d 806 (R.I. 1998); Woodland Manor IIIAssoc. v. McCleod, C.A. No. 89-2477, 2000 R.I. Super. LEXIS 17 (R.I. Super. Ct. filed March 2, 2000); Woodland Manor III Assoc. v. Keeney, C.A. No. 89-2477, 1996 R.I. Super. LEXIS 150 (R.I. Super. Ct. filed Dec. 12, 1996); Woodland Manor III Assoc. v. Keeney, C.A. No. 89-2477, 1994 R.I. Super. LEXIS 23 (R.I. Super. Ct. filed Feb. 10, 1994). To chronicle the relevant facts, this Court revisits the early 1970s, when Mapleroot Development Corporation (Mapleroot) purchased an eighty-nine acre parcel of land in the Town of Coventry for development purposes. The owners of Mapleroot were John Assalone, Sr., Pasquale Confreda, Robert Rocchio, and Dominick DelVecchio.

The design for the land in Coventry was a Planned Unit Development (PUD), which was to include a hodgepodge of buildings that were to be integrated as a cohesive whole. Mapleroot entered into an agreement with Antonio L. Giordano, whereby Giordano would take control of developing the PUD. Even though the project was conceived as a whole, it was to proceed in five distinct phases: a commercial phase, Woodland Manor I, Woodland Manor II, Coventry Health Center, and Woodland Manor III. Woodland Manor I was 150 units of Section 8 housing. Woodland Manor II was 126 units of Section 8 elderly housing. Coventry Health Center was a 300 bed nursing home. The last phase of the PUD, Woodland Manor III, was to be 150 units of multi-family Section 8 housing.

These projects would be financed by loans that were to be guaranteed by the United States Department of Housing and Urban Development (HUD). Since HUD requires each of its projects to be owned by a single purpose entity, Mapleroot and Giordano created entities for each phase of the project that were owned in equal shares. Thus, several "business entities were used in implementing each phase of the project. However, these various entities comprised the same individual persons and operated as coadunate components of the larger business enterprise." Woodland ManorIII Assoc, C.A. No. 89-2477, 1994 R.I. Super. LEXIS 23 at 2.

To proceed with the project, on or about February 4, 1974, Mapleroot filed a Request for Freshwater Wetlands Applicability Determination (RAD) with the Department of Environmental Management1 (DEM). Once the DEM received the RAD, it would then do an on site inspection to delineate any wetlands and thereafter would decide whether the proposed development would impact the wetlands. If the DEM believed that the development would significantly impact any wetlands, it could then require Mapleroot to submit to the burdensome process of a formal wetlands application. With the RAD, Mapleroot submitted a site plan and map. A wetland biologist for the DEM then inspected the site to flag wetlands and delineated the 247.5 contour line as the limit of disturbance. In a June 17, 1974 letter (1974 letter) sent to Mapleroot, the DEM stated:

"provided there is no construction or regarding below the 147.52 foot contour as shown on the above referenced plan and that final grading and drainage plans and computations are submitted for review and approval of this Department prior to start of construction, it is our conclusion that the Fresh Water Wetlands Act does not, at this time, appear applicable to this proposal."

Mapleroot was thus spared the process of submitting a formal wetlands application to the DEM.

Upon receipt of the 1974 letter, Mapleroot presented the proposal to the requisite state and local agencies. Consequently, Mapleroot expended substantial sums of money preparing the site, which included the design and construction of a 3.5 mile sewer system. In 1978, 1980 and 1981, Mapleroot submitted site plans for the first three phases of the project, respectively, to the DEM. The DEM replied to the submissions with essentially similar letters stating that construction would be allowed provided that "1. Only work specifically shown on the aforementioned site plan is allowed; 2. Adequate measures are taken to prevent sediments from entering adjacent wetlands . . ." As a result, Mapleroot was able to complete the first three phases of the project.

At the time that preparations were under way for the construction of Woodland Manor III, legislation for the Tax Reform Act of 1986 (the Act) was pending; it subsequently became law in October 1986. Of consequence to Mapleroot was the Act's retroactive elimination of the ability of developers to syndicate Section 8 housing projects, which is what Woodland Manor III was set to become. In order to be grandfathered under the law as it existed at that time, Mapleroot must have managed the completion of certain tasks related to the project by deadline dates that were set by the Act. First, Mapleroot must have had a binding contract in place with a developer for construction of the project by March 1, 1986. Secondly, Mapleroot must have secured qualified investors for its syndication project by August 16, 1986. If these deadlines were not met, Mapleroot would fail to qualify for the narrow grandfather provision in the Act, and thus its ability to syndicate the project would have been all but lost.

On August 15, 1985, Giordano, on behalf of Woodland Manor Associates, entered into a contract with Mast Construction (Mast) to develop the project. Mast had been the developer for other phases of the PUD. Per the agreement, Mast then began the process of securing HUD approval for the project. Storm clouds, however, formed on the horizon. In November 1985, the DEM informed Mapleroot that it needed to submit a new application for the last phase of the project, Woodland Manor III. Wetlands Section Review Sheet (March 7, 1986) (Plaintiff's Exhibit 58). On February 28, 1986, however, in accordance with their previous submissions to the DEM for the first three phases, Mast submitted to the DEM only a site plan, drainage plans and calculations for Woodland Manor III. The DEM formally rejected Mast's submission by letter of April 11, 1986. The April 1986 letter references the Wetlands Section Review Sheet, id., wherein Brian Tefft of the DEM stated that a new RAD would have to be filed.

To comply with the DEM's demands-but without harboring any delusion as to its chance of success-Woodland Manor Associates submitted a new RAD to the DEM on August 7, 1986. Thereafter, the DEM inspected the site and concluded that the site was part of a large wetland. By letter of August 28, 1986, the DEM stated:

"[i]t is our conclusion that this proposal represents a SIGNIFICANT ALTERATION of a Fresh Water Wetland for the following reasons.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Monongahela Navigation Co. v. United States
148 U.S. 312 (Supreme Court, 1893)
Chicago, Burlington & Quincy Railroad v. Chicago
166 U.S. 226 (Supreme Court, 1897)
Olson v. United States
292 U.S. 246 (Supreme Court, 1934)
United States v. General Motors Corp.
323 U.S. 373 (Supreme Court, 1945)
United States v. Petty Motor Co.
327 U.S. 372 (Supreme Court, 1946)
United States v. Causby
328 U.S. 256 (Supreme Court, 1946)
Kimball Laundry Co. v. United States
338 U.S. 1 (Supreme Court, 1949)
Armstrong v. United States
364 U.S. 40 (Supreme Court, 1960)
Penn Central Transportation Co. v. New York City
438 U.S. 104 (Supreme Court, 1978)
San Diego Gas & Electric Co. v. City of San Diego
450 U.S. 621 (Supreme Court, 1981)
United States v. Riverside Bayview Homes, Inc.
474 U.S. 121 (Supreme Court, 1985)
Nollan v. California Coastal Commission
483 U.S. 825 (Supreme Court, 1987)
Lucas v. South Carolina Coastal Council
505 U.S. 1003 (Supreme Court, 1992)
Eastern Enterprises v. Apfel
524 U.S. 498 (Supreme Court, 1998)
Palazzolo v. Rhode Island
533 U.S. 606 (Supreme Court, 2001)
Tabb Lakes, Ltd. v. United States
10 F.3d 796 (Federal Circuit, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
Woodland Manor, III Assoc. L.P. v. Reisma, 89-2447 (2003), Counsel Stack Legal Research, https://law.counselstack.com/opinion/woodland-manor-iii-assoc-lp-v-reisma-89-2447-2003-risuperct-2003.