Wipro, LLC v. First Data Government Solutions, LP

CourtDistrict Court, D. Nebraska
DecidedSeptember 30, 2025
Docket4:22-cv-03116
StatusUnknown

This text of Wipro, LLC v. First Data Government Solutions, LP (Wipro, LLC v. First Data Government Solutions, LP) is published on Counsel Stack Legal Research, covering District Court, D. Nebraska primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wipro, LLC v. First Data Government Solutions, LP, (D. Neb. 2025).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF NEBRASKA

WIPRO, LLC,

Plaintiff, 4:22CV3116

vs. MEMORANDUM AND ORDER FIRST DATA GOVERNMENT SOLUTIONS, LP,

Defendant.

This matter is before the Court on Defendant’s Motion for Summary Judgment. (Filing No. 110.) For the reasons explained below, the motion will be granted. STATEMENT OF FACTS This action arises out of a 2014 contract executed between Plaintiff and the State of Nebraska. Under the contract, Plaintiff was to serve as the systems integrator to replace the functionality of the State’s Medicaid Eligibility and Enrollment System (“EES”) (the “Project”) with computer software that met certain criteria established by the federal government. (Filing No. 97.) Plaintiff proposed to the State that it would complete all deliverables and work product and bring the EES system live within 12 months, with an initial go-live date of December 2015. (Filing No. 113-4.) When the State awarded Plaintiff the contract, the State agreed to pay Plaintiff approximately $80 million pursuant to a fixed-bid proposal. (Filing No. 113-2.) To obtain federal funding for the Project, the State had to hire an Independent Validation and Verification (“IV&V”) contractor whose role was to provide an independent overview of progress on the Project and report to the State and federal government regarding the progress of the Project. (Filing No. 97.) The State accepted Defendant’s bid to serve as the IV&V contractor. (Filing No. 113-3.) Regina Blazek (“Blazek”) was the project manager for the IV&V team. (Filing No. 97; Filing No. 123.) Between 2014 and 2017, the Project go-live date was extended multiple times. It was extended from December 2015 to September 2016, then to April 2017, then to December 2017. (Filing No. 113-5.) During this period, the contract was also amended three times because more time was needed to complete the work. (Filing No. 113-5.) Dr. Matthew Van Patton (“Director Van Patton”) became the Director of Medicaid and Long-Term Care for the State of Nebraska in February 2018. (Filing No. 113-8.) Director Van Patton testified that he was briefed on the Project and recalled hearing concerns about Plaintiff’s performance from other State employees. (Filing No. 113-8.) Director Van Patton testified that when he became director, he understood that the Project was off schedule. (Filing No. 113-8.) In January 2018, Ruth Vineyard (“Vineyard”), the State’s Deputy Director of Medicaid and Long-Term Care, emailed Nagaraj Bhogshetty (“Bhogshetty”), who was Plaintiff’s Account Delivery Head, about change requests for the Project. (Filing No. 143-25; Filing No. 143-18.) Vineyard’s email mentioned changing the go-live date to February 2, 2019. (Filing No. 143-25.) Around this time, Plaintiff proposed another amendment to the contract (“Amendment 5”). (Filing No. 113-7.) On March 16, 2018, Bhogshetty requested another $7.3 million to complete the proposed Amendment 5. (Filing No. 113-4; Filing No. 113-7.) On March 26, 2018, Bhogshetty sought approval from the State to begin work under Amendment 5, and emailed Vineyard the following: As we discussed, as per current contract (Amendment #3) the DDI phase end date was Dec. 2017 however this has been pushed out to Feb 2019 as per proposed Amendment #5. Based on the change request proposed by the State and [Plaintiff’s] response to it, we have principally agreed to work towards revised Go Live date for NTRAC which is under review and approval by the State (as attached). We continue to work on the change request while we are waiting final approval from [Centers for Medicare & Medicaid Services] and the signed document. Request you to approve the continuation of the work till we get the final signed document. (Filing No. 113-9.) On March 28, 2018, Vineyard emailed Bhogshetty, writing “Nebraska DHHS is working in good faith with [Plaintiff] on an amendment to the existing contract that modifies the project Go Live date to Feb. 2019. In addition, we are working collaboratively to realign the deliverable line items to better represent the current work effort and changes requested by the state. The undated commercial value as proposed is under review by the state and will require CMS approval.” (Filing No. 113-9; Filing No. 143-26.) Vineyard testified at her deposition that she did not give approval for Plaintiff to begin work under Amendment 5 and that she did not have the authority to do so. (Filing No. 113-4.) On or about May 15, 2018, there was a meeting of the Project’s Steering Committee, which was attended by Director Van Patton. (Filing No. 113-10.) Minutes from the meeting reflect that Director Van Patton expressed that “[t]here has to be a firm production plan and schedule that can be managed.” (Filing No. 113-10.) Bo Botelho (“Botelho”), the Chief Operating Officer for the Nebraska Department of Health and Human Services (“DHHS”), testified that following the meeting, the State “put a hold” on all of Plaintiff’s invoices until the State could “figure out what was going on with the Project.” (Filing No. 113-6.) Email correspondence between State employees during this time indicate that Director Van Patton had instructed that Plaintiff’s invoices not be paid until Plaintiff provided “him with the master schedule he has requested.” (Filing No. 113-12.) Director Van Patton testified that if the State was going to agree to another amendment to “a fixed-price bid [contract, for which Plaintiff was] asking for more time,” he needed to be certain as to what exactly Plaintiff required to finish the Project because he “had accountability to Governor Ricketts.” (Filing No. 113-8.) By June 2018, Plaintiff’s initial request for an additional $7.3 million to complete the Project had increased to $12.9 million. (Filing No. 113-6; Filing No. 113-13.) On June 15, 2018, Ashish Kumar (“Kumar”), who was Plaintiff’s General Manager for Health, emailed Cat Gekas- Steeby (“Gekas-Steeby”), who was an Administrator for Policy & Communications with the State, requesting email confirmation to continue work as they sorted through the formalization of Amendment 5. (Filing No. 113-14.) Gekas-Steeby forwarded Kumar’s email internally to Greg Walkin (“Walkin”), an attorney with the State, who responded to Gekas-Steeby’s email, copying Botelho, stating: Hi, Cat, Thanks for the e- mail. They should not be doing any work that is reflected in Amendment 5. Before they can [go and] do any work that is to be reflected in amendment, and before we should even consider paying them for it, we need to give it sufficient scrutiny from our end. Bo [Botelho] wants to be involved and will need to look at the final version . . . Bo [Botelho] wants us to take a very hard look.

