Wisconsin Builders, Inc. v. General Insurance Co. of America

221 N.W.2d 832, 65 Wis. 2d 91, 1974 Wisc. LEXIS 1245
CourtWisconsin Supreme Court
DecidedOctober 3, 1974
Docket191
StatusPublished
Cited by42 cases

This text of 221 N.W.2d 832 (Wisconsin Builders, Inc. v. General Insurance Co. of America) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wisconsin Builders, Inc. v. General Insurance Co. of America, 221 N.W.2d 832, 65 Wis. 2d 91, 1974 Wisc. LEXIS 1245 (Wis. 1974).

Opinion

Connor T. Hansen, J.

The apartment was being constructed at the foot of a bluff in an “L” shape so that the corner of the bluff bisected the inside angle of the “L.” One wing of the building ran north and south along the west side of the bluff; the other wing ran east and west along the south side of the bluff.

On August 14, 1969, when construction of the apartments had reached the point of installing the interior drywall, the most easterly one third of the east wing of the building located along the south side of the bluff collapsed. By pretrial stipulation, the parties agreed that the policy in question was in full force at the time of the collapse and covered the damage unless one or both of the following exclusions applied:

“V. Exclusions
“This policy does not insure under this form against:
“C. Loss caused by, resulting from, contributed to or aggravated by any of the following:
“1. earth movement, including but not limited to earthquake, volcanic eruption, landslide, mudflow, earth sinking, earth rising or shifting;
“D. Loss caused by or resulting from error, omission or deficiency in design, specifications, ...” 1

The building was commenced in the fall of 1968, at which time the bluff was partially excavated, leaving almost a vertical rise behind the building site. In Decem *95 ber, 1968, work on the project was ordered stopped by the department of industry, labor & human relations because of concern over the safety of people working beneath the vertical cliff. Some 14 feet of driveway adjacent to another apartment complex previously built by plaintiff and located on top of the bluff had broken off and slid down the west side of the bluff toward the north wing of the building in question. Corrective measures were taken by building a telephone pole “crick” in the west bank of the bluff to prevent further erosion and by cutting back the bluff to change the angle of repose. Construction was allowed to recommence early in 1969 and continued without further interruption until the collapse, damaging the other or east wing of the building which is the subject of this litigation.

Between December, 1968, and August, 1969, much concern was expressed about the continuing instability of the bluff, including the south side immediately above that portion of the building which subsequently collapsed. Robert S. Schley, a real estate appraiser hired by the financing bank, West Federal Savings & Loan Association, to monitor the work and make recommendations as to the release of funds for the project, visited the site four times between May, 1969, and the date of the collapse. Each time he reported concern over what he termed “severe bank slippage” on the south slope of the bluff. Schley testified that he repeatedly warned the bank and the plaintiff of this condition and recommended the installation of a retaining wall around the complete bluff. Schley's final report in this regard was made the day of the collapse based on his inspection of the site that morning.

Willard Van Handel of the department of industry, labor & human relations also testified as to large cracks in the top of the bluff, including the area above the building in question, which he observed in his four to five *96 inspections subsequent to December, 1968. While his reports showed no notations of bank slippage, additional terracing and filling was done on the south side of the bluff in May, 1969, at his department’s suggestion.

Witnesses called by the plaintiff testified they did not believe the bluff to be unstable. Leon V. Sniegowski, a loss control representative for the defendant, called adversely by the plaintiff, testified that only fill dirt from the upper parking lot had washed out in December, 1968; that no movement of the original hill had occurred; and that any additional erosion would be controlled by the terracing that was contemplated. He also stated that the distance on top of the bluff from the edge of the south side to the nearest upper apartment building remained a constant 12 feet through June, 1969, the time of his last inspection. Sniegowski saw no slides or cracks in the bluff during his June inspection. Robert D. Trebilcox, president of the plaintiff company, testified that in May and June he saw no severe bank slippage but merely erosion caused by improperly directed water spouts from the apartments on top of the bluff. Kenneth Leathers, plaintiff-company’s superintendent at the building site, corroborated Trebilcox’s testimony.

