Wm Dickson Co., V Misenar Construction Inc.

Court of Appeals of Washington·Decided July 2, 2013·No. 42489-4·Unpublished

Opinion

FILE ` COURT OF APP AIS - DIVISIM 11 ,

2013 JUL -2 AM 9-06 STATE OF WASHINGTON BY 4DPU IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON

DIVISION II

WM. DICKSON COMPANY, No. 42489 4 II - -

Respondent,

V.

MISENAR CONSTRUCTION, INC. d/ a b / UNPUBLISHED OPINION MISENAR HOMES,

I. 1

JOHANSON, A. . Misenar Construction J. C — Inc. ( Misenar) appeals the trial court's ruling

that it owed Wm. Dickson Company ( ickson)for unpaid excavation and site development work D

that Dickson performed at Misenar's housing development. We affirm and hold that substantial

evidence supports the challenged findings of fact which in turn support the trial court's

conclusions of law. We also award Dickson reasonable attorney fees on appeal.

FACTS

In October 2005, Misenar contracted with Dickson for development services on

Misenar's new Lakeridge Estates housing development. Their written contract included the

work's basic scope, the price and terms, insurance terms, and written change order requirements

in a standard construction industry format. Dickson's initial bid for the work 05. 411, 31. was $ 5 No. 42489 4 II - -

Throughout the project the parties discussed, verbally and by e mail, several changes to the - contract. These changes required Dickson to perform additional work, at additional cost and

delay. But Dickson believed that Misenar (1)approved all changes prior to Dickson doing the

work, 2)accepted all its work, and ( 3)agreed ( to pay Dickson for the work. Misenar paid

Dickson the original contract amount plus approximately $ 000 in changes but left several 46,

charged amounts unpaid. In May 2007, Dickson's work ended and Misenar made its final

payment to Dickson.

In January 2009, Dickson filed its complaint against Misenar for breach of contract and

quantum meruit unjust enrichment, seeking a judgment for $ / 14 81, 33. plus interest from May 2 2007. In response, Misenar (1)denied that it owed Dickson more money than it had already

paid, ( )raised several affirmative defenses, and (3)sought judgment against Dickson for 2 Dickson's breach of contract.

In May 2009, Misenar moved for summary judgment dismissal of all Dickson's claims.

In response, Dickson argued that factual questions remained making the case improper for

summary judgment. In denying Misenar's summary judgment motion, the trial court's order

provided, in part:

While the Mike M. Johnson caseE has strong language as to whether recovery can be made if the contract language as to change orders is not followed, the facts in that case are significantly different than the facts in the instant manner. [ T] here are factual issues as to whether the parties agreed to deviate from the contract language. There are also credibility determinations which cannot be made on a summary judgment motion.

Clerk's Papers (CP)at 355.

1 Mike M. Johnson, Inc. v. County ofSpokane, 150 Wn. d 375, 78 P. d 161 (2003). 2 3

2 No. 42489 4 II - -

Between May 2009 and May 2010, the trial court permitted Misenar to file three

amended answers. Each amended answer included additional breach of contract counterclaims

against Dickson.

Trial began on September 21, 2010. After Dickson rested its case on September 27,

Misenar moved for a directed verdict on its counterclaims under CR 7( )and CR 8( )because a d

Dickson had not filed a reply to Misenar's counterclaims. Misenar argued that because

Dickson's failure to reply was an admission of breach, the trial court should enter judgment in

Misenar's favor for its counterclaims. The next day, Dickson filed a motion for leave to file a

late reply to Misenar's counterclaims and a response to Misenar's motion for directed verdict.

Dickson also filed its reply to Misenar's counterclaims and asserted several affirmative defenses. Dickson argued that the trial court should (1)treat Misenar's motion for directed verdict as a

motion for default, 2) ( deny it,and (3)thereby accept Dickson's late filing. Dickson argued that

it complied with CR 55( )( 1)a because it had provided ample notice to Misenar of its position on

the counterclaims and had already presented testimony at trial denying the counterclaims.

Misenar moved to strike Dickson's reply.

