Wohlfeld v. Commissioner

1958 T.C. Memo. 128, 17 T.C.M. 677, 1958 Tax Ct. Memo LEXIS 103
CourtUnited States Tax Court
DecidedJune 30, 1958
DocketDocket No. 59112.
StatusUnpublished
Cited by2 cases

This text of 1958 T.C. Memo. 128 (Wohlfeld v. Commissioner) is published on Counsel Stack Legal Research, covering United States Tax Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wohlfeld v. Commissioner, 1958 T.C. Memo. 128, 17 T.C.M. 677, 1958 Tax Ct. Memo LEXIS 103 (tax 1958).

Opinion

Nathan Wohlfeld and Helen Wohlfeld v. Commissioner.
Wohlfeld v. Commissioner
Docket No. 59112.
United States Tax Court
T.C. Memo 1958-128; 1958 Tax Ct. Memo LEXIS 103; 17 T.C.M. (CCH) 677; T.C.M. (RIA) 58128;
June 30, 1958
Sam G. Winstead, Esq., and Vester T. Hughes, Jr., Esq., for the petitioners. J. C. Linge, Esq., for the respondent.

TRAIN

Memorandum Findings of Fact and Opinion

TRAIN, Judge: Respondent determined a deficiency in petitioners' income tax for the calendar year 1951 in the amount of $38,862.14. The issue to be decided is whether*104 a certain contract was completed in 1952 or 1953 for purposes of determining whether a net operating loss from the contract is applicable to 1951 as a net operating loss carryback.

Findings of Fact

Some of the facts are stipulated and are hereby found as stipulated.

Petitioners, husband and wife, are individuals living in Dallas, Texas. They filed joint income tax returns for the calendar years 1951 and 1952 with the then collector of internal revenue at Dallas, Texas. Nathan Wohlfeld, (hereinafter referred to as petitioner) had been in the construction business for many years as an individual. He used the cash basis of accounting and reported the income from long-term contracts on the completed contract method.

On June 29, 1951, petitioner entered into Contract No. DA-41-243-eng-1048 with the United States Government, which contract called for the construction of eight 225-man barracks at Fort Hood, Texas, for a total contract price of $2,778,453. Other pertinent provisions of the contract are:

"3. Changes and Extras. - The contracting officer may at any time, in writing, and without notice to the sureties, order extras or make changes in the drawings and/or specifications*105 of this contract providing such extras or changes are within the general scope thereof. If any such extra or change causes an increase or decrease in the amount due under this contract, or in the time required for its performance, an equitable adjustment shall be made and the contract shall be modified in writing accordingly. Any claim of the contractor for adjustment under this Clause must be asserted in writing within 30 days from the date of receipt by the contractor of the notification of extra or change: Provided, however, That the contracting officer, if he decides that the facts justify such action, may receive, and act upon any such claim asserted at any time prior to the date of final settlement of the contract. If the parties fail to agree upon the adjustment to be made the dispute shall be determined as provided in Clause 6 hereof. But nothing provided in this clause shall excuse the contractor from proceeding with the prosecution of the work as changed.

"4. Changed Conditions. - Should the contractor encounter, or the Government discover, during the progress of the work subsurface and/or latent physical conditions at the site materially differing from those shown on*106 the drawings or indicated in the specifications, or unknown physical conditions of an unusual nature differing materially from those ordinarily encountered and generally recognized as inhering in work of the character provided for in the drawings and specifications, the contracting officer shall be notified promptly in writing of such conditions before they are disturbed. The contracting officer shall thereupon promptly investigate the conditions, and if he finds that they do so materially differ, the contract shall be modified to provide for any increase or decrease of cost and/or difference in time resulting from such conditions. If the parties fail to agree upon the adjustment to be made, the dispute shall be determined as provided in Clause 6 hereof.

* * *

"7. Payments to Contractors. - (a) Unless otherwise provided in the specifications, progress payments will be made as the work progresses at the end of each calendar month, or as soon thereafter as practicable, or at more frequent intervals as determined by the contracting officer, on estimates approved by the contracting officer. In preparing estimates the material delivered on the site and preparatory work done may be*107 taken into consideration.

"(b) In making such progress payments there shall be retained 10 percent on the estimated amount until final completion and acceptance of all work covered by the contract: Provided, however, That the contracting officer, at any time after 50 percent of the work has been completed, if he finds that satisfactory progress is being made, may make any of the remaining progress payments in full: And provided further, That on completion and acceptance of each separate building, vessel, public work, or other division of the contract, on which the price is stated separately in the contract, payment may be made in full including retained percentages thereon, less auhorized [authorized] deductions.

"(c) All material and work covered by progress payments made shall thereupon become the sole property of the Government, but this provision shall not be construed as relieving the contractor from the sole responsibility for all materials and work upon which payments have been made or the restoration of any damaged work, or as a waiver of the right of the Government to require the fulfillment of all of the terms of the contract.

"(d) Upon completion and acceptance of*108 all work required hereunder, the amount due the contractor under this contract will be paid upon the presentation of a properly executed and duly certified voucher therefor, after the contractor shall have furnished the Government with a release, if required, of all claims against the Government arising under and by virtue of this contract, other than such claims, if any, as may be specifically excepted by the contractor from the operation of the release in stated amounts to be set forth therein. If the contractor's claim to amounts payable under the contract has been assigned under the Assignment of Claims Act of 1940, 54 Stat. 1029 (41 U.S.C. sec. 15), a release may also be required of the assignee at the option of the contracting officer.

"23. Assignment of Claims.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ball, Ball & Brosamer, Inc. v. Commissioner
964 F.2d 890 (Ninth Circuit, 1992)
Ball v. Commissioner Internal Revenue Service
964 F.2d 890 (Ninth Circuit, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
1958 T.C. Memo. 128, 17 T.C.M. 677, 1958 Tax Ct. Memo LEXIS 103, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wohlfeld-v-commissioner-tax-1958.