Woodger v. AMR Corp.

677 P.2d 512, 106 Idaho 199, 1984 Ida. App. LEXIS 438
CourtIdaho Court of Appeals
DecidedFebruary 29, 1984
Docket14154
StatusPublished
Cited by2 cases

This text of 677 P.2d 512 (Woodger v. AMR Corp.) is published on Counsel Stack Legal Research, covering Idaho Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Woodger v. AMR Corp., 677 P.2d 512, 106 Idaho 199, 1984 Ida. App. LEXIS 438 (Idaho Ct. App. 1984).

Opinion

WALTERS, Chief Judge.

AMR Corporation appeals from a judgment of the district court awarding Edward and Jana Woodger and Woodger Development, Inc., (herein Woodger) almost $13,-000, pursuant to a liquidated damages provision of their real estate sale contract. Woodger cross-appeals, challenging the district court’s denial of rescission of his purchase of a subdivision lot from AMR Corporation. We affirm.

I. Facts

The following facts in this case are not in dispute. In June 1978, Woodger and Bruce Lind, president of AMR, negotiated a contract for the sale of lots located in Panorama Hills Subdivision and owned by AMR. This contract covered two lots which were owned entirely by AMR and a third lot which AMR owned in part, for a total sale price of $30,000. Woodger also entered into a contract to purchase the remainder of this third lot from its owner, Brent Peterson, for $10,000. Woodger made down payments on both contracts. He executed a note in the amount of $22,000 to pay the balance of the purchase from AMR. To arrange construction financing, Woodger replaced that note with three other notes. Two of the notes later were paid off. Woodger also executed another note in the amount of $8000 to Peterson. That note was to be paid no later than December 9, 1978.

At the time Woodger purchased these lots, neither water nor power had been provided to any of them. Lind testified that AMR and Peterson were responsible for providing water and power to their respective lots. Prior to the sale Lind was aware that the district health department had indicated that it would not issue new sewage permits for new construction in Panorama Hills until problems in the subdivision’s water system were corrected. Lind testified that he fully informed Woodger, during the contract negotiations, of problems concerning the water system existing in Panorama Hills. He further testified that AMR promised to provide water to Woodger’s lot lines within a reasonable amount of time. Woodger testified that Lind had never advised him that the state had approved the water system, but that Lind had told him that “it wouldn’t be too long” before water would be supplied. The contracts which Woodger entered into *201 with AMR and Peterson provided that each agreement was “subject to [Woodger] obtaining a building permit, water and power to be furnished to lot lines.”

When Woodger applied for sewer permits for all three lots, the district health department denied his application. Following negotiations between Lind, Woodger and a district health department official, the department issued sewer permits for two lots. Woodger applied for and received building permits for those two lots. However, both building permits provided that occupancy of the completed houses would not be permitted until the water system for Panorama Hills had been approved.

Woodger began construction in August 1978 on the first two lots. In December 1978, the note payable to Peterson on the third lot became due. Because water had not been supplied to the lot, and the sale was subject to Peterson supplying water to the lot, Woodger told Peterson and Lind that he would not pay the balance of the note. To induce Woodger to pay the note, Lind agreed that AMR would take responsibility for supplying water “to the lot lines of those properties purchased by Ted Woodger at Panorama Hills by no later than March 1, 1979.” Lind further agreed that AMR would “pay a penalty of $45.00 per day each and every day thereafter that said water has not been delivered to the lot lines.” This written agreement was executed December 15, 1978, the same date that Woodger paid the note to Peterson in full.

AMR did not deliver water to the lot lines by March 1, 1979. Woodger later sued to collect the liquidated damages provided by the December 15, 1978 agreement for the period from March 1, 1979 through April 1, 1980, in the amount of $17,820, and to collect sums accruing after that date. He requested rescission of the sale and return of payments made on the third lot, Lot 3, Block 8, on which he had not begun building. He also asked for attorney fees.

AMR had taken a note in payment of Lot 3, Block 8. It counterclaimed for the balance due on the note, $11,000, interest on that balance, and for attorney fees. It also asked that the court declare the liquidated damages agreement void and unenforceable.

Following trial to the court without a jury, the court found that the liquidated damages agreement was valid and did not impose an unconscionable penalty. The court found that water lines were installed to the lot lines by September 14, 1979 and that, after installing a temporary water storage tank which was made functional in November 1979, AMR “had substantially complied with the requirement to furnish water” as of November 1979. The court further awarded liquidated damages to Woodger for the period from March 1, 1979 to November 15, 1979. The court also found that Woodger’s purchase of property was not by virtue of a divisible contract, so he could not rescind the portion of the contract relating to Lot 3, Block 8. It awarded AMR the balance due on AMR’s note. The court declined to award costs and attorney fees to either party. This appeal and cross-appeal followed.

II. Liquidated Damages Provision

AMR argues that the trial court erred in finding the liquidated damages agreement was valid. AMR attacks this finding by contending that Woodger presented insufficient evidence to show a reasonable relationship between the amount stipulated as damages in the agreement and the actual damages he suffered.

However, we do not understand the burden of proof concerning the reasonableness of a liquidated damages provision to be the same as AMR contends. It was not incumbent upon Woodger to show the reasonableness of the relationship between the stipulated damages and his actual damages. Rather, the burden was upon AMR to show the unreasonableness of that relationship. Provisions in a contract for liquidated damages in the event of a default are prima facie valid. In re Grodnik’s, Inc., 128 F.Supp. 941 (D.Minn.1955). The burden of proving facts to show that damages *202 provided for by such a contract do not bear a reasonable relation to the actual damages suffered or that they are exorbitant and unreasonable rests upon the party seeking to invalidate the liquidated damages provision. See Howard v. Bar Bell Land & Cattle Co., 81 Idaho 189, 340 P.2d 103 (1959). Accord Ellis v. Butterfield, 98 Idaho 644, 570 P.2d 1334 (1977); Dolbeer v. Harten, 91 Idaho 141, 417 P.2d 407 (1966); Anderson v. Michel, 88 Idaho 228, 398 P.2d 228 (1965); Nichols v. Knowles, 87 Idaho 550, 394 P.2d 630 (1964). See also W.L. Scott, Inc. v. Madras Aerotech, Inc., 103 Idaho 736, 747, 653 P.2d 791

Free access — add to your briefcase to read the full text and ask questions with AI

Related

M & H RENTALS, INC. v. Sales
700 P.2d 970 (Idaho Court of Appeals, 1985)
Fleming v. Hathaway
686 P.2d 837 (Idaho Court of Appeals, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
677 P.2d 512, 106 Idaho 199, 1984 Ida. App. LEXIS 438, Counsel Stack Legal Research, https://law.counselstack.com/opinion/woodger-v-amr-corp-idahoctapp-1984.