Two days later, the court heard argument on ( ) 1 Dickson's motion for leave to file a late

reply, 2) s motion to strike Dickson's untimely reply and affirmative defenses, and (3) ( Misenar' Misenar's motion for directed verdict, in that order. First, the trial court granted Dickson leave

to file its late reply, finding that doing so appropriately allowed the case to be decided on the merits.

3 No. 42489 4 II - -

Next, the trial court determined that Dickson's late filing was negligent, but that it was

excusable because the parties' filings and discovery throughout the case indicated both parties'

understanding that Dickson denied the counterclaims. Thus, the trial court denied Misenar's

motion to strike Dickson's entire reply, but it granted Misenar's motion to strike Dickson's

affirmative defenses, finding that allowing Dickson's affirmative defenses so late in the case

would prejudice Misenar.

Third,the trial court treated Misenar's motion for a directed verdict as a CR 12( ) c motion

for judgment on the pleadings. But, the trial court concluded that Dickson met its burden to

prove that the parties had waived the written change order requirement, and denied Misenar's motion.

Trial then continued with Misenar's case. Several months after trial,the trial court issued

its ruling, ordering Misenar to pay Dickson an additional $ 52. 80, 41. Misenar appeals. 3 ANALYSIS

I. SUMMARY JUDGMENT

As a threshold issue, we reject Misenar's argument that the trial court erred when it

denied Misenar's motion for summary judgment because a summary judgment order is not

appealable after trial. A party cannot appeal a denial of summary judgment following a trial if the denial was based upon a determination that material facts were in dispute and must be

2 The court specified that there was "a sufficient factual basis through the testimony of Mr. Hoven and Mr. Asahara to support that there has been a waiver" of the written change order requirement. Verbatim Report of Proceedings (VRP)Sept. 29,2010)at 625. ( 3 The court denied Dickson's claims regarding a steel post for a stop sign and road crossing costs. The $ 52 80, 41. ordered included $ 3 58 28, 63. for Dickson's additional work plus interest 5 and attorney fees.

11 No. 42489 4 II - -

resolved by the trier of fact. Johnson v. Rothstein, 52 Wn. App. 303, 304, 759 P. d 471 (1988). 2

Under RAP 12. ( can raise this issue sua sponte because it " one that affects judicial b), 1 we is

economy and involves interpreting court rules that define our jurisdiction." Rothstein, 52 Wn.

App. at 304 05. Here, the trial court clearly determined that there were disputed facts which -

must be resolved by the trier of fact; thus the summary judgment order cannot be appealed

because it was followed by a trial. Rothstein, 52 Wn. App. at 304.

II. DIRECTED VERDICT

Next, Misenar argues that the trial court erred in denying its motion for a directed verdict

Free access — add to your briefcase to read the full text and ask questions with AI

Wm Dickson Co., V Misenar Construction Inc., (Wash. Ct. App. 2013).

Wm Dickson Co., V Misenar Construction Inc. (Wm Dickson Co., V Misenar Construction Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Johnson v. Rothstein
759 P.2d 471 (Court of Appeals of Washington, 1988)
CKP, Inc. v. GRS Construction Co.
821 P.2d 63 (Court of Appeals of Washington, 1991)
Cresap v. Pacific Inland Navigation Co.
469 P.2d 950 (Court of Appeals of Washington, 1970)
Beers v. Ross
154 P.3d 277 (Court of Appeals of Washington, 2007)
Jansen v. Nu-West, Inc.
6 P.3d 98 (Court of Appeals of Washington, 2000)
Lakes v. von der Mehden
70 P.3d 154 (Court of Appeals of Washington, 2003)
U.S. Bank National Ass'n v. Whitney
81 P.3d 135 (Court of Appeals of Washington, 2003)
Korst v. McMahon
136 Wash. App. 202 (Court of Appeals of Washington, 2006)
Paopao v. Department of Social & Health Services
145 Wash. App. 40 (Court of Appeals of Washington, 2008)
Atlas Supply, Inc. v. Realm, Inc.
287 P.3d 606 (Court of Appeals of Washington, 2012)