Wisconsin Engine Co. v. Altoona Portland Cement Co.

126 P. 1076, 87 Kan. 806, 1912 Kan. LEXIS 246
CourtSupreme Court of Kansas
DecidedOctober 12, 1912
DocketNo. 17,681
StatusPublished

This text of 126 P. 1076 (Wisconsin Engine Co. v. Altoona Portland Cement Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wisconsin Engine Co. v. Altoona Portland Cement Co., 126 P. 1076, 87 Kan. 806, 1912 Kan. LEXIS 246 (kan 1912).

Opinion

The opinion of the court was delivered by

West, J.:

The plaintiff sued to recover an alleged balance of $66,000 of the purchase price for three gas engines built for the defendant. In December, 1907, it contracted to build and furnish three engines of a specified kind in strict accordance with the ■ specifica[807]*807tions attached to and made part of the contract subject to such -changes as were authorized therein. The contractor was to submit detailed drawings of any part of the engine to the defendant’s engineer, Victor Beutner, for criticism and approval, and it was agreed that during the progress of the work the quality, design, material and character of the workmanship should be subject to Beutner’s inspection and approval. The defendant was to furnish the foundations to suit the contractor’s requirement, and all common labor, help and material necessary to the proper erection of the machinery, assuming all responsibility as to the proper depth and size of the foundations. The contractor was to furnish skilled help necessary to supervise the erection and assembling of the engines and the pipe work and to operate the installation “until its success is clearly demonstrated and until the engines are accepted and final payment for the same is approved by the owner’s engineer.”

Each engine was to develop 550 brake horsepower and to operate alternating generators in parallel with each other, the title and right of possession to remain in the plaintiff until final payment should be made. In November, 1909, a supplementary agreement was entered into reciting that “the three engines furnished under the original contract are not performing in a manner as to fulfill the guarantee set forth in the original contract,” and providing that the engine company should, with all possible speed, replace all defectivo parts and proceed with the work in such manner that the first engine should be in perfect condition according to contract not later than January 15, 1910, the second and third not later than March 15, 1910; to maintain until the completion of all permanent changes a sufficient force of mechanics' to make any changes, alterations, and repairs without additional cost to the [808]*808cement company. This supplemental contract contained the following provisions:

“It is further agreed that after all permanent changes in the design and construction have been made upon the first engine the party of the second part shall have the privilege of operating said engine for a term of 45 days, and to notify the party of the first part at any time during these 45 days to run a 72 hour test to ascertain if said engine in its redesigned and reconstructed condition will meet all the stipulations and guarantees of the original ■ contract.
“It is further agreed that if by the result of this test or by the failure of the party'of the second part to have the first engine ready for such test within the stipulated time, or by the ordinary operating conditions, it should be .demonstrated that the terms of1 the original contract have not been fulfilled, the party of the first part shall have the right at his own option to notify the party of the second part to remove each or any of the three units and if the party of the second part fails to comply át once with such notification then the party of the first part shall have the right to remove any or all engines with its own help at the expense of the party of the second part, and the party of the second part ■agrees to remit and refund upon removal of each engine from the foundation of the party of the first part one-third (%) of the sums paid to this date in stock, cash and note, provided however that the party of the first part shall not use the first engine more than two (2) months, the second engine more than four (4) months, and the third engine more than six (6) months, after the test has been demonstrated that the guarantee of the original contract has not been fulfilled.”

The petition alleged that the engines had been furnished in accordance with the contract,- that after each and all of them were completed and in place and in operation they were operated for a period of more than forty-five days, and that during such period (namely, on or about the twentieth day of May, 1910) the plaintiff notified the defendant to run a seventy-two-hour test to ascertain if the engines would meet all stipulations and guarantees in the contract, that the defend-. [809]*809ant declined, refused and neglected to make such tests, and that ever since had been using and was still using the engines for the purpose of operating the plant, the petition being filed June 10, 1910. The second cause of action alleged that the foundations provided for by the defendant were insufficient in that they were not deep enough or large enough to properly hold and support the engines or any of them, whereby the plaintiff was compelled to remove the greater portion of each of the engines from the foundations in order to permit the defendant to make them larger, to plaintiff’s damage of $5000. The answer denied this latter allegation, and by way of cross-petition alleged that the first contract obligated plaintiff to have its engines completed prior to the first day of March, 1909, at which time the defendant was otherwise ready to produce not. less than 1000 barrels of cement a day; that the plaintiff assured the defendant- from time to time prior to November 11, 1909, that the engines would very soon be completed and in condition to operate in accordance with the contract; that on November 11, 1909, a supplemental contract was entered into but that the plaintiff did not have the first engine in perfect condition by January 15, 1910, nor either of the others by March 15, 1910; that it refused to operate such engine or either of them while a seventy-two-hour test was being made; that the engines failed to comply with the terms of the contract in that each failed to develop 550 brake’ horsepower, and that the three would not operate alternating-current generators as contracted for; that they would not operate continuously or successfully but were constantly breaking down or giving way in some of their parts, requiring overhauling or repairing and the stopping of the operation of the plant, and that it had been demonstrated by the ordinary operating conditions that the terms of the contract of December 21,1907, had not been fulfilled; that the engines were unfit for the work desired. After setting out [810]*810various specifications of defective mechanism and operation it was alleged that the defendant, on the 22d day of July, 1910, notified the plaintiff to remove each and all of the engines and that it refused °to accept them. There was a claim for damages but this went out of the case and need not be considered. The reply alleged that the failure to have the first engine in perfect condition by January 15, 1910, was waived by the defendant in that it was orally agreed that in consideration of changing the water connections on the engines their erection and completion within the time specified were to be delayed until such water connections were changed and completed, and that the engines were completed and ih working condition in accordance with the contract and such oral agreement. After a protracted trial the jury returned a verdict in favor of the defendant for $43,556.46.

Special findings were returned to the effect that the plaintiff first offered the defendant the seventy-two-hour test provided for in the contract about May 21, 1910, and the last test about June 22, 1910, at Kansas City, Mo.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
126 P. 1076, 87 Kan. 806, 1912 Kan. LEXIS 246, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wisconsin-engine-co-v-altoona-portland-cement-co-kan-1912.