Wm. Collins, Inc. v. South Dakota State Board of Transportation

264 N.W.2d 491, 1978 S.D. LEXIS 158
CourtSouth Dakota Supreme Court
DecidedMarch 29, 1978
Docket12266
StatusPublished
Cited by8 cases

This text of 264 N.W.2d 491 (Wm. Collins, Inc. v. South Dakota State Board of Transportation) is published on Counsel Stack Legal Research, covering South Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wm. Collins, Inc. v. South Dakota State Board of Transportation, 264 N.W.2d 491, 1978 S.D. LEXIS 158 (S.D. 1978).

Opinion

PORTER, Justice.

CASE SUMMARY

This is an appeal from the judgment of the circuit court granting the plaintiff’s (Collins) motion for summary judgment as to count one of its complaint (the parties having stipulated to the dismissal of plaintiff’s counts two and three), and awarding the plaintiff $56,384.66, plus interest. We conclude that summary judgment should not have been granted, and reverse and remand for trial on the merits.

FACTS

On February 18, 1972, the plaintiff, Collins, and defendant, South Dakota State Board of Transportation (Board), entered into a construction contract for base course and asphalt surface treatment of a state highway in Stanley County, South Dakota. In addition to the written provisions in the agreement, the contract expressly included within its terms the Standard Specifications for Roads and Bridges, 1969 Edition, with certain modifications. The contract provided “that the work embraced under this contract shall be completed on or before September 1, 1972 unless such date of completion be set at a later date as is specifically provided for in the specifications. . *493 Collins was granted an extension of ten working days through construction change orders properly executed pursuant to the contract specifications. An additional sixteen working day extension was granted for reasons beyond Collins’ control, which caused it to be unable to complete the work within the time scheduled. 1 Therefore, the date for completion was extended by a total of twenty-six working days from September 1, 1972, to June 8, 1973. The project was not actually completed, however, until July 15, 1974.

On June 11, 1975, Collins initiated the action from which this appeal arises. Count one of the complaint requested $56,-384.66 damages for careless and negligent designation of a non-existent haul road in the contract plans and improper and negligent statements by the Board; count two requested $11,340.00, the amount of liquidated damages assessed against Collins for an overrun of time of eighty-one working days at $140.00 per day; and count three requested $2,400.00 for additional roadway shaping costs for 9.6 miles of road at $250.00 per mile. On October 10, 1975, the Board made a motion for summary judgment, alleging that the applicable statute of limitations barred Collins’ claim. On October 18, 1975, Collins made a motion for summary judgment, stating, in part, that there was no genuine issue as to any material fact, that by waiting over two years to act on Collins’ request for a time extension the Board had waived its right to assert the statute of limitations, and that the statute of limitations had not barred Collins’ claim. On May 11, 1977, Collins and the Board stipulated and agreed that counts two and three of Collins’ complaint would be dismissed in their entirety, pursuant to SDCL 15-6-41(a)(1). 2 The final judgment of the trial court was entered May 11, 1977, denying the motion for summary judgment by the Board, dismissing counts two and three of Collins’ complaint, and granting Collins summary judgment as to count one in the amount of $56,384.66, plus interest. The Board appeals from the judgment.

ISSUES

The following issues are dealt with on appeal:

Issue One — Was Collins’ cause of action against the Board barred by the statute of limitations embodied in SDCL 31-2-37?

Issue Two — Was Collins entitled to summary judgment on count one of its complaint?

DECISION

ISSUE ONE

We conclude that the statute of limitations embodied in SDCL 31-2-37 did not bar Collins’ cause of action against the Board, because the two year time limit had not expired when Gollins initiated action under the contract. SDCL 31-2-37 provides:

Actions against the state of South Dakota authorized under the provisions of § 31-2-34 shall be instituted within two years from the date of the completion of the work as provided under the terms of that particular contract or contracts.

SDCL 31-2-34 3 in pertinent part provides that the state of South Dakota may be sued *494 for claims, rights, and controversies arising out of the work performed, or by virtue of the provisions of any construction contract entered into by the South Dakota Department of Transportation.

The Board contends that the “date of the completion of the work” provided in SDCL 31-2-37 means the specified completion date in the contract, or the specified completion date plus any extensions granted pursuant to the contract specifications. We disagree with this contention. The statute does not say two years from the date on which the contract work is specified to be completed; rather, it says two years from the date of the completion of the work as provided under the terms of that particular contract or contracts. If the legislature had intended the statute of limitations to run from the completion date specified in the contract, it simply would have stated it that way. The words “under the terms of that particular contract” include the whole contract, not just the statement specifying the completion date. The terms of this particular contract define work as follows: “Work shall mean the furnishing of all labor, materials, equipment, and other incidentals necessary to the successful completion of the project.” Standard Specifications for Roads and Bridges, 1969 Edition, § 1.70. The furnishing of all labor, materials, equipment, and other necessary incidentals was not complete in this project until July 15, 1974. Therefore, under the terms of this contract the statute of limitations embodied in SDCL 31-2-37 did not start to run until July 15, 1974, and Collins’ initiation on June 11, 1975, of the cause of action from which this appeal arises was timely.

State v. Wm. O’Neil Sons Co., 209 Minn. 219, 296 N.W. 7 (1941), dealt with the construction of a statute of limitations similar to the one we have before us in the present case. O’Neil involved a contract for construction of an interstate bridge in Minnesota. The contract provided for arbitration of claims or controversies arising out of the contract, and the only issue presented on appeal was whether timely demand for arbitration was made.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
264 N.W.2d 491, 1978 S.D. LEXIS 158, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wm-collins-inc-v-south-dakota-state-board-of-transportation-sd-1978.