At the suggestion of the department of industry, labor & human relations, it was decided to do additional filling and terracing of the bluff after that done in May, 1969. The May filling had raised the level of the dirt behind the north wall of the east wing to approximately 10 feet. The building plans called for backfilling to this height. Additional fill was ordered and was brought in on August 13th and 14th to fill the terrace behind or north of the east wing. This fill raised the level behind the wall to 14 feet and the intention was to terrace the fill back up the bluff leaving the level behind the wall at 10' feet. On the two days in question, the fill was being deposited all along the north wall of the east wing by dumping it off *97 the top of the bluff, letting1 it slide down the south side of the hill and then moving it around at the bottom, using a bulldozer. There was testimony that on August 13th the bulldozer was working within six feet of the north wall which subsequently collapsed. The filling continued on August 14th until mid-day when the north wall started tilting. The fill which had been deposited was resting against the building as they had not yet started terracing it back up the bluff.

There were three eyewitnesses to the collapse of the building who testified at the trial. Warren Gollin, secretary of the plaintiff company, stated that he observed cracks in the cement floor of the building at 1:30 p. m. He saw the north wall slowly tilt toward the south, taking five or six hours to fall over. He further stated he saw no earth movement on the bluff before the wall started to tilt, but that the earth fill seemed to follow the wall as it fell over. He saw no cracks or erosion in the bluff before the wall started to tilt. Leathers, the construction superintendent, stated that he saw Allen Wun-derlich, the excavator, dumping fill which created a gradual slope from the top of the bluff down to the north wall. He saw the floor cracks and determined that too much earth pressure was being exerted against the north wall. He called for a backhoe to dig the dirt away from the wall and relieve the pressure. He saw no landslide or earth movement down the bluff but rather described the slow movement of the wall as if a glacier was pushing behind the wall. Leathers went to the top' of the bluff after the collapse and noted that 12 feet of the bluff table had cracked and moved straight down as if it had settled leaving the top soil still intact. Wunderlich, the third eyewitness and the excavator at the site, stated he saw no movement of earth behind the north wall or on the bluff before or as the wall was tipping.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Izrael P. Westbrook v. Daniel L. Jones
Court of Appeals of Wisconsin, 2026
High 5 Sportswear, Inc. v. H5G, LLC
237 F. Supp. 3d 674 (S.D. Ohio, 2017)
BROOM v. WILSON PAVING & EXCAVATING, INC.
2015 OK 19 (Supreme Court of Oklahoma, 2015)
Hankins v. Maryland Casualty Co./Zurich American Insurance Co.
101 So. 3d 645 (Mississippi Supreme Court, 2012)
Willmar Development, LLC v. Illinois National Insurance
726 F. Supp. 2d 1280 (D. Oregon, 2010)
Nautilus Insurance Co. v. Vuk Builders, Inc.
406 F. Supp. 2d 899 (N.D. Illinois, 2005)
Smith v. Katz
595 N.W.2d 345 (Wisconsin Supreme Court, 1999)
Murray v. State Farm Fire & Casualty Co.
509 S.E.2d 1 (West Virginia Supreme Court, 1998)
State Farm Fire & Casualty Co. v. Bongen
925 P.2d 1042 (Alaska Supreme Court, 1996)
Richland Valley Products, Inc. v. St. Paul Fire & Casualty Co.
548 N.W.2d 127 (Court of Appeals of Wisconsin, 1996)
American Motorists Insurance v. R & S Meats, Inc.
526 N.W.2d 791 (Court of Appeals of Wisconsin, 1994)
Qualman v. Bruckmoser
471 N.W.2d 282 (Court of Appeals of Wisconsin, 1991)
American Home Assurance Co. v. Safway Steel Products Co.
743 S.W.2d 693 (Court of Appeals of Texas, 1987)
Gonzalez Ex Rel. Bichler v. City of Franklin
403 N.W.2d 747 (Wisconsin Supreme Court, 1987)
Jones v. St. Paul Insurance Co.
725 S.W.2d 291 (Court of Appeals of Texas, 1987)
United Nuclear Corp. v. Allendale Mutual Insurance
709 P.2d 649 (New Mexico Supreme Court, 1985)
State Farm Mutual Automobile Insurance v. Rechek
370 N.W.2d 787 (Court of Appeals of Wisconsin, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
221 N.W.2d 832, 65 Wis. 2d 91, 1974 Wisc. LEXIS 1245, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wisconsin-builders-inc-v-general-insurance-co-of-america-wis-1974.