(Filing No. 113-14; Filing No. 113-6.) By this point, the go-live date had been moved again from 2019 to April 2020. (Filing No. 113-14.)

Botelho testified that although Plaintiff submitted several iterations of a proposed amendment to the State for review, no one at DHHS had approved Amendment No. 5, nor had it been submitted to the Department of Administrative Services (“DAS”) or the Centers for Medicare & Medicaid Services (“CMS”) for approval. (Filing No. 113-6.) Botelho explained that the process to get an amendment approved required several layers of review. (Filing No. 113-6.) He testified that the draft amendment had to be approved by individuals at DHHS, including himself and Director Van Patton, as well as individuals from DAS. (Filing No. 113-6.) Also, any amendments required CMS approval. (Filing No. 113-6.) Botelho testified that he never approved Amendment 5 and, as of August 14, 2018, the State did not have a final-draft amendment. (Filing No. 113-6.)

On or around July 16, 2018, the State held an internal meeting about the Project. (Filing No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Torgerson v. City of Rochester
643 F.3d 1031 (Eighth Circuit, 2011)
Barber v. C1 Truck Driver Training, LLC
656 F.3d 782 (Eighth Circuit, 2011)
Reimer v. SURGICAL SERV. OF GREAT PLAINS
605 N.W.2d 777 (Nebraska Supreme Court, 2000)
Huff v. Swartz
606 N.W.2d 461 (Nebraska Supreme Court, 2000)
Stahlecker v. Ford Motor Co.
667 N.W.2d 244 (Nebraska Supreme Court, 2003)
American Cable Technologies Services, Inc. v. AT & T Corp.
140 F. Supp. 2d 1026 (W.D. Missouri, 2001)
Steinhausen v. HomeServices of Neb.
289 Neb. 927 (Nebraska Supreme Court, 2015)
Mike Leach v. Craig James, ESPN, Inc. and Spaeth Communications, Inc.
455 S.W.3d 171 (Court of Appeals of Texas, 2014)
Denali Real Estate, LLC v. Denali Custom Builders, Inc.
302 Neb. 984 (Nebraska Supreme Court, 2019)
Summit Restoration v. Keller
29 Neb. Ct. App. 243 (Nebraska Court of Appeals, 2020)

Cite This Page — Counsel Stack

Bluebook (online)
Wipro, LLC v. First Data Government Solutions, LP, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wipro-llc-v-first-data-government-solutions-lp-ned-